Foss Launch & Tug Co. v. The Kukui

130 F. Supp. 180, 1955 U.S. Dist. LEXIS 3346
CourtDistrict Court, N.D. California
DecidedApril 1, 1955
DocketNo. 26031
StatusPublished
Cited by4 cases

This text of 130 F. Supp. 180 (Foss Launch & Tug Co. v. The Kukui) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foss Launch & Tug Co. v. The Kukui, 130 F. Supp. 180, 1955 U.S. Dist. LEXIS 3346 (N.D. Cal. 1955).

Opinion

EDWARD P. MURPHY, District Judge.

This is a suit for tug hire and for money expended by libelant in payment to another tug for assisting in the towage. I shall set forth the facts quite generally and then relate them more particularly to the legal issues involved.

On December 7, 1951, Foss Launch & Tug Company entered into a contract of towage with Independent Iron Works, Inc. Foss agreed to provide the tug Martha Foss to tow two of Independent’s barges from Oakland, California to Hawaii. At Honolulu, the Martha Foss was to pick up three tows — The Columbia, the Kukui and the Intrepid, and tow them to Oakland. Independent agreed to pay tow hire in the amount of $750 per day commencing on the pick-up of the tows in Oakland and terminating on delivery at Oakland.

The two barges were picked up at Oakland on the 15th day of December, 1951 and towed to Hawaii without incident. They arrived on January 1, 1952. There was some dispute with the Coast Guard over the master’s license but that was resolved.

The three tows were at Independent’s docks in the Kapalana Basin in Honolulu. They were taken to Pier 2 where the tow was to be made up on January 4, 1952. The tow had been provided with bridles and surge chains by Independent. Captain Hilton, the master of the Martha Foss, suggested certain changes in the towing arrangement. Captain Powers, Independent’s marine supervisor in Honolulu, acquiesced. The changes were completed on January 5, 1952. The weather was bad, so the tug did not depart. The Martha Foss, with the Columbia, Kukui and Intrepid in tow left Honolulu Harbor on January 6, 1952.

On January 10,1952, the Columbia was observed breaking in two. Captain Hilton reeled in the towing hawser but the Columbia was sinking fast and the master ordered the towing hawser burned. The Columbia sank almost immediately. The hawser between the Intrepid and the Kukui severed. Due to the Intrepid’s higher freeboard, it drifted away from the Kukui. The Martha Foss stood by the Kukui and made efforts to retrieve her, finally succeeding in the early morning of January 15th. The Martha towed her to a port of refuge at Kaunakakai on the south side of Molokai Island arriving on the 16th at 1800 hours.

The Coast Guard was keeping track of the Intrepid. Captain Hilton had informed Foss at Seattle of his situation and advised that he could recover only [182]*182one vessel. When Foss communicated with Independent, Foss was told to recover both vessels despite the fact that Foss explained this would be impossible for the Martha. Foss hired Young Brothers to retrieve the Intrepid. The Young Brothers’ tug Miki-Miki picked up the Intrepid and towed her to Kaunakakai.

At Kaunakakai, Captain Hilton was joined by Mr. Campbell, an official in the Foss Company, who had flown from Seattle. They discovered small holes in the bow of the Intrepid at the water line. Sea water was flowing from these holes. Mr. Campbell asked Independent’s representatives to come to Kaunakakai but Independent’s president in Oakland ordered them not to go. He told Foss that Independent had a contract and to bring both vessels.

Captain Hilton decided that the Intrepid was unfit for the tow across the Pacific during that time of year. Young Brothers returned her to Independent at Honolulu. The Martha towed the Kukui to Oakland and delivered her on February 3, 1952.

Respondents contend that the Columbia was lost due to the negligence of the tug master in rearranging the tow setup ; that the tug was unseaworthy as improperly manned, fueled and powered; that libelants breached the towage contract by returning the Intrepid to Honolulu and by failing to deliver the Columbia; and that delay was caused by defects in the master’s license and by the negligent arrangement of the tow which caused the Intrepid and Kukui to come adrift.

These are asserted both as defenses in the answer and are asserted as bases for affirmative relief in the cross-libel.

It is fundamental that a tow-age contract does not constitute a bailment. Stevens v. The White City, 1932, 285 U.S. 195, 52 S.Ct. 347, 76 L.Ed. 699. There is no guarantee that the towed vessel will be delivered. The remedy for failure to deliver must sound in tort. B. Turecamo Towing Corp. v. U. S., 2 Cir., 1942, 125 F.2d 1001. The contract here provides that the loss of a tow will not affect the hire due.

The Delays

The contract provides that in the event of any delay ‘‘arising solely from the fault of Foss and/or the tug, time so lost if in excess of twenty-four hours shall be deducted from charter hire”.

A. Getting Under Way

The Martha had delivered the two tows and was fast at Young Brothers’ pier at 1725 hours on the first of January. Captain Hilton’s license was limited to Pacific Ocean coastwise. He had made several trips to Honolulu and back on this license and it had never been questioned. However, when the Martha arrived the Coast Guard did question his license. This was resolved and on the 4th of January the Coast Guard endorsed his license to make it applicable to any ocean.

It is clear that if this license matter caused any delay it is chargeable to Foss. While reconstructing what might have happened is always difficult, I have carefully examined the log to determine when the Martha could have got underway if the license difficulty had not taken place. The tows were in the same condition on the 1st as they were on the 4th when they were taken to pier 2 to make up the tow. The change in the towing bridles and surge chain is not chargeable to Foss.

It took the Martha four hours to refuel and one working day to transport the tows to pier 2 and get ready for sea. I believe that without the delay regarding the license the tow could have been ready for sea on noon of the 3rd. This requires no work on the 1st and allows the same amount of time for the necessary work as it actually took.

The tow was ready for sea at 1400 hours on the 5th. Departure was delayed by weather, which is not chargeable to Foss. The delay of 50 hours from noon on the 3rd to 1400 hours on the 5th is chargeable to Foss.

[183]*183B. Retrieving the Kukui and Intrepid

The sinking of the Columbia caused the other two tows to be set adrift from the Martha. If the sinking was due to the Martha’s fault, Independent need not pay for the delay in recovering the tows and restarting the tow. As discussed below, no negligence of Foss caused the sinking of the Columbia.

The respondents argue that the change in the towing arrangement made by Captain Hilton caused the Intrepid and Kukui to be severed from the tow, because Captain Hilton’s set-up did not allow for the release of a sinking tow without the release of the other tows. It is not necessary to go into the towing arrangement or the changes made by Captain Hilton. It is clear that the conditions of the sea were such that when the Columbia sank, the tow line would have had to be cut in the manner it was cut, whatever were the towing arrangements. I do not believe that Captain Hilton was negligent in setting up the tow, but it is crystal clear that his arrangement in no way caused or contributed to the Intrepid and Kukui being set adrift.

Seaworthiness

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
130 F. Supp. 180, 1955 U.S. Dist. LEXIS 3346, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foss-launch-tug-co-v-the-kukui-cand-1955.