Foster Construction Co. v. Wafer

776 So. 2d 1272, 2000 La. App. LEXIS 3449, 2000 WL 1874098
CourtLouisiana Court of Appeal
DecidedDecember 27, 2000
DocketNo. 00-218
StatusPublished

This text of 776 So. 2d 1272 (Foster Construction Co. v. Wafer) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foster Construction Co. v. Wafer, 776 So. 2d 1272, 2000 La. App. LEXIS 3449, 2000 WL 1874098 (La. Ct. App. 2000).

Opinions

hAMY, Judge.

The plaintiff, a construction company, and the defendant entered into a contract for the construction of a restaurant. The plaintiff contends the defendant failed to honor the contract and seeks out-of-pocket expenses and lost profits. The defendant contends the contract was contingent on his ability to obtain financing. The trial court found in favor of the plaintiff. The defendant appeals. We affirm.

Factual and Procedural Background

This matter involves a contract entered into for the construction of a restaurant in Alexandria, Louisiana. The plaintiff, Foster Construction Company, Inc., alleges that it entered into the contract in which it agreed to construct a restaurant to be called The New Orleans Connection Restaurant for the sum of $199,516.00. Of this figure, $28,008.50 was designated as the company’s overhead and profit. The agreement was signed by Michael D. Foster, the owner of Foster Construction, and the defendant, Otis Wafer. The contract provided that the project would move toward completion “After all Building Permits have been received and upon Notice to Proceed.” A notice to proceed is contained in the record and contains Mr. Wafer’s signature. It is dated September 24, 1997.

Mr. Foster testified that Foster Construction obtained a building permit and did some survey work on the property and began to try to contact Mr. Wafer. He stated that attempts at contact were unsuccessful. Foster Construction filed suit on January 30, 1998, alleging that the defendant had breached the contract by permitting others to begin construction on the project. According to Mr. Foster’s testimony at trial, part of the contract entered [1274]*1274into provided that Foster Construction would remove the existing slab on the proposed restaurant site. He stated that he went to the site, observed that the concrete had been removed, and dirt placed on the property. Suit was filed seeking the profits designated in the contract, $28,008.50.

|p.Mr. Wafer answered the petition and argued that the plaintiff was aware that the contract was conditioned upon the ability to obtain financing and that construction would not proceed if financing was unavailable. He further stated that “Your defendant shows that every financial institution he tendered this project to rejected it and, as of this day, he has no funds for this project.”1 In answering a supplemental petition filed by the plaintiff, Mr. Wafer stated that he did not recall signing a notice to proceed, but he did, however, acknowledge that the signature on the document was his. He stated that he also signed other documents without reading them because he and the Foster Construction representative, John Hammond, had a “relationship built on trust” and that, at the time of signing he understood the condition was subject to his ability to obtain financing. With regard to the removal of the slab, he stated “he had learned that a service station had been built on the location and he demolished the slab and now has doubts as to whether or not a restaurant could have been built on the location even though he was assured by the agent of Foster Construction Company Inc. that the land was suitable for [the] construction of a restaurant.”

Following trial, judgment was entered in favor of Foster Construction. In written reasons for ruling, the trial court explained:

Louisiana Civil Code Article 2765 provides, “the proprietor has a right to cancel at pleasure the bargain he has made, even in case the work has already commenced, by paying the undertaker for the expense and labor already incurred, and such damages as the nature of the case may require.” The Second Circuit in the case of Harrington v. Oliver, 459 So.2d 111 (La.App. 2 Cir.1984), notes the interpretation of this article by Louisiana Courts as follows,
|3The damages which a contractor is entitled to receive in excess of his labor and material cost expended at the time the proprietor terminates the contract are the profits which he would have made had he been permitted to complete the contract. He is to be placed in the same position he would have occupied if he had completed the contract. Forrest and Crocker v. Caldwell and Hickey, 5 La.Ann 220 (1850); Dugue v. Levy, 114 La. 21, 37 So. 995 (1904); Tom Black & Associates v. Thibaut Const. Co., 420 So.2d 1150 (La.App. 5th Cir. 1982).
[[Image here]]
The Court finds from the testimony adduced at trial that the parties agreed upon the submission of a “notice to proceed,” because Wafer did not have his funding situation finalized at the time the parties entered into the contract. The purpose of the “notice to proceed” was to prevent Wafer from being bound to the terms of the contract until funding could be procured. Wafer, a licensed contractor in Jefferson Parish, knew or should have known that the submission of the “notice to proceed” bound him to the terms of the contract.
Accordingly, under the provisions of La.C.C. art. 2765 and its corresponding jurisprudence Wafer is bound to Foster in the amount of $2,262.30 for expenses [1275]*1275incurred,2 and $28,008.58 for lost profits. Defendant is to pay court costs.

(Footnote added.)

The defendant appeals assigning the following as error:

1) The trial judge abused his discretion when he concluded that the defendant’s inability to get financing to fulfill the contract in question was not a valid cause for his not fulfilling the contract and, in fact, constituted an arbitrary rescission of the contract.
2) The trial judge abused his discretion when he awarded to plaintiff the full amount of the profit plaintiff would have received had he completed the contract after concluding that defendant failed to fulfill the contract because he could not get financing.
3) The trial judge erred when he failed to rule that there was a meeting of the minds between plaintiff and defendant in the reduction of the contract in that the contract was in fact reduced from $199,000.00 |4and $99,000.00 and, therefore, loss of profit should have been reduced accordingly.

Discussion

Louisiana Civil Code Article 2765

As seen above, the trial court referenced La. Civ. Code art. 2765 in awarding damages to the plaintiff. Article 2765 provides:

The proprietor has a right to cancel at pleasure the bargain he has made, even in case the work has already been commenced, by paying the undertaker for the expense and labor already incurred, and such damages as the nature of the case may require.

In his first two assignments of error, the defendant contends that Article 2765 permits damages only in the presence of “willful intent to cancel the contract without any legal or rational basis.” For this proposition, he cites Thibodeaux v. Kern, 143 So.2d 422, 425 (La.App. 3 Cir.1962), wherein the court addressed damages under the Article and stated:

The phrase, ‘such damages as the nature of the case may require’, has almost invariably been interpreted to include the ‘loss of profit’ because of the cancellation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wasco, Inc. v. Economic Development Unit, Inc.
461 So. 2d 1055 (Louisiana Court of Appeal, 1984)
GUARANTY SAV. ASSUR. CO. v. Uddo
386 So. 2d 670 (Louisiana Court of Appeal, 1980)
Sonnier v. Boudreaux
673 So. 2d 713 (Louisiana Court of Appeal, 1996)
Harrington v. Oliver
459 So. 2d 111 (Louisiana Court of Appeal, 1984)
Rosbottom v. Office Lounge, Inc.
654 So. 2d 377 (Louisiana Court of Appeal, 1995)
O'NEAL v. Chris Steak House, Inc.
525 So. 2d 325 (Louisiana Court of Appeal, 1988)
Nugent v. Stanley
336 So. 2d 1058 (Louisiana Court of Appeal, 1976)
Osborne v. Ladner
691 So. 2d 1245 (Louisiana Court of Appeal, 1997)
Marcello v. Bussiere
284 So. 2d 892 (Supreme Court of Louisiana, 1973)
Hampton v. Hampton, Inc.
713 So. 2d 1185 (Louisiana Court of Appeal, 1998)
Thibodeaux v. Kern
143 So. 2d 422 (Louisiana Court of Appeal, 1962)
Dugue v. Levy
37 So. 995 (Supreme Court of Louisiana, 1904)
Peterson v. Sutter
4 La. App. 180 (Louisiana Court of Appeal, 1926)
Tom Black & Associates, Inc. v. Thibaut Construction Co.
420 So. 2d 1150 (Louisiana Court of Appeal, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
776 So. 2d 1272, 2000 La. App. LEXIS 3449, 2000 WL 1874098, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foster-construction-co-v-wafer-lactapp-2000.