Forster v. Fink

407 P.2d 523, 195 Kan. 488, 1965 Kan. LEXIS 425
CourtSupreme Court of Kansas
DecidedNovember 6, 1965
Docket44,196
StatusPublished
Cited by10 cases

This text of 407 P.2d 523 (Forster v. Fink) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forster v. Fink, 407 P.2d 523, 195 Kan. 488, 1965 Kan. LEXIS 425 (kan 1965).

Opinion

The opinion of the court was delivered by

Harman, C.:

Defendant-cross petitioner appeals from an adverse judgment rendered in an action brought by plaintiff for monies due on contract, defendant’s cross petition being one for damages for alleged breach of that contract.

The background of this controversy may be stated thus: Plaintiff *489 manufactures and installs elevator equipment; defendant purchased and commenced operating two elevator buildings at Milan, Kansas, about May 1, 1959. Desiring to enlarge his storage capacity substantially defendant arranged for construction of a new storage steel tank to be completed by June 1, 1959, which construction is not involved in this controversy. On May 18, 1959, plaintiff and defendant entered into a written contract whereby plaintiff undertook to furnish and install a twelve inch screw conveyor eighty-four feet long to extend from the headhouse of one of the old elevators to the top of the new steel tank, its purpose being to convey grain from the smaller to the much larger facility. The contract executed was on a printed form denominated “Purchase Agreement,” with certain blanks filled in, salient parts of which were price, a description of component parts to be furnished by plaintiff with the notation, “No starter or elect, boxes,” the further notation: “Installed except for wiring” and a provision stating “Delivery June 1, 1959.” Rewiring of the elevator electrical system being necessary to handle the new equipment, defendant first attempted to get local third parties to do this but being unsuccessful, on May 28, 1965, entered into an oral contract with plaintiff for plaintiff to do the necessary electrical work. No time was expressly fixed for completion of this work. Plaintiff does not ordinarily do electrical work but accepted this under the circumstances with the understanding, according to plaintiff, that he would do the best he could.

In his petition plaintiff alleged execution of both contracts; that plaintiff furnished material and completed said work under the contracts, defendant thereby becoming indebted to him for $4,080.54, which defendant refused to pay, and plaintiff claimed judgment for that amount.

In his answer and cross-petition defendant admitted the execution-of the written contract and the employment of plaintiff for additional labor and electrical material as alleged and further alleged that time was of the essence and that performance on the part of the plaintiff and installation of all equipment was promised by him by June 1, 1959; defendant further alleged the 1959 wheat harvest in the area of his elevator occurred primarily during the days of June 10 to-June 15 but plaintiff failed to complete and deliver the installation to be made by him for use during said wheat harvest, by reason of which defendant was unable to receive and store grain which he otherwise could have, and his business reputation was damaged, all to his total damage of $28,852.96, for which he prayed judgment-

*490 Plaintiff’s reply and answer to defendant’s answer and cross petition, filed under our former code of civil procedure, consisted of a general denial. With issues thus joined trial was had to the court without a jury in July, 1964, at the conclusion of which the following findings of fact were made:

“1. The Plaintiff was engaged in the business of manufacturing equipment for the operation of grain elevators in the year 1959 and during the month of May, 1959 the Defendant was engaged in the ownership and operation of a grain elevator at Milan, Kansas.
“2. On May 18th, 1959 an instrument in writing, designated as a purchase agreement, was entered into between the Plaintiff and Defendant whereby the Plaintiff was to furnish certain equipment in the construction of certain improvements at the west Milan grain elevator owned by the Defendant. This called for certain equipment manufactured by the Plaintiff, but provided for no electrical boxes or starters, and in said purchase agreement it was provided that delivery date of June 1, 1959 was set forth.
“3. On May 28, 1959 an oral agreement was entered into between Plaintiff .and Defendant for the doing and furnishing of certain labor and materials in the construction of certain electrical improvements,—wiring and installation •of other equipment which was essential to the operation of the machinery •and equipment provided by the written contract. This oral contract for the electrical work provided no time for the doing of the work except to have it done, as the parties understood, as soon as possible and to the best of the ability of the workmen to get the job done.
“4. There was certain work also to be done on the building in the nature of carpentry and strengthening of the wooden structures in the elevator for the carrying of the equipment to be installed. The electrical contract had originally been negotiated with persons other than the Plaintiff which contract was terminated by the parties and was taken over by the Plaintiff and a contract made on May 28, 1959 between Plaintiff and Defendant for that work. Work on the electrical contract began on the date of May 28, 1959 through a checking of the required materials needed for the job by the superintendent of the Plaintiff, and other work was commenced on June 1, 1959 in the electrical and carpentry work.
'“5. The work contracted by the Plaintiff in this action was subject to completion of the building of a storage tank which, according to the evidence, was completed on the 1st or 2nd day of June, 1959. On the 9th day of June, 1959 the conveyor provided for in the written contract was assembled and on June 18th it was installed, or placed in position. On June 20th, 1959 certain electrical equipment, including a starter for the conveyor motor was received and was on that date installed, and on the 21st day of June, 1959 the work was completed on the entire job.
"6. The Court finds that none of the work and material provided by the written contract could be operated, or could be used until the completion of the electrical work for there would be no power transmitted to the conveyor motor.
“7. The Court finds that by the oral contract for the electrical work no time was agreed upon for the completion of the work but it was to be done *491 to the best of the ability of the contractor who was on the job to do the work and furnish the materials.
“8. The Court further finds that any loss occasioned by the Defendant by reason of inability to handle grain during the 1959 wheat harvest was due to no lack of performance on the part of the Plaintiff in the execution of the oral contract, and that no liability arises by reason of any failure in the purchase agreement of the written contract as to the lack of certain electrical equipment, especially a starter, that prevented the placing of the equipment in operation.
“9. The Court finds that by the invoices of the Plaintiff the amount payable on the written contract totals $3185.00, and the amount payable on the oral contract on the electrical invoice is $998.14.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hoffman v. City of Topeka
Court of Appeals of Kansas, 2018
In Re the Marriage of Killman
939 P.2d 970 (Court of Appeals of Kansas, 1997)
Boyle v. Harries
923 P.2d 504 (Court of Appeals of Kansas, 1996)
Reed v. Hess
716 P.2d 555 (Supreme Court of Kansas, 1986)
Kiser v. Gilmore
587 P.2d 911 (Court of Appeals of Kansas, 1978)
Starkovich v. Noye
529 P.2d 698 (Arizona Supreme Court, 1974)
Moore v. Bayless
524 P.2d 721 (Supreme Court of Kansas, 1974)
Lehigh, Inc. v. Stevens
468 P.2d 177 (Supreme Court of Kansas, 1970)
Thompson v. Aetna Life Insurance
440 P.2d 548 (Supreme Court of Kansas, 1968)

Cite This Page — Counsel Stack

Bluebook (online)
407 P.2d 523, 195 Kan. 488, 1965 Kan. LEXIS 425, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forster-v-fink-kan-1965.