Forsgren v. Gillioz

123 F. Supp. 231, 1954 U.S. Dist. LEXIS 2992
CourtDistrict Court, W.D. Arkansas
DecidedJuly 21, 1954
DocketCiv. A. No. 1132
StatusPublished

This text of 123 F. Supp. 231 (Forsgren v. Gillioz) is published on Counsel Stack Legal Research, covering District Court, W.D. Arkansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forsgren v. Gillioz, 123 F. Supp. 231, 1954 U.S. Dist. LEXIS 2992 (W.D. Ark. 1954).

Opinion

JOHN E. MILLER, District Judge.

Statement

Plaintiffs filed their complaint against defendant in the Circuit Court of Miller County, Arkansas, seeking to recover damages resulting from an alleged breach of contract on the part of the defendant.

[232]*232Briefly stated, plaintiffs allege that the defendant had a contract with the Arkansas State Highway Department covering certain highway construction between Van Burén, Arkansas, and Alma, Arkansas, in Crawford County; that they subcontracted to do in its entirety part of the work included in the general contract between defendant and the State; that one of the items of work to be performed was the removing and resetting of shrubs in the approximate quantity of 40; that under the prime contract defendant was to be paid $1 each for removing and resetting said shrubs, while under the subcontract plaintiffs were to be paid $5 per shrub by defendant.

That it developed that it was necessary to remove and reset 5,391 shrubs; that defendant under his prime contract and plaintiffs under their subcontract were both entitled and required to remove and reset said shrubs, regardless of any overrun; that the Arkansas State Highway Department so construed the prime contract and that defendant accepted said construction; that plaintiffs proceeded to commence the removal and resetting of said shrubs but that defendant refused to permit plaintiffs to proceed with the work, and instead proceeded to do the work on his own account, receiving therefor $5,391 under the prime contract.

. Plaintiffs allege that defendant’s actions constituted a breach of the subcontract, and that they are entitled to recover from defendant the sum of $26,-450, less the reasonable cost of removing and resetting 5,290 shrubs. (101 of the 5,391 shrubs were paid for by defendant at the rate of $5 each.) Plaintiffs also allege that defendant is indebted to them in the sum of $1,693.51 for other work done under the subcontract.

On January 18, 1954, the case was removed to the United States District Court, Western District of Arkansas, Texarkana Division.

• The defendant on January 27, 1954, filed an answer containing a general denial of the allegations of plaintiffs’ complaint. On February 11, 1954, defendant filed an amended answer alleging that both the prime contract and the subcontract provided for the removal and resetting of ornamental shrubs in yards along the right of way; that the 5,290 “shrubs” for which plaintiffs seek damages were not in fact shrubs, but were potted plants and other plants located in and near a greenhouse encroaching upon the right of way; that said plants were not removed and reset within the purview of the prime contract or the subcontract.

Defendant further alleges that plaintiffs refused to move said plants and that defendants arranged for and accomplished the moving of the same; that defendant in fact moved 4,818 potted plants and 3,586 other small plants in and around the greenhouse, and was allowed $5,290 as an estimated reasonable allowance for moving said plants, which were not covered by the prime contract or the subcontract.

On April 2,1954, a pre-trial conference was had, and upon motion of plaintiffs the case was transferred from the Texarkana Division of the Western District of Arkansas to the Fort Smith Division of said District.

After the case was transferred, another pre-trial conference was had on May 5, 1954, and it was stipulated that defendant is indebted to plaintiffs in the sum of $1,693.51 for work not connected with the shrubs; that plaintiffs are in possession of a check in said amount issued by defendant, but that plaintiffs have not cashed said check because there appears thereon a statement that it is a settlement in full.

On June 8, 1954, defendant filed a second amended answer, repeating the allegations of his first amended answer, and further alleging that plaintiffs are not entitled to recover damages from him since they first breached the subcontract by failing to provide labor and materials during the course of the work, as required by said subcontract, and therefore cannot urge a breach of contract on his part.

[233]*233Upon the issues as made by the pleadings, the case was tried to the Court, without a jury, on June 14 and 15, 1954, and at the conclusion of the trial the parties were directed to file briefs in support of their respective contentions.

The briefs have been received, and now the Court, having considered the pleadings, ore tenus testimony of the witnesses, depositions, stipulations, exhibits and briefs of the parties, makes and files herein its findings of fact and conclusions of law, separately stated.

Findings of Fact

1.

The plaintiffs are each citizens and residents of the State of Arkansas.

The defendant is a citizen and resident of the State of Missouri.

The amount in controversy, exclusive of interest and costs, exceeds the sum of $3,000.

2.

Sometime prior to September 16, 1950, the State of Arkansas entertained bids for certain highway construction work between Van Burén and Alma, Arkansas, said job being designated as Arkansas State Highway Department Job No. 4333, Crawford County, Arkansas. The defendant and plaintiffs were bidders on the job, and had inspected the job site and the plans and profiles prior to making their bids. Defendant was the successful bidder, while plaintiffs were second low bidders.

The .contract entered into between defendant and the State contained the following relevant provisions:

“Proposal Schedule (Sheet 6)
“Item No. SP-1064-1, Approximate Quantity 40, Each Removing and Resetting Shrubs at One Dollar and No Cents per Each. Unit Price Bid 1.00. Amount Bid 40.00.”
“Special Provision
“ — Removing and Resetting Shrubs — •
“Description: :
“This item shall consist of the removing-and resetting of shrubs, including rose bushes, in accordance with these specifications and at locations shown on the plans or as designated by the Engineer.
“Construction Methods:
“A section of earth of sufficient area and depth to assure the shrub living after it has been reset, shall be removed intact with the roots and body of the shrub. Each shrub shall be reset at a location designated by the Engineer after the location has been properly prepared by grading, loosening of earth, excavating pit, removal of stone or any other unsatisfactory materials, or by any other means necessary to obtain a satisfactory root bed. The shrub shall be carefully set in the new pit and backfill made with suitable material, well tamped and watered, and such other means shall be used in transplanting as are necessary for the continued life and growth of the shrub.
“In removing and resetting, care shall be taken to prevent damage to the shrub and in case any shrub is damaged through carelessness on the part of the Contractor, it shall be replaced by him at his own expense with a shrub equivalent to the one damaged.
“Basis of Payment:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Board of Directors of Carden's Bottom Levee District No. 2
139 S.W. 1136 (Supreme Court of Arkansas, 1911)
S. J. Groves & Sons Co. v. Warren
135 F.2d 264 (D.C. Circuit, 1943)
Drainage District No. 5 or Lonoke County v. Kochtitzky
226 S.W. 172 (Supreme Court of Arkansas, 1920)
Connelly v. Parkes
255 S.W. 22 (Supreme Court of Arkansas, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
123 F. Supp. 231, 1954 U.S. Dist. LEXIS 2992, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forsgren-v-gillioz-arwd-1954.