Forte Construction Corp. v. Distinctive General Contracting LLC

CourtDistrict Court, S.D. New York
DecidedApril 9, 2025
Docket1:24-cv-00727
StatusUnknown

This text of Forte Construction Corp. v. Distinctive General Contracting LLC (Forte Construction Corp. v. Distinctive General Contracting LLC) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forte Construction Corp. v. Distinctive General Contracting LLC, (S.D.N.Y. 2025).

Opinion

UNITED STATES DISTRICT COURT SOUTHERN DISTRICT OF NEW YORK -----------------------------------------------------------------X FORTE CONSTRUCTION CORP.,

Plaintiff, ORDER

-against- 24-CV-727 (ALC) (JW)

DISTINCTIVE GENERAL CONTRACTING LLC d/b/a ADVANCED POLISH SYSTEM,

Defendant. -----------------------------------------------------------------X JENNIFER E. WILLIS, United States Magistrate Judge: The Court is receipt of a joint letter requesting an extension of deposition deadlines and seeking this Court’s intervention on the Parties’ Rule 30(b)(6) topic disputes. Dkt. No. 40. Regarding the Rule 30(b)(6) topics, the joint letter is not identified as a motion to compel nor a motion for a protective order, but merely a request that the Court issue a determination with respect to each of the disputed topics. Id. For ease of disposition, the Court will treat the letter as a pre-motion letter for a protective order seeking to strike deposition topics. One of the attachments to the Parties’ 2-page letter is a 10-page landscape layout document listing out the Parties’ Rule 30(b)(6) disputes and each Party’s position on such disputes. Dkt. No. 40-1. This Court’s individual rules provide that “a party may submit a letter motion no longer than 3 single-spaced pages explaining the nature of the dispute and requesting a conference.” While not expressly prohibited, this Court does not look fondly upon the Parties clear circumvention of the Court’s rules by submitting substantive arguments as an attachment. Nonetheless, the Court rules on each of the disputes in turn. A. Disputes On Rule 30(b)(6) Topics

“Under Federal Rule of Civil Procedure 26, parties may obtain discovery regarding any nonprivileged matter that is relevant to any party's claim or defense.” U.S. Commodity Futures Trading Comm'n v. Parnon Energy Inc., 593 F. App'x 32, 36 (2d Cir. 2014) (summary order) (citing Fed.R.Civ.P. 26(b)(1)) (internal quotation marks omitted). “Relevance to the subject matter under Rule 26 is ‘construed broadly to encompass any matter that bears on, or that reasonably could lead to other matter that could bear on, any issue that is or may be in the case.’” Id. (citing Oppenheimer

Fund, Inc. v. Sanders, 437 U.S. 340, 351, 98 S.Ct. 2380, 57 L.Ed.2d 253 (1978). However, discovery inquiries should be accompanied by objective support rather than mere speculation. See In re Bernard L. Madoff Inv. Sec. LLC, No. 13-CV-4332 (ALC), 2014 WL 1302660, at *7 (S.D.N.Y. Mar. 31, 2014) (finding discovery “is not intended to be a fishing expedition, but rather is meant to allow the parties to flesh out allegations for which they initially have at least a modicum of objective support.”).

i. Forte’s Compensation from the Owner of the Project (Topic Number Three) Defendant Distinctive General Contracting LLC d/b/a Advanced Polish System (“APS”) seeks to depose a Rule 30(b)(6) designee from Plaintiff Forte Construction Corp. (“Forte”) regarding Forte’s compensation, from the owner of the project, for completing the concrete work. Dkt. No. 40-1. Defendant APS argues that this

2 information is relevant because Plaintiff Forte may not have incurred any damages as a result of terminating the subcontract with APS. Id. Plaintiff Forte argues its overall compensation is irrelevant because the proper

measure of its damages is “the delta between the value of the parties’ subcontract and the cost to complete [Defendant APS’s] scope of work.” Dkt. No. 40-1. Plaintiff Forte also notes that the subcontract between Plaintiff Forte and Defendant APS provides that Plaintiff Forte, in the event of Defendant APS termination, is entitled to “the difference between the unpaid balance of the amount to be paid under this SUBCONTRACT and the cost of completing the Work of the Subcontractor[.]” Id. (citing Dkt. No. 40-2 at § 6(A)(3)(i)).

The Court agrees with Plaintiff Forte. The relevant damages calculation here is the difference between the costs of completing the subcontract and the unpaid balance to Defendant APS. Defendant APS’s inquiry of whether Plaintiff Forte incurred any damages will be determined by that difference—not compensation from the owner of the overall project. Thus, the request to strike topic number three is GRANTED as it is not relevant to Plaintiff Forte’s damages under the relevant

subcontract. ii. Surface Solutions’ Bids for the Concrete Finishing (Topic Number Eight) Defendant APS also seeks to depose a Plaintiff Forte designee on the subcontract bids submitted by Defendant APS and the replacement contractor Surface Solutions. Dkt. No. 40-1. Defendant APS argues that the cost of completion increased because, at least in part, the scope of work increased. Id. As a result, 3 Defendant APS argues that the bids submitted by it and the eventual replacement Surface Solutions are discoverable. Id. Plaintiff Forte argues the bids are irrelevant because the subcontracts with

both subcontractors provide that the subcontracts supersede any previous representations. Dkt. No. 40-1. Plaintiff Forte also argues Surface Solutions’ bid is sensitive data that would have been a more appropriate question for Defendant APS’s deposition of the Surface Solutions designee. Id. While it may be true that the signed subcontracts supersede any prior representations, that does not make prior bids irrelevant to Defendant APS’s inquiry into how the potential change to the scope of work affected Plaintiff Forte’s damages.

It is likely that the signed subcontract with Surface Solutions at the time of replacement would vastly vary from any bid submitted prior to the start of Defendant APS’s work. And of course, there is no signed subcontract with Surface Solutions prior to any work because Defendant APS received that subcontract. Without such initial subcontract, any previous bid by Surface Solution, and its scope of work or pricing, is relevant to the comparison with the eventual replacement subcontract.

Thus, the motion to strike topic number eight is DENIED. iii. Forte and APS’s Negotiations (Topic Number Ten) Defendant APS also seeks to depose a Plaintiff Forte designee on their “understanding” of the terms of the subcontract. Dkt. No. 40-1. Defendant APS argues both that the topic is relevant and that Plaintiff Forte cannot make the

4 determination that the subcontract is not ambiguous triggering the integration clause. Id. Plaintiff Forte counters that Defendant APS has failed to identify any

ambiguity in the subcontract’s language. Dkt. No. 40-1. Arguing as a result, its designee’s understanding is irrelevant. Id. The Court agrees with Plaintiff Forte’s objection. The subcontract speaks for itself, and barring an identified ambiguity, Plaintiff Forte designee’s understanding of unambiguous terms is irrelevant. Defendant APS does not identify any ambiguity in the terms of its subcontract with Plaintiff Forte. Thus, the motion to strike topic number ten is GRANTED.

iv. Forte and Surface Solutions’ Negotiations (Topic Number Eleven) Defendant APS seeks to depose a Plaintiff Forte designee on the negotiation of the subcontract between Plaintiff Forte and Surface Solutions. Dkt. 40-1. Like topic number eight, Defendant APS argues that the information sought is relevant and may reveal possible increased scope of work and price in the Surface Solutions subcontract. Id.

Plaintiff Forte argues, in relevant part, any questions regarding the timeline or date of completion are irrelevant. Dkt. No. 40-1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oppenheimer Fund, Inc. v. Sanders
437 U.S. 340 (Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
Forte Construction Corp. v. Distinctive General Contracting LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forte-construction-corp-v-distinctive-general-contracting-llc-nysd-2025.