Ford v. Whittle Trunk & Bag Co.

12 Tenn. App. 486
CourtCourt of Appeals of Tennessee
DecidedJuly 1, 1931
StatusPublished
Cited by4 cases

This text of 12 Tenn. App. 486 (Ford v. Whittle Trunk & Bag Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ford v. Whittle Trunk & Bag Co., 12 Tenn. App. 486 (Tenn. Ct. App. 1931).

Opinion

PORTRUM, J.

The purpose of this suit was to collect an alleged indebtedness of $4579.46 claimed by the complainants to be due them for electrical equipment installed by them in the manufacturing plant of the defendant, Whittle Trunk & Bag Company, and for work claimed to have been done on said equipment. A recovery was sought for this sum and the declaration of a mechanic’s lien to secure and enforce the same. The complainants allege a special contract with the defendant, Whittle Trunk & Bag Company and Whittle Trunk & Bag Corporation, its successor; they installed, constructed and equipped an electrical system consisting of a generator, switchboard, concrete foundation, and electric motor, and that in the installation of said electrical equipment they reconnected a large generator and switchboard and furnished the necessary materials incident thereto. Boyd Ford and J. E. Shumaker were co-partners doing business in Knoxville, under the name of Armature & Motor Works. They allege the terms of their special contract to be: They were to be paid for the necessary labor and materials which they used in the installation, equipment and rearrangement of said electrical system when said labor was performed and said materials furnished. The bill made no reference to a provision of the contract for the profit of those doing the work, but in the answer to the cross-bill it is said the contract contained the further provision that the compensation was measured by 33-J per cent of the cost of the work and materials furnished. Originally ’there was a contract for a stipulated sum for specified work but it became necessary to amend this contract to provide for additions and alterations found necessary. It was further averred [488]*488that the work was completed, accepted and put into use by the defendant, and the account was due and unpaid.

In the defendant’s answer it admits the execution of the original contract and the supplemental agreement in reference to the changes made necessary by the addition of. motors and the incidental rewiring. But it says the foreman of their plant aiíthorized a rewiring of the building without authority and when the bill for the re-wiring, along with the account under the original contract was presented, the general manager, Mr. Rule, objected to the exces iveness of the account for the re-wiring and also notified the complainants that the work -was done without authority. He then and there notified them to do no more work without his express direction further than complete the job Under the original agreement and its supplement. It is averred that notwithstanding this express direction to the complainants, and after they had asked for the work of re-wiring- the generator and rebuilding the switchboard and had been told to submit a bill or an estimate to determine this cost, so the general manager could determine whether to'permit them to do the work, they failed to submit the estimates but went to the foreman in charge, and represented to him that they had authority from Mr. .Rule to do the work, and told the foreman that it would cost about $800 to re-wire the generator; under this representation, the foreman permitted them to begin work upon the installation of this generator and switchboard in the plant wh,ere they were then completing the original contract and supplement. It is averred that tliey did the work without authority and in a surreptitious manner, and no liability arose on the part of the defendant. Tt is insisted, in the event of liability, that the charges are grossly excessive and that the accounts for supplies are padded, and as a result the profits or percentage upon the cost are greatly increased. At the time the account for the unauthorized re-wiring was presented objection was made to its excessiveness but the account was paid with the understanding that there was to be no work done without express authority from the general manager. The company filed a cross-bill Reeking to surchange and falsify this settlement and purge it of its alleged excessive charges and also to recover for a generator said to have been converted by the partnership. These issues were put at issue by the answer of the partnership.

Upon the main issue the chancellor found in favor of the complainant. The partnership was engaged in rewinding the motor and installing the switchboard over a period of several months, and • during this period the general manager of the corporation was present and in and about the building; the presence of the workmen and their engagement in installing the equipment was apparent. The court held, “ . .he (Rule) was bound [489]*489to have taken notice of the doing of said work and the furnishing of said materials, and that in fact, he knew about it; . . . said materials were furnished and said work done under the eye of the general manager and with his knowledge and consent . . . ”

In reference to the cross-bill the court declined to reopen the settlement made in November for the re-wiring of the house; he granted a recovery for the conversion of the generator in an amount of $75; and as for the excessiveness of the charges, he said: “ . . . under the facts of this case the contract did not authorize a charge by the complainant for overtime and work done on Sunday, and that in order to reach the equities of the ease, the bill of the complainants, 'after the deduction of said sum of $75, the value of said generator thereof, should be further reduced to the extent of five per cent.” He entered judgment in favor of the complainants for the sum of $4,279.24, with interest from the date of the filing of the bill, and declared a mechanic’s lien and ¡ordered the property sold, under terms specified in the decree. From this decree, the defendant has appealed.

The first error'is,-“The chancellor erred in holding and finding that the defendant entered into a contract with the complainants for the doing of the work and furnishing of the materials sued for in this case, and in finding that the general manager of the defendant company knew that said work was being done and said material being furnished.”

Originally there was a special contract entered into by the parties without question. The contract price was specified but it became necessary to do additional work and install additional motors, as for this, it was to be done on a force account basis, that is, cost of the work and materials plus a certain per cent for the contractor. While this work was being done, the foreman directed the complainants to re-wire the building, in order that the wiring would conform to the new arrangement. When the bills for this work were present the first dispute arose. The complainants admit that Mr. Rule countermanded any additional work and expressly directed them to do no work without liis expressed order. They were to do the work at hand, that is, complete the work they had undertaken. -About this time they had a contract to go to Campbell County and remove a generator, which had been used in a coal mine, to the plant of the defendant; it was the purpose of the defendant to electrify its plant and generate its own motor power, since it could do this more cheaply from the refuse of this plant than purchase its electricity from the Knoxville Power & Light Company. The complainants were paid an agreed price for the removal of this generator from Campbell County to the plant in Knox County, but this generator generated voltage of 2200 volts, and in order to use it in the plant it was necessary to do one of [490]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Realty Shop, Inc. v. RR Westminster Holding, Inc.
7 S.W.3d 581 (Court of Appeals of Tennessee, 1999)
Hussmann Refrigeration, Inc. v. South Pittsburg Associates
697 S.W.2d 588 (Court of Appeals of Tennessee, 1985)
Paschall's, Inc. v. Dozier
407 S.W.2d 150 (Tennessee Supreme Court, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
12 Tenn. App. 486, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ford-v-whittle-trunk-bag-co-tennctapp-1931.