Foster v. Swaback

58 Ill. App. 581, 1895 Ill. App. LEXIS 94
CourtAppellate Court of Illinois
DecidedMay 16, 1895
StatusPublished
Cited by4 cases

This text of 58 Ill. App. 581 (Foster v. Swaback) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster v. Swaback, 58 Ill. App. 581, 1895 Ill. App. LEXIS 94 (Ill. Ct. App. 1895).

Opinion

Mr. Justice Shepard

delivered the opinion oe the Court.

This was a bill filed by the appellant, the owner of a certain city lot therein described, for a general settlement under the provisions of Sec. 39, Chap. 82, Rev. Stat. Ill., pertaining to mechanic’s liens.

The bill alleged inter alia, that on November 13,1891, the appellant entered into a contract in writing with one Thomas D. Tansey, whereby the said Tansey agreed to furnish all the material and labor required to erect and complete a three story and basement store and flat building for the appellant upon his said lot, according to certain plans and specifications, and to build and complete the same within one hundred days from said date in a good and workmanlike manner under the direction of the architect, and to the satisfaction of the appellant, for the consideration of $3,000 in money to be paid, and four certain lots, to be conveyed to said Tansey by the appellant.

According to the terms of the said contract, the cash part of the consideration was to be paid in installments, at specified times, and the lots were to be conveyed upon completion and acceptance of the building.

There was no valuation placed upon the lots agreed to be conveyed, and no value or cost of the building so as to be erected, named in the contract.

Tansey, and all persons who furnished labor and materials as sub-contractors in the erection of the building, and who had not been paid, and who claimed anything therefor, either under the statute relating to mechanic’s liens, or otherwise. were made parties defendant to the bill, and most of them, including Tansey, answered, and some of them filed cross-bills.

The cause was referred to a master in chancery, who found and reported that twelve of said defendants furnished under contracts entered into between themselves, severally, and said Tansey, certain labor and materials, and that there remained due to them therefor several sums, exceeding, in the aggregate, the sum of $4,500.

The master also found that “ the building to be erected under said contract could not be built by any contractor, allowing him a reasonable profit, for less than about $8,500;” that the four lots which Tansey had agreed to take did not exceed in value the sum of $1,200; that the appellant paid out to sub-contractors and to Tansey the sum of $3,862.45; and the master, upon the theory and finding by him that appellant, the owner, and Tansey, the contractor, had fraudulently and for the purpose of defrauding sub-contractors, fixed an unreasonably low price in their original contract for the erection of said building, within the provisions of section 29 of the mechanic’s lien act, found and reported that the appellant should pay to the respective defendants, severally, their proportionate share of the difference between the sum of $8,550, which he had as above found to be the cost value of the building, and the sum of $3,862.45, paid by him on account thereof, and recommended that in default thereof the premises of the appellant upon which the building had been erected should be sold to satisfy the same.

The decree of the court followed the master’s report in substance, and so much of it as is pertinent to and explanatory of the main issue involved, is as follows:

“That said Samuel B. Foster and Thomas D. Tansey must have been aware at the time the contract was entered into between them that the building could not be constructed without a loss to the sub-contractors of from $3,000 to $5,000, and the court finds that the case made out by the defendants against said Foster and Tansey in this cause comes within the provisions of section twenty-nine (29), of chapter eighty-two (82), on mechanic’s liens, wherein it is provided that if it shall appear to the court that the owner and contractor fraudulently, for the purpose of defrauding sub-contractors, fixed an unreasonably low price to their original contract for the erection or repairing of such building, then the court shall ascertain how much of a difference exists between a fair price for the labor and material used in said building or other improvement, and the sum named in said original contract, and said difference shall be considered as a part of the contract, and shall be subject to lien.

And the court finds that a fair price for the construction of the building aforesaid, at the date of the construction thereof was eight thousand five hundred dollars ($8,500) in money; that complainant has paid out on said building the sum of three thousand eight hundred and sixty-two dollars and forty-five cents ($3,862.45) leaving a balance of four thousand six hundred and thirty-seven dollars and fifty-five cents ($4,637.55) which should have been paid over by complainant on the date of the filing of the bill herein, and which equitably should bear interest from the date of the master’s report herein at the legal rate.

And the court further finds that although certain lots are mentioned in said contract to be paid for the erection of said building, that the complainant is estopped, as against the sub-contractors herein, by reason of the fraud aforesaid, and as set out in .the master’s report, from claiming the right to have the said lots applied toward the payment of claims made herein. That said lots were worth, at the making of said contract, not to exceed $1,200, and said Foster is estopped to deny that the contract price is payable in money; and the court therefore finds that enough of said balance of $4,637.55, with interest, should be divided among the several parties hereinafter adjudged to be entitled to share therein.”

The decree then proceeds to apportion among the several defendants their respective shares of said balance, and to adjudge to them, respectively, liens upon the premises upon which the building was erected, and to order a sale thereof, if the said balance is not paid by appellant or said Tansey, within a time named.

We omit discussion of the fact that is not disputed, that the largest part of the claims decreed to be liens were never protected by the service of the notice required by the statute, in the assurance that when it becomes important, as it will, to such of the defendants as have served requisite notices, to see that proper attention of the master and court is called to the statutes and decisions upon that subject, as against the other defendants, it will be done.

A bill of this kind is not an appeal to the conscience of the court to do equity, but is a method to ascertain and dispose of purely statutory liens. Under section 39, it is only persons having liens under other provisions of the mechanic’s lien statute, that a decree in favor of can be rendered.

Whether in case of a surplus remaining due from the owner to the contractor, after satisfying all persons having liens, the court, under a bill like the present one, would distribute it upon equitable principles among such persons as were equitably entitled to it, as against the original contractor, is a question not before us.

A discussion bearing upon that question is in Newhall v. Kerstens, 70 Ill. 156, which was a bill, in the nature of a bill of interpleader, filed before section 39 was enacted:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago Bonding & Surety Co. v. United States
261 F. 266 (Seventh Circuit, 1919)
Hudek v. Ennesser
66 Ill. App. 609 (Appellate Court of Illinois, 1896)
Ricardi Apartment House Co. v. Beaudet
64 Ill. App. 261 (Appellate Court of Illinois, 1896)
Jamieson v. Wallace
60 Ill. App. 618 (Appellate Court of Illinois, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
58 Ill. App. 581, 1895 Ill. App. LEXIS 94, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-v-swaback-illappct-1895.