Florida Precast Concrete, Inc. v. City of Orlando (In re Florida Precast Concrete, Inc.)

112 B.R. 451, 1990 Bankr. LEXIS 627
CourtUnited States Bankruptcy Court, M.D. Florida
DecidedMarch 22, 1990
DocketBankruptcy No. 89-0832-8P1; Adv. No. 89-247
StatusPublished

This text of 112 B.R. 451 (Florida Precast Concrete, Inc. v. City of Orlando (In re Florida Precast Concrete, Inc.)) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, M.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Precast Concrete, Inc. v. City of Orlando (In re Florida Precast Concrete, Inc.), 112 B.R. 451, 1990 Bankr. LEXIS 627 (Fla. 1990).

Opinion

FINDINGS OF FACT, CONCLUSIONS OF LAW AND MEMORANDUM OPINION

ALEXANDER L. PASKAY, Chief Judge.

THIS is a Chapter 11 reorganization case and the matter under consideration is an adversary proceeding filed by Florida Precast Concrete, Inc. (Debtor), against the City of Orlando (City), seeking to “compel turnover of property of the estate” [sic] and payment of money due under certain contracts. The claim in Count I of the five-count Complaint is based on an alleged breach of contract by the City and requests an order directing the City to pay the Debt- or all sums remaining due under two construction contracts and change orders. The claim in Count II seeks an order directing the City of Orlando to turn over all sums due under the two agreements pursuant to § 542 of the Bankruptcy Code. The claim in Count III is also based on an alleged breach of contract by the City and seeks payment for services performed post-petition by the Debtor pursuant to the two construction agreements and change orders. The claim in Count IV alleges that the construction work to be performed by the Debtor was delayed and made more difficult by the City; that the insistence and directions of the City to the Debtor which required the Debtor to complete its work within the original time limitations constituted an order to the Debtor to accelerate its work. Based on the foregoing, the Debtor seeks a money judgment for additional costs incurred by the Debtor and [453]*453a reasonable profit for the accelerated work required by the City. The claim in Count V asserts that the City required the Debtor to complete the contract work to a higher degree of completion than was required by the original contract and, therefore, the Debtor claims costs and reasonable profit on account of an “over inspection” by the City of the Debtor’s work.

The City has filed its Answer and also asserted affirmative defenses, along with a five-count Counterclaim. In Count I, the City seeks an order declaring that the re-tainage withheld by the City in the amount of $305,706.67 is not property of the estate and that the City may withhold such retain-age until such time as final completion of the construction project is achieved. The claim in Count II seeks a set-off pursuant to § 553 of the Bankruptcy Code of liquidated damages in the amount of $454,-000.00 against the sums remaining due under the new contracts. The claim in Count III also requests a set-off pursuant to § 553 of the Bankruptcy Code. However, rather than seeking liquidated damages, the City in this Count seeks actual damages in the amount of $514,719.00. The claim in Count IY is a claim for indemnification from the Debtor for damages allegedly caused by the Debtor’s delay in completion of the construction contracts and interference and obstruction of the work of other contractors in the amount of $514,-759.00. Finally, the claim in Count V seeks adequate protection for the City’s interest in a one-year warranty of the work performed by the Debtor.

The facts as established at the final evi-dentiary hearing which are relevant and germane to the disposition of this cause are as follows:

The Debtor is a contractor engaged in the business of the manufacture and erection of architectural precast concrete panels and other concrete pieces used in large commercial construction projects.

On February 8, 1989, the Debtor filed a voluntary Petition for Relief under Chapter 11 of the Bankruptcy Code. Prior to the filing of the Petition, the Debtor entered into two contracts with the City to perform certain work on a project known as “The Orlando Arena”.

The first contract was entered into on March 25,1988. (Debtor’s Exh. P-1). This contract, referred to as “Bid Package 54”, required the Debtor to manufacture and erect certain architectural precast panels to form a portion of the outside skin of the Orlando Arena. In addition, the Debtor was to provide architectural precast pieces formed to fit over poured-in-place concrete. These pieces are used to form a wall which accommodates seating in the outside areas and are known as “seat walls”. The second contract, known as “Bid Package 60” was dated October 17, 1988, and required the Debtor to provide architectural precast concrete stairs (Plaintiff’s Exh. P-2).

The City also contracted with Gilbane Building Company (Gilbane) to act as construction manager for the Orlando Arena Project. The City acted as an owner-builder and contracted with numerous other contractors to build various portions of the Arena Project. Although the names and functions of all of the individual contractors were not put in evidence, it is clear that there was a roofer, a glass block contractor, a contractor to pour the cement for the foundation for the stairs, a contractor to pour concrete in the landscaping area, a sheetrock contractor, and an electrical contractor. It appears that there were approximately thirty contractors involved in the project.

As noted, Gilbane acted as construction manager and the Debtor’s point of contact with the City during construction. The Debtor and the City had very little direct contact during the construction until some time after the opening of the Orlando Arena on January 29,1989, and the Debtor and the City did have substantial contacts during the “close-out” phase of the project in the form of negotiations between Mr. Charles, a consultant employed by the Debtor and Mr. Kotzin, an employee of the City’s Bureau of Construction Management, who acted as a liaison between City Hall and Gilbane.

The Debtor claims that the City owes it unpaid contract balances under both con[454]*454tracts and additional sums for extra work performed pursuant to change orders. The Debtor also claims that the City required the Debtor to perform additional services after substantial completion of the contract to repair damage caused by other contractors on the job.

In opposition, the City asserts that the Debtor is liable for liquidated damages for failure to meet the substantial completion deadline required in Bid Package 54. In addition, the City alleges that the Debtor delayed other contractors in completing their portions of the construction and, therefore, the City was required to pay additional monies to those contractors. Although the City initially asserted that the Debtor was liable for liquidated damages under Bid Package 60, counsel for the City announced in open court that this claim would be withdrawn and that the City would not offer any proof as to that issue.

The original contract price for Bid Package 54 was $2,000,000.00. The City paid $1,782,761.04, leaving a balance due under the original contract of $217,238.96. As to Bid Package 60, the original contract amount was $747,000.00, which was increased by Change Order No. 1 in the amount of $314,000.00, for a total revised contract amount of $1,061,000.00. The City paid $954,900.00 and the remaining balance due is $106,000.00. In addition, the City also required the Debtor to perform additional work to prepare a ramp to receive precast panels and caps. The evidence presented at trial clearly shows that the amount due for performance of this additional work is $4,185.08. (Debtor’s Exh. P-379). The City further requested the Debtor to fabricate four additional precast panels which were not required by the original contract. The Debtor complied and claims an additional sum of $1,876.00 for delivery of these panels.

Under Bid Package 60, the Debtor was also required to perform additional work and provide additional materials not contemplated by the contract in four separate and distinct areas.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hyman v. Cohen
73 So. 2d 393 (Supreme Court of Florida, 1954)
Pembroke v. Caudill
37 So. 2d 538 (Supreme Court of Florida, 1948)

Cite This Page — Counsel Stack

Bluebook (online)
112 B.R. 451, 1990 Bankr. LEXIS 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-precast-concrete-inc-v-city-of-orlando-in-re-florida-precast-flmb-1990.