Foos Gas Engine Co. v. Fairview Land & Cattle Co.

185 S.W. 382, 1916 Tex. App. LEXIS 449
CourtCourt of Appeals of Texas
DecidedMarch 15, 1916
DocketNo. 893. [fn*]
StatusPublished
Cited by12 cases

This text of 185 S.W. 382 (Foos Gas Engine Co. v. Fairview Land & Cattle Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Foos Gas Engine Co. v. Fairview Land & Cattle Co., 185 S.W. 382, 1916 Tex. App. LEXIS 449 (Tex. Ct. App. 1916).

Opinion

HENDRICKS, J.

In 1913 the Hickcox-Whyman Engineering Corporation was under contract with the Fairview Land & Cattle Company to drill five certain wells on the property of said Land & Cattle Company, four of which are designated in this record as the “four small wells”; the other as “the large well.” The wells were to be dug in accordance with certain specifications, providing for certain excavations and tanks of certain dimensions, with dykes, with a stipulation in said contract that if the same were not completed within the time specified, $10 per day for delay in the completion of the small wells and $20 per day as to the large well would be paid as liquidated damages by the Engineering Company. The Foos Gas Engine Company, the appellant herein, was a creditor of the Engineering Company to the amount of about $7,000, and sued said company in the district court of Potter county, aiding it with a 'writ of garnishment, served upon the Fairview Land & Cattle CompanjL

The appellee Land & Cattle Company answered by setting up its contract with the Engineering Company that the latter had agreed to construct and equip the four small wells at a cost of $4,400, and a large well at a cost of $3,900, alleging a failure to construct all the wells within the time prescribed, or according to specifications, and that on August 7, 1913, after notice, it declared the contracts at an end, and resumed possession of its lands; that the work done upon the four small wells was not worth over $3,514.34, pleading that it had expended certain amounts and was required to expend a further amount for the completion of said small wells; and that, after deducting the *384 liquidated damages, owing by tbe Engineering Company, ior delay to all the wells, it did not owe said engineering corporation more than $1,513.24, tendering the same into court. The appellee Land & Cattle Company also filed a separate cross-action and enumerated certain parties who were claiming liens upon its property on account of labor performed or material furnished, making them parties to the suit.

There were also several interventions in the case by other parties holding the same character of claims, setting up their alleged liens and praying for a participation in the fund.

We particularly call attention to the intervention of the Amarillo Hardware Company, claiming an indebtedness of $668.51, against the engineering corporation, with interest thereon at the rate of 6 per cent, per annum, based upon a Judgment obtained September 30, 1913, against said corporation, the Hardware Company also alleging that on the 7th day of July, 1913, the defendant engineering corporation executed and delivered to it an assignment and transfer of $3,600, out of any sum due by the Land & Cattle Company, to secure the payment of the account, which thereafter had been merged into the judgment, and a certain note of $3,348.24, dated May 2, 1913, with 10 per cent, interest and 10 per cent, attorney’s fees, alleging the payment of the note, but also claiming the collateral as a continuous security for the payment of the $668.61.

D. It. Hiekcox and one Busby were sureties for the engineering corporation, on the $3,300 note, executed by it, as principal, to the Hardware Company. The total satisfaction to the Hardware Company of said note consisted of a payment of $1,725.19 by Hick-cox; the balance paid by the engineering corporation. Hiekcox also intervened, alleging his previous suretyship on said note, the total satisfaction of same as above stated, and the part payment by him of the $1,-725, and a transfer of said note for the balance paid by him> also setting up the transfer of the well-drilling contract to the Hardware Company as collateral security for the note, and that by his part payment he was subrogated to that company’s rights in the sum paid, with interest.

The case was submitted to the jury upon special issues, who found that the engineering corporation did not substantially construct the four small wells and reservoir in compliance with the written contract, and that these particular wells were received by the appellee on August 7, 1913; that it was necessary for appellee Land & Cattle Company to expend $600, to have the wells and reservoirs substantially conform to the contracts; that the larger well was mutually abandoned on July 1, 1913; that the company, under the contracts (excluding the question of liquidated damages), was indebted to the engineering corporation, for work on the four small wells, in the sum of $3,800; that the Land Company terminated the contract for the larger well on July 1,1913, and answered that said company did not have in its possession any effects of the engineering corporation, but that certain machinery of the value of $1,600 was still upon its lands. The record also shows that the Land Company, on August 7, 1913, wrote the engineering corporation that the latter had breached the contract, declaring the same at an end, stating that it would resume exclusive possession of its premises, and did not waive its right to damages. The Fair-view Land & Cattle Company made a motion for judgment as to the liquidated damages, claiming delay of 83 days of the four small wells in violation of the contract, at $10 per day, aggregating $830, and a delay as to the large well of 21 days, at $20 per day, aggregating $420. The appellant and appel-lee Fair view Land & Cattle Company seem to agree, according to their briefs, that this motion was sustained by the court, which accounts for the judgment against the Land & Cattle Company, in the sum of $2,550, the court deducting $1,250 as liquidated damages.

The appellants’ thirty-first and thirty-second assignments are, in substance, as follows: (1) That the trial court erred in entering judgment for the sum of $2,550, because the jury found that the garnishee owed the engineering corporation, at the time it filed its answer, the sum of $3,800, and that said garnishee had in its possession effects belonging to the engineering corporation of the value of $1,600, as evidenced by the jury’s findings; (2) the court erred in entering judgment in accordance with the motion of the garnishee, and allowing the Land & Cattle Company the offset as liquidated damages, the sum of $10 a day, for the reason that there is no testimony showing that the garnishee suffered any damages on account of the wells not having been completed.

[1] The thirty-fifth assignment complains of the court’s failure to enter a judgment for the full $3,800, as found by the jury, for the reason that it was not shown that the garnishee suffered any actual damages, and because the liquidated damages stipulated in the contract constituted a penalty, and could not be recovered unless actual damages were shown. The proposition under the thirty-first assignment is that the only judgment that could be rendered by the trial court was one in conformity with the verdict rendered upon the special issues submitted to the jury. Both parties agreeing that the judgment of the court for $2,550 against the Land & Cattle Company was the result of a finding by the court of liquidated damages, deducted from the jury’s verdict of $3,800, and a sustaining of appellee Land & Cattle Company’s motion, our consideration is, as affecting these assignments: First, can the liquidated *385 damages be maintained? and, second, did tbe court bave tbe right to make tbe offset?

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Med Center Bank v. Fleetwood
854 S.W.2d 278 (Court of Appeals of Texas, 1993)
Med Center Bank v. M. D. Fleetwood
Court of Appeals of Texas, 1993
L & S Concrete Co. v. Bibler Bros., Inc.
807 S.W.2d 50 (Court of Appeals of Arkansas, 1991)
Branch v. Whitaker
294 S.W.2d 948 (Court of Appeals of Kentucky, 1956)
Ricketts v. Alliance Life Ins. Co.
135 S.W.2d 725 (Court of Appeals of Texas, 1939)
Ramey v. Cage
90 S.W.2d 626 (Court of Appeals of Texas, 1935)
Fowler v. Lee
143 So. 613 (Supreme Court of Florida, 1932)
Shaddix v. National Surety Co.
128 So. 220 (Supreme Court of Alabama, 1930)
San Antonio & A. P. Ry. Co. v. Carpenter
13 S.W.2d 929 (Court of Appeals of Texas, 1929)
Ward Jr. v. Etier
251 S.W. 1028 (Texas Supreme Court, 1923)

Cite This Page — Counsel Stack

Bluebook (online)
185 S.W. 382, 1916 Tex. App. LEXIS 449, Counsel Stack Legal Research, https://law.counselstack.com/opinion/foos-gas-engine-co-v-fairview-land-cattle-co-texapp-1916.