Fort Chartres & Ivy Landing Drainage & Levee District v. Smalkand

70 Ill. App. 449, 1897 Ill. App. LEXIS 558
CourtAppellate Court of Illinois
DecidedJune 10, 1897
StatusPublished

This text of 70 Ill. App. 449 (Fort Chartres & Ivy Landing Drainage & Levee District v. Smalkand) is published on Counsel Stack Legal Research, covering Appellate Court of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fort Chartres & Ivy Landing Drainage & Levee District v. Smalkand, 70 Ill. App. 449, 1897 Ill. App. LEXIS 558 (Ill. Ct. App. 1897).

Opinion

Mr. Presiding Justice Sample

delivered the opinion of the Court.

The plaintiff in error had a contract with the firm of Schilling & Hank to make some large ditches with a dredge, to cost several thousand dollars. It required a large quantity of water to float the dredge boat, and in order to obtain it Schilling shut down a flood-gate at the mouth of “ Mill Pace Ditch,” without the consent of the commissioners. High waters came, overflowed the lock, and damaged the foundation. Schilling* attempted to open the gate, but, on account of the pressure of the water, or for some other cause, it could not be raised, and thereafter, in the night time, it was blown up by dynamite, by whom, the evidence does not disclose. The firm agreed to restore the gate and lock to its former condition, and for this purpose they entered into a written contract with the defendant in error, drawn up by one of the drainage commissioners, and signed by the parties—the firm and defendant in error—Hovember 12, 1892, which is too long to set out here. The effect of the contract was, first, that the work was to be done under the supervision of the commissioners, or their superintendent; second, that for certain specified work defendant in error was to receive 'the sum of $975; third, he was, further, “ to put in or under or about such lock a good and sufficient concrete * * * and rock * * * about said lock as said commissioners may require to put said lock in as good condition, in their judgment, as it was before the high water of 1892,” and for such concrete work was to receive $6.50 per cubic yard, and was to receive a reasonable price for all the work. Then the kind of material to be used is described and how to be prepared, which was to be subject to the inspection of the commissioners. Fourth, “And said contractor shall be allowed a reasonable price for all extra work not above specified; that is to say, for the extra work of pumping water - * * for bridge work * * * and for repairing the concrete foundation under the pillars or abutments, as the case may be; or for any other extra work said contractor may do or cause to be done under or about said lock.” The commissioners had paid Schilling & Hank over $1,000 for work on the ditches, and held back about $2,800 until they repaired the lock. It appóars that at the time the above contract was made it could not be definitely determined what the condition of the injured lock was, on account of the water, but when that was pumped out, the foundation was found to be so injured that piling had to be driven and a concrete foundation made on them, and also it was determined'to deepen the foundation at one part some two feet. As Schilling could not be present, he requested- Mr. Hardy, one of the commissioners, to look after his interests. The defendant in error began work under his contract with Schilling & Hank, but claims it was soon interrupted by changes made by verbal direction of Hardy, especially as to the piling, which was not specifically mentioned in the contract. He requested a written order, as to the piling, from the commissioners. Thereupon the commissioners entered of record an order, of which a copy was given him, to do said piling so as to make the necessary foundation ‘‘for the new piers to be built by Alphonse Smalkand, under his contract with Schilling & Hank, * * * to repair said lock.” He also claims that the deepening of the foundation some two feet was extra and outside the contract. The items, as presented on his bill for extra work, outside of the contract, were $947.70 for concrete, $423.50 for masonry, $34 for extra work on rip-rap, and $650.50 for piling, and some other items, making a total of $2,915.50. He also did the specified work in the contract, amounting to $975, which was paid, making a total of work $3,890.50. On what he calls extra work, he received from the district $2,000 in bonds, which were discounted $200, which, as he says, the district was to bear, leaving a net payment on the whole extra work of $1,800, making still due him $1,115.50. The payments made by the commissioners were made under a written order of Schilling, of date December 20, 1892, on the commissioners, to pay Smalkand in “ bonds of the district, on account of repairing the Mill Hace Lock, in such amount as said board of commissioners may deem safe and proper on such work, and at such time as they may consider proper, on my account.” Under this order the commissioners paid to. Smalkand $3,000 in bonds for this work, which was more than the balance owing to Schilling & Hank under the original ditch contract. Therefore the commissioners refused to pay Smalkand any more bonds, claiming his contract was with Schilling & Hank, and not with them. Hence this suit. ,

There is no claim that the commissioners made a contract, with Smalkand, and the fact is, no contract was made by. them. The claim is that Hardy, one of the commissioners,: ordered certain work to be done, which is called extra, and that he, and another commissioner, verbally stated the district would pay for it. " The commissioners claim all the work was done under the contract and that they never, promised] verbally or otherwise, to pay for any of it, except to the extent of the balance due Schilling & Hank.

Smalkand obtained a judgment for $1,099.50. The principal contentions are that the judgment is not supported by the evidence; that the yerdict on which it is based was obtained by erroneous instructions, which misled the jury; that under the law the commissioners had no legal right to create such a debt in the manner in which it is claimed this alleged debt was created.

The record has been carefully examined, and without going into an extensive analysis of the evidence in this opinion, suffice it to say that all the work done by Smalkand was under the contract he had with Schilling & Hank, except possibly deepening a part of the foundation, which it is said, owing to the customary way of measuring such-work, did not add to the cost. The terms of the contract between Schilling & Hank and Smalkand show that the concrete and masonry work was included, and when the water was pumped out, the conditions disclosed showed •that it was necessary to drive piling to make a foundation for the concrete. The written order of the commissioners was notice, to Smalkand that, he was doing that piling work under the contract. The contract by its terms covers all extra work necessary to place the lock in its former condition, which was destroyed substantially by Schilling & Hank. All such work, which Smalkand calls extra, is as clearly covered by the contract as the specified work, amounting to $975. The reason that amount was specified was that it was above the water at that time, while much of the other work was not, and therefore could not be specifically agreed upon.

There is no evidence that the commissioners ever, at a meeting or otherwise, agreed to make such repairs at their expense, or had a contract with Smalkand to do the work. The contract referred to sufficiently shows that the district was not to pay for repairing the lock. We a,re unable to find a basis for Smalkand’s claim against the district on the facts.

In addition to this conclusion, if the facts were that the commissioners had made a verbal contract with Smalkand to do the work, there could not, in law, have been a recovery, under the authority of Badger et al. v. Inlet Drainage District, 141 Ill. 540. In that case the district was organized and the assessments made and confirmed in November, 1879.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Badger v. Inlet Drainage District
31 N.E. 170 (Illinois Supreme Court, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
70 Ill. App. 449, 1897 Ill. App. LEXIS 558, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fort-chartres-ivy-landing-drainage-levee-district-v-smalkand-illappct-1897.