Forest Oil Corp. v. Tenneco, Inc.

622 F. Supp. 152, 87 Oil & Gas Rep. 302, 1985 U.S. Dist. LEXIS 14297
CourtDistrict Court, S.D. Mississippi
DecidedOctober 31, 1985
DocketJ84-0084(L), E83-0143(L)
StatusPublished
Cited by3 cases

This text of 622 F. Supp. 152 (Forest Oil Corp. v. Tenneco, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Forest Oil Corp. v. Tenneco, Inc., 622 F. Supp. 152, 87 Oil & Gas Rep. 302, 1985 U.S. Dist. LEXIS 14297 (S.D. Miss. 1985).

Opinion

MEMORANDUM OPINION AND ORDER

TOM S. LEE, District Judge.

Before the court are identical motions filed in the above-referenced causes by Tenneco, Inc. (Tenneco) requesting dismissal or stay of further proceedings pending a referral to and decision by the Federal Energy Regulatory Commission (FERC) on *153 certain matters assertedly central to these lawsuits. Plaintiffs Forest Oil Corp. (Forest) and J.E. Stack, Jr. (Stack) filed timely responses in opposition to the motions, and the parties have supplemented their initial memoranda with frequent submissions to the court concerning the present state of the law in this area. After careful consideration of the updated memoranda with attachments submitted by the parties, and for reasons more fully developed below, this court is of the opinion that the above-referenced causes should not be dismissed or stayed pending a determination by the FERC.

These actions allege a breach by Tenneco of individual gas purchase contracts between Tenneco and Forest and Tenneco and Stack. While there are significant differences between the Forest-Tenneco and Stack-Tenneco contracts, for purposes of this motion the pertinent provisions are sufficiently similar to allow this court to make a single determination on both motions.

Forest and Tenneco executed their gas purchase contract on June 1, 1981. Stack and Tenneco executed their gas purchase contract on March 22, 1982. Under the terms of both contracts, Tenneco agreed to buy all of the gas produced by Forest and Stack from wells in certain fields owned by Forest and Stack in Mississippi. The Forest-Tenneco contract was for a term of ten years. The Stack-Tenneco contract was for a term of fifteen years. Both contracts required Tenneco to pay the respective producer for a minimum quantity of gas on an annual basis. If Tenneco’s needs fell below those required in the contracts, Tenneco was required to make a “take-or-pay” payment 1 to the producer for the amount of gas which the producer could have delivered under the terms of the contract. Neither the Forest-Tenneco nor the Stack-Tenneco contract contained an immediately exercisable market-out clause, which is included in many of Tenneco’s contracts with other producers, giving it the right to unilaterally reduce the contract price payable to the producer whenever Tenneco considers it necessary to do so in order to keep its resale price competitive and maintain its profit margin. Such immediately exercisable market-out clauses are the product of negotiation between the parties. 2

In late 1982, Tenneco began experiencing increased deliverability capacity of high-cost gas by some of its producer-suppliers, while at the same time experiencing a reduced demand for the gas it was reselling. In light of this increased supply and diminished demand, Tenneco began exercising its rights under the market-out clauses in the vast majority of its contracts. 3 There remained, however, a number of gas purchase contracts which, like Forest’s and Stack’s, contained no market-out clauses and which obligated Tenneco to high take- or-pay agreements negotiated under different market conditions. Thus, on April 29, 1983, Tenneco announced that it was unilaterally abrogating various provisions of some of its gas purchase contracts, including Forest’s and Stack’s, under the terms of its Emergency Gas Purchase Policy (EGPP). Utilizing this EGPP, Tenneco either suspended or construed in its favor contractual provisions concerning price, deliveries, take-or-pay, nomination of gas cat *154 egories and other related matters. The notices of the implementation of the EGPP that were sent to Forest and Stack contained a further demand that either they accede in writing within one month or Tenneco would terminate their respective contracts. Over the three months following the implementation of the EGPP, some 16 of Tenneco’s approximately 3500 producer-suppliers filed suits against it for breach of contract. On July 14, 1983, Tenneco filed its complaint with the FERC requesting a ruling on the propriety of its EGPP, naming Forest and Stack as respondents in FERC Docket No. 83-109. To date, no action has been taken on this matter by the FERC.

In its instant motions, Tenneco argues that these actions should be dismissed or stayed pending determination by the FERC for the following reasons: (1) the major issues in this litigation are now under review by the FERC; (2) the FERC has plenary jurisdiction over the major issues; (3) the doctrine of primary jurisdiction requires at least a stay of this action. Plaintiffs counter that the substantive claims and defenses in these cases present textbook state law contract disputes concerning inter alia mutual mistake, impossibility and impracticability of performance, failure of consideration, unjust enrichment and lack of mutuality. Furthermore, plaintiffs argue that the FERC cannot have primary jurisdiction over these actions as they concern the sale of deregulated, deep high-cost gas as such is defined in § 601(a)(1) of the Natural Gas Policy Act of 1978, codified at 15 U.S.C. § 3431(a)(1). The overwhelming weight of authority supports plaintiffs’ position.

In Pennzoil Co. v. FERC, 645 F.2d 360 (5th Cir.1981), cert. denied, 454 U.S. 1124, 102 S.Ct. 1000, 71 L.Ed.2d 293 (1982), the Fifth Circuit addressed the issue of the FERC’s primary jurisdiction over contractual disputes arising from the sale of natural gas covered by the Natural Gas Policy Act of 1978 (NGPA). The court held that NGPA § 601(a)(1)(A) removed certain categories of gas sales from the jurisdiction granted to the FERC by the Natural Gas Act, including gas which qualified as high-cost gas under § 107 of the NGPA that was not committed or dedicated to interstate commerce as of November 8, 1978. 645 F.2d at 380. The court further held that the state or federal court which hears a contractual dispute concerning the sale of gas exempted from exclusive FERC jurisdiction by NGPA § 601(a)(1)(A) is competent to interpret and apply any relevant federal regulations without the need to refer all or part of the ease to the FERC. 645 F.2d at 385. This court concludes that the rule announced in Pennzoil disposes of Tenneco’s argument that the FERC has primary jurisdiction over these contract disputes arising from Tenneco’s promulgation of its EGPP. From all that appears in the record before this court, the sale of the gas from the well-heads owned by Forest and Stack falls within the exclusionary language of NGPA § 601(a)(1)(A). Therefore, this court is of the opinion that the FERC has no primary jurisdiction over either of these cases.

Tenneco next argues that even if the FERC is without primary jurisdiction, this court should stay these cases and refer them to the FERC so as to take advantage of the special expertise of the FERC in the area of interstate sale of natural gas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wagner & Brown v. Anr Pipeline Company
837 F.2d 199 (Fifth Circuit, 1988)
Resources Investment Corp. v. Enron Corp.
669 F. Supp. 1038 (D. Colorado, 1987)
Stack v. Tenneco, Inc.
641 F. Supp. 199 (S.D. Mississippi, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
622 F. Supp. 152, 87 Oil & Gas Rep. 302, 1985 U.S. Dist. LEXIS 14297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/forest-oil-corp-v-tenneco-inc-mssd-1985.