FLORIDA POWER & LIGHT COMPANY v. HEYDI VELEZ

CourtDistrict Court of Appeal of Florida
DecidedMarch 22, 2023
Docket22-0181
StatusPublished

This text of FLORIDA POWER & LIGHT COMPANY v. HEYDI VELEZ (FLORIDA POWER & LIGHT COMPANY v. HEYDI VELEZ) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FLORIDA POWER & LIGHT COMPANY v. HEYDI VELEZ, (Fla. Ct. App. 2023).

Opinion

Third District Court of Appeal State of Florida

Opinion filed March 22, 2023. Not final until disposition of timely filed motion for rehearing.

________________

No. 3D22-181 Lower Tribunal No. 17-22854 ________________

Florida Power & Light Company, Appellant,

vs.

Heydi Velez, et al., Appellees.

An Appeal from a non-final order from the Circuit Court for Miami-Dade County, David C. Miller, Judge.

Squire Patton Boggs (US), LLP, Alvin B. Davis and Digna B. French; Joseph Ianno, Jr. (Juno Beach); Boies, Schiller & Flexner, LLP, Stuart H. Singer, Sashi C. Bach, and Pascual Oliu (Ft. Lauderdale), for appellant.

Armas Bertran Zincone and J. Alfredo Armas; MSP Recovery Law Firm, John H. Ruiz and Alexis Fernandez; Acosta Law Firm, Julio C. Acosta and Simeon Genadiev; Dorta Law and Gonzalo R. Dorta, for appellees.

Before FERNANDEZ, C.J., and LINDSEY, and HENDON, JJ.

FERNANDEZ, C.J. Florida Power & Light Company (“FPL”) appeals the trial court’s non-

final order certifying a class of FPL customers who sued FPL for breach of

contract and gross negligence after Hurricane Irma. Because the trial court

correctly determined that plaintiffs satisfied the elements necessary to

establish class treatment of their claims against FPL under Florida Rule of

Civil Procedure 1.220(b)(3), we affirm.

FACTS AND PROCEDURAL BACKGROUND

In 2005, FPL filed a base rate proceeding before the Public Service

Commission (“PSC”). The parties reached a Settlement Agreement whereby

FPL would be allowed to recover storm restoration costs and replenish its

Storm-Recovery Reserve through the monthly storm surcharge.

Thereafter, FPL customers were affected by Hurricanes Dennis,

Katrina, Rita, and Wilma. FPL petitioned the PSC to approve the issuance

of storm recovery bonds pursuant to section 366.8260, Florida Statutes

(2005). The bonds would allow FPL to recover over $213 million and $815

million for 2004 and 2005 storm costs; replenish its storm-recovery reserve

to a level of approximately $650 million; and recover interest incurred

through the bond issuance date and bond issuance costs of $23 million. As

a result of the bonds, FPL customers would have to pay a monthly storm

2 surcharge. In return, FPL was to improve and strengthen its facilities for

future storms, remove decaying utility poles, and remove vegetation that was

making contact with local power lines.

During hearings the PSC scheduled on the bond issue, FPL stated the

storm charge would be used for, among other things, restoring FPL’s

facilities to their pre-storm condition; repairing and replacing poles that were

leaning or were braced during the initial restoration stage; replacing lightning

arrestors; repairing or replacing capacitor banks; and strengthening system

infrastructure. FPL’s Storm Secure Plan further would adopt the National

Electric Safety Code (“NESC”) to improve FPL’s system infrastructure to

withstand extreme wind conditions. The PSC approved the order and the

issuance of the storm-recovery bonds in the amount up to $708 million.

Later, in 2012, FPL petitioned for a permanent increase in base rates

and charges. It requested a base rate increase of $528 million. A Settlement

Agreement was reached, and the PSC gave FPL a revenue increase of $378

million effective January 1, 2013.

In 2016, FPL requested another base rate increase. FPL's request was

intended to "reduce outages and enable FPL to restore power for customers

and help local communities recover more quickly when severe weather

strikes." The PSC authorized a revenue increase of $400 million effective

3 January 1, 2017. Also in 2016, FPL filed a petition seeking to implement a

storm surcharge to recover $318.5 million for Hurricane Matthew restoration

costs and to replenish its Storm-Recovery Reserve. The PSC granted FPL's

2017 storm surcharge on each customer’s monthly residential bill, beginning

on March 1, 2017, which was to last for twelve months.

On March 15, 2016, FPL filed its petition with the PSC for approval of

FPL’s Storm Hardening Plan. FPL stated it would comply with NESC

extreme wind loading (“EWL”) standards by hardening its system so that it

would withstand winds of 145, 130, and 105 mph in the three different wind

regions of the state.

In September 2017, Hurricane Irma sideswiped Florida. Named class

members Heydi Velez, Miriam Perez, Guillermo Patino-Hidalgo, Enrique

Arguelles, Mercedes Sastre, Ruben N. Mendiola, Carlos M. Colina, Shalom

Navarro, and Jose Zarruk (collectively, “plaintiffs”) were FPL customers

whose power went out for an extended period after Hurricane Irma. As

customers, they entered into a contract with FPL, the Tariff, for electrical

services that set out the parties’ obligations. In the Tariff, FPL agreed to use

“reasonable diligence at all times to provide continuous service and storm

recovery activities.”

4 During Hurricane Irma, the very highest sustained wind recorded by

the National Weather Service was 115 mph in Marco Island where the storm

first made land fall. The highest gust recorded was 142 mph near Naples

Airport. Although Irma did not approach any county east of Lake

Okeechobee, over 75% of FPL customers in South Florida lost power for

close to a week. In the western half of South Florida, over 90% of FPL

customers lost power for over a week.

On February 1, 2018, plaintiffs brought a class action lawsuit against

FPL. They alleged one count for breach of contract seeking compensatory

damages for FPL’s failure to comply with its contractual obligations to use

reasonable diligence at all times to provide continuous service in accordance

with FPL’s Tariff and industry standards. Plaintiffs alleged that each of the

individual plaintiffs entered into a uniform contractual agreement with FPL

for services (the Tariff), for which plaintiffs paid a monthly fee. They alleged

each plaintiff was individually charged a surcharge for storm restoration and

hardening activities, pursuant to section 366.8260, Florida Statutes (2017).

Plaintiffs suffered consequential damages such as loss of food and incurred

expenses, loss of income, loss of sleep, intense discomfort, and more.

The Tariff specifically stated that FPL “will use reasonable diligence at

all times to provide continuous service at the agreed nominal voltage” and

5 storm recovery activities. Plaintiffs claim that FPL failed to use reasonable

diligence by failing to meet NESC standards and its own standards, and that

as a result of FPL’s breaches, Florida residents suffered unnecessary and

prolonged power outages from Hurricane Irma that sideswiped South

Florida.

In Count II for gross negligence, plaintiffs claimed FPL “acted with

reckless, willful, and wanton disregard for plaintiffs in the gross negligent

maintenance and management of its system infrastructure, storm

organization, restoration plan, and outright failure to restore, replace, and

better the distribution system and hazards posed by vegetation and trees

close to power lines.” They alleged FPL became aware of this need after

previous storms hit Florida and undertook a duty to strengthen its distribution

system in anticipation of the next hurricane. Plaintiffs further alleged that FPL

was grossly negligent in performing various actions such as in replacing

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Broin v. Philip Morris Companies, Inc.
641 So. 2d 888 (District Court of Appeal of Florida, 1994)
InPhyNet Contracting Services, Inc. v. Soria
33 So. 3d 766 (District Court of Appeal of Florida, 2010)
Canakaris v. Canakaris
382 So. 2d 1197 (Supreme Court of Florida, 1980)
Freedom Life Ins. Co. of America v. Wallant
891 So. 2d 1109 (District Court of Appeal of Florida, 2004)
Love v. General Development Corp.
555 So. 2d 397 (District Court of Appeal of Florida, 1989)
TERRY L. BRAUN, PA v. Campbell
827 So. 2d 261 (District Court of Appeal of Florida, 2002)
Paladino v. American Dental Plan, Inc.
697 So. 2d 897 (District Court of Appeal of Florida, 1997)
Sosa v. SAFEWAY PREMIUM FINANCE CO.
73 So. 3d 91 (Supreme Court of Florida, 2011)
Florida Power & Light Co. v. Velez
257 So. 3d 1176 (District Court of Appeal of Florida, 2018)
Miami Automotive Retail, Inc. v. Baldwin
97 So. 3d 846 (District Court of Appeal of Florida, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
FLORIDA POWER & LIGHT COMPANY v. HEYDI VELEZ, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-light-company-v-heydi-velez-fladistctapp-2023.