Florida Power Corp. v. First Energy Corp.

54 F. Supp. 3d 860, 2014 U.S. Dist. LEXIS 145441, 2014 WL 5112787
CourtDistrict Court, N.D. Ohio
DecidedOctober 10, 2014
DocketCase No. 1:12 CV 1839
StatusPublished

This text of 54 F. Supp. 3d 860 (Florida Power Corp. v. First Energy Corp.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Power Corp. v. First Energy Corp., 54 F. Supp. 3d 860, 2014 U.S. Dist. LEXIS 145441, 2014 WL 5112787 (N.D. Ohio 2014).

Opinion

OPINION AND ORDER

DAN AARON POLSTER, District Judge.

I. Factual Background

Plaintiff Florida Power Corporation d/b/a Progress Energy Florida, Inc., (“Progress Energy”) brought this action under the Comprehensive Environmental Response, Compensation, and Liability Act (“CERCLA”), 94 Stat. 2767, 42 U.S.C. §§ 9601-9675, to recover cleanup costs it has incurred in connection with the release of hazardous substances on property located in Orlando and Sanford, Florida (together the “Sites”, individually the “Orlando Site” or “Sanford Site”). Progress Energy did not own the Sites when the hazardous substances were released, nor did it release the hazardous substances. Nonetheless, as a former owner of the Sites it is a “Potentially Responsible Party” (“PRP”) and is therefore responsible for the cleanup costs under CERCLA. Progress Energy can, however, recoup those costs from other PRPs, including parties who, at the time hazardous material substances were released, owned either the Orlando Site or the Sanford Site. Progress Energy alleges that Defendant First Energy Corp. (“First Energy”) is such a party.

First Energy, which is the corporate successor to the Associated Gas & Electric Company (“AGECO”), did not own either the Orlando Site or the Sanford Site when the hazardous materials were released. Rather, from 1924 until 1943, the Florida Public Service Company (“FPSC”) owned the Orlando Site and, from 1932 until 1943, Sanford Gas Company (“Sanford Gas”) owned the Sanford Site. Both the FPSC and Sanford Gas owned and operated a manufactured-gas plant at the respective Sites, during which they released hazardous substances. AGECO’s connection to Sanford Gas is relatively direct; Plaintiff alleges that in 1930 AGECO acquired Sanford Gas. AGECO’s connection to FPSC is more complex. At the time that FPSC owned the Orlando Site, FPSC was a sub- ■ sidiary of General Gas & Electric Corpora[862]*862tion (“General Gas”). General Gas, in turn, was a subsidiary of Associated Gas & Electric Corporation, which was itself a subsidiary of AGECO, the predecessor company of Defendant First Energy. Progress Energy alleges that AGECO’s officers and directors persistently disregarded the corporate form, exercising complete dominance and control over FPSC and Sanford Gas. Plaintiff therefore seeks to pierce the corporate veil and hold AGECO responsible for FPSC and Sanford Gas.

On December 5, 2012, First Energy filed a Motion for Judgment on the Pleadings pursuant to Fed.R.Civ.P. 12(c) on two grounds (“Motion for Judgment on the Pleadings”) (Doc. # 56). First, First Energy argued that Progress Energy did not properly allege facts to support its veil piercing theory, and second, First Energy argued that even if Progress Energy had done so, its claims under CERCLA were barred by the applicable statute of limitations. On March 18, 2013, this Court issued an Opinion and Order (“March 18 Order”) denying the motion on both grounds (Doc. # 59).1 Now, First Energy has filed a Motion for Reconsideration asking the Court to reconsider its ruling that Progress Energy’s claims are not barred by the applicable statute of limitations (Doc. # 84).

II. Law & Analysis

While a motion for reconsideration is not mentioned in the Federal Rules of Civil Procedure, it is typically treated as a motion to alter or amend the judgment under Fed.R.Civ.P. 59(e). U.S. v. Rohner, 2014 WL 4809454, *1 (N.D.Ohio Sept. 26, 2014) (citations omitted). “Generally, there are three major situation which justify a court reconsidering one of its orders: (1) an intervening change in controlling law; (2) the availability of new evidence; and (3) the need to correct clear error or to prevent manifest injustice.” Id. (citation and internal quotation omitted).

Here, First Energy’s Motion for Reconsideration is based upon the Sixth Circuit’s decision in Hobart Corporation v. Waste Management of Ohio, Inc., 758 F.3d 757 (6th Cir.2014). According to First Energy, Hobart is “new and binding Sixth Circuit precedent” and is therefore “an intervening change in controlling law.” The Court agrees.

The question of whether or not a PRP’s action to recover cleanup costs from other PRPs is time-barred under CERCLA depends on what kind of action a PRP is bringing. As the Court explained in its March 18 Order, the statute of limitations under CERCLA depends upon whether a PRP is bringing a cost-recovery action pursuant to § 107(a)(4)(B), 42 U.S.C. § 9607(a)(4)(B), or a contribution action pursuant to § 113(f), 42 U.S.C. § 9613(f):

CERCLA provides two avenues through which private parties may recoup expenses associated with cleaning up contaminated sites. One is a cost-[863]*863recovery action. 42 U.S.C. § 9607(a). The other is a contribution action. 42 U.S.C. § 9613(f). These two remedies complement each other but apply to parties in different procedural circumstances. United States v. Atl. Research Corp., 551 U.S. 128, 139 [127 S.Ct. 2331, 168 L.Ed.2d 28] (2007). A cost-recovery action is the way a party recovers cleanup costs it has voluntarily incurred. Id. A contribution action, by contrast, is the way a party seeks reimbursement for money it has paid to other parties to satisfy a settlement agreement or court judgment. Id.
The statute of limitations for a contribution action is straightforward. Such action must be commenced within three years of the “entry of a judicially approved settlement with respect to such costs or damages.” 42 U.S.C. § 9613(g)(3). A consent decree constitutes a judicially approved settlement. RSR Corp. v. Commercial Metals Co., 496 F.3d 552, 556 (6th Cir.2007).
The statute of limitations for cost-recovery actions is slightly more complex. There are two types of cost-recovery actions: removal and remedial. In essence, a removal action is taken to prevent or temporarily correct an immediate threat and is intended to be a short-term solution. 2 SupeRfund & BROWNFIELDS CLEANUP § 17:1 (2012). The Sixth Circuit has held that a remedial investigation/feasibility study is a type of removal action. Kelley v. E.I. DuPont De Nemours & Co., 17 F.3d 836, 840 (6th Cir.1994). A remedial action is a longer-term or permanent solution. 2 Superfund & Brownfields Cleanup § 17:1 (2012).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Atlantic Research Corp.
551 U.S. 128 (Supreme Court, 2007)
ITT Industries, Inc. v. BorgWarner, Inc.
506 F.3d 452 (Sixth Circuit, 2007)
Hobart Corp. v. Waste Management of Ohio, Inc.
758 F.3d 757 (Sixth Circuit, 2014)
Kelley v. E.I. DuPont de Nemours & Co.
17 F.3d 836 (Sixth Circuit, 1994)
RSR Corp. v. Commercial Metals Co.
496 F.3d 552 (Sixth Circuit, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
54 F. Supp. 3d 860, 2014 U.S. Dist. LEXIS 145441, 2014 WL 5112787, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-power-corp-v-first-energy-corp-ohnd-2014.