Ford Lumber & Manufacturing Co. v. Cornett

188 S.W. 466, 171 Ky. 404, 1916 Ky. LEXIS 371
CourtCourt of Appeals of Kentucky
DecidedOctober 10, 1916
StatusPublished
Cited by6 cases

This text of 188 S.W. 466 (Ford Lumber & Manufacturing Co. v. Cornett) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ford Lumber & Manufacturing Co. v. Cornett, 188 S.W. 466, 171 Ky. 404, 1916 Ky. LEXIS 371 (Ky. Ct. App. 1916).

Opinion

Opinion of the Court by

Judge Thomas

Reversing.

This suit was brought on an open account of Arch Cornett against the defendant corporation (appellant), by which the plaintiff sought to recover from the defendant the sum of $436.89, which, it is charged, is a balance that the defendant owed the plaintiff for goods, wares and merchandise sold and delivered to it during the period from October 30, 1905, to December 23, 1909: Besides the merchandise charged to have been sold and delivered to defendant, there is incorporated into the account various sums due the plaintiff from the defendant growing out of a contract entered into between the parties of date July 3, 1906, whereby the plaintiff, Cor-nett, agreed “to cut and saw into saw logs and place on good, strong skids all the timber owned by the second party (defendant) on the waters of Mason’s Creek and Defeated Creek; skids must be located on roads, or where wagon roads can be made where wagons can g’et to them, and logs placed on skids in-such manner that they can be easily loaded by two men.”

The answer is a denial, and is also made a counterclaim. A recovery was sought to be had therein against the plaintiff because, as is charged, he did not comply with his contract concerning the cutting, sawing and placing of the timber, in that he failed to place a large number of logs “on skids located on roads, or where wagon roads could be made, where wagons can get to them;” and that the defendant was thereby compelled to, and it did, expend $301.17 in skidding and collecting the logs in such places as to enable it to get to them with wagons on that part of the job on Defeated Creek; [406]*406and it spent for the same purpose on the logs to be cut from Mason’s Creek the sum of $225.75. It is furthermore charged by way of counter-claim that the defendant did not complete his contract to cut, saw and locate the logs, as specified, within the time agreed upon, which was “on or before the first day of January, 1907,” and that many of the logs which had been cut in the woods previous to that time became damaged by decay and sun cracks in a total sum of $527.22. Judgment was asked on the counter-claim for these various amounts.

The case is not altogether so hoary as “Jarndyee v. Jarndyce,” but it has been pending sufficiently long for it to have been the first case of the attorneys for the parties and for them to now be qualified, because of their length of practice, to fill the office of circuit judge within this Commonwealth, or that of a member of this court. During its pendency, on motion of defendant, it was referred to the Master Commissioner to take proof and report upon the matters contained in the account of plaintiff, as well as those in the answer and counterclaim of the defendant. The report was filed in which the commissioner allowed the • entire claim of plaintiff, and disallowed all claims of the defendant. To this report the defendant filed exceptions, and upon trial thereof, as well as “upon the whole case,” as is recited in the judgment, the chancellor found the total amount due the plaintiff to be $251.17, instead of the amount sued for, and allowed the defendant on that part of its counter-claim seeking to charge the defendant for failing to properly place the logs, as required by his contract, the sum of $50.00, and gave judgment in favor of plaintiff for the sum of $201.17, and from this judgment the defendant prosecutes this appeal. It may be stated here that since the filing of this transcript in this court the plaintiff, Arch Cornett, has died, but the appeal has been properly revived against his personal representatives, as well as his heirs, it not being necessary, however, that the revivor should have been made against the latter.

Attorneys for appellee insist that this court has no jurisdiction of this appeal, because the judgment is for a sum of money less than five hundred dollars and was granted by the court below, and that under subsection 3, section 950 of Ky. Statutes a motion for appeal in this court is necessary. Counsel, however, overlooked [407]*407the fact that under frequent rulings of this court the amount involved necessary to give this court jurisdiction on appeal is not limited to the judgment recovered, but likewise includes amounts sought to be recovered by way of set-off or counter-claim, and which were denied by the judgment appealed from. Richard v. Goodpaster, 25 Ky. Law Rep., 889; Kefauver v. Kefauver, 26 Ky. Law Rep., 1058; Singer Sewing Machine Co. v. Witt, 26 Ky. Law Rep., 213. The amount involved is not only the judgment which was rendered against appellant, but also the sums for which it prayed judgment against the appellee, and which the lower court dismissed. It is manifest that this contention of appellee’s counsel cannot be upheld. This leaves for consideration only questions of fact.

It is shown by the testimony that the defendant did not, in person, do any of the work imposed upon him by his contract relative to the preparing of the logs, as specified therein. He seems to have sub-let this work to others, and we gather that he had, by the first of January, 1907, when he should have completed the contract under its terms, scarcely made a beginning, and almost the entire work was done during the years 1907 and 1908. In regard to the non-fulfillment of the contract in the respects complained of, with reference to the timber on Defeated Creek, it is admitted by a letter written by plaintiff that his sub-contractors had not placed the logs as required by the contract in these particulars; and that a great number of them were not collected together by plaintiff or his agents in such places as the contract specified. It is, however, furthermore shown that the sums expended by defendant for the collection of these logs were credited by the plaintiff on the account upon which he based his suit. The court, therefore, properly, refused to allow any part of the $301.17 sought to be recovered by the counter-claim for this delinquency.

In regard to the logs on Mason’s Creek, it is shown beyond dispute that the sum sought to be recovered on the counter-claim, expended by defendant because of plaintiff’s failure to comply with the contract, concerning them, was $225.75, but it is insisted that this was unnecessary, and defendant should not be allowed to recover it as against the plaintiff, because, in regard to these logs, plaintiff contends the contract was fully complied with. Upon the issue of compliance with the con[408]*408tract relative to the logs on Mason Creek the testimony is no stronger in favor of plaintiff than it is with reference to the logs on Defeated Creek, and it is conceded that the contract was not complied with in regard to the logs on the latter creek. There is but one witness who testified for plaintiff to the effect that the logs on Mason Creek were properly collected and skidded, as required by the contract, and he admits that he did not collect all of them, as was required by the agreement, but excuses himself because, he says, the defendant, through its agent, informed him that it was unnecessary, and he, therefore, abandoned the job and removed his teams. Three witnesses, who stand unimpeached in this record, state that the logs were scattered promiscuously through the forest, many of them were not collected together at all, and frequently the collections into piles were at such places as that it was impossible to g’et to them with wagons, and that the defendant had to remove jhem to places where they could be put upon the wagons and hauled to the mill, and that it was this work for which the $225.75 was expended.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Warfield Natural Gas Co. v. Maynard
162 S.W.2d 204 (Court of Appeals of Kentucky (pre-1976), 1942)
Ezell v. Ezell
86 S.W.2d 998 (Court of Appeals of Kentucky (pre-1976), 1935)
Schachleiter v. Watson
21 S.W.2d 656 (Court of Appeals of Kentucky (pre-1976), 1929)
Perry Garage v. Combs
299 S.W. 196 (Court of Appeals of Kentucky (pre-1976), 1927)
Chesapeake Ohio Railway Company v. Johnson
291 S.W. 744 (Court of Appeals of Kentucky (pre-1976), 1927)
Caulder v. Elmore
188 S.W. 666 (Court of Appeals of Kentucky, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
188 S.W. 466, 171 Ky. 404, 1916 Ky. LEXIS 371, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ford-lumber-manufacturing-co-v-cornett-kyctapp-1916.