Florida Department of Insurance v. Centex-Great Southwest Corp.

639 So. 2d 646, 1994 Fla. App. LEXIS 6519
CourtDistrict Court of Appeal of Florida
DecidedJuly 5, 1994
DocketNos. 93-761, 93-958 and 93-1941
StatusPublished

This text of 639 So. 2d 646 (Florida Department of Insurance v. Centex-Great Southwest Corp.) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Florida Department of Insurance v. Centex-Great Southwest Corp., 639 So. 2d 646, 1994 Fla. App. LEXIS 6519 (Fla. Ct. App. 1994).

Opinion

DAVIS, Judge.

The Florida Department of Insurance, as receiver for Southeastern Reinsurance Company, Inc. and Southeastern Casualty and Indemnity Insurance Company, Inc. appeals the trial court’s order on claim of right filed by Centex-Great Southwest Corporation (“GSW”) as that order was modified by order on the receiver’s motion for rehearing, and an order on the receiver’s motion to tax costs and assess attorney’s fees. This case arises [648]*648out of a demand by the receiver pursuant to section 631.154, Florida Statutes, for return of funds of the receivership estate, which funds were being held by GSW. The trial court awarded GSW certain sums which GSW claimed as set-offs from funds belonging to the receivership estate. On appeal, the receiver challenges the trial court’s finding that GSW had a claim of right to funds claimed by GSW as set-offs and the court’s award of statutory prejudgment interest on the set-off funds. The receiver also asserts as error the trial court’s failure to award the receiver full reimbursement for the costs of collection of the receivership funds. GSW cross-appeals and asserts that the trial court lacked subject matter jurisdiction, under section 631.154, over the dispute between the receiver and GSW, a claimant in the receivership, as to the receiver’s entitlement to payment of funds assigned to its predecessor and the amount of set-off to which GSW was entitled. GSW also cross-appeals the partial summary judgment holding that GSW’s parent corporation’s claims could not be set-off against funds due and owing from GSW. Because we find that the trial court erred in awarding statutory interest on the set-off in the course of a receivership proceeding conducted under Chapter 631, we reverse that award. Because we find a lack of evidence to support the set-off of $29,516.28 allowed by the trial court, we reverse that award. The trial court did not err in disallowance of certain costs. We find no merit to the other issues raised by the receiver nor to the issues raised on cross-appeal by GSW, and therefore affirm as to those issues.

Insolvent insurers, Southeastern Reinsurance Company, Inc. and Southeastern Casualty and Indemnity Insurance Company, Inc. (“Southeastern”) were liquidated by orders of the Leon County Circuit Court on September 1, 1989. The Florida Department of Insurance was appointed as statutory receiver pursuant to Chapter 631. The companies were treated as one and the cases were consolidated. Prior to their liquidation, the Southeastern companies had been in the insurance and surety business, issuing payment and performance bonds for contractors engaged in the construction business in Florida. Two of the companies’ surety bonds were issued in favor of GSW guaranteeing the performance of subcontractors Peerless Electric, Inc. (“Peerless”) and Bloomingdale Landscape Nursery, Inc. (“Bloomingdale”) in relation to subcontracts for work on the Orlando International Airport. GSW was the general contractor.

Both Peerless and Bloomingdale defaulted under their subcontracts. Peerless defaulted in June 1988; Bloomingdale defaulted in July 1988. Southeastern, as the surety, undertook the completion of the subcontracts. Southeastern used an affiliated entity, Contractors Performance Corporation (“CPC”), to supervise the two contracts. Peerless executed an assignment of the “proceeds of contract number 115” to Southeastern. After entry of the liquidation order, the receiver entered into a formal settlement agreement with Peerless by which the funds due to Peerless under the bonded subcontract were to be formally assigned to the receiver. The settlement agreement was approved by the receivership court by order dated November 27, 1989. Bloomingdale’s principal also assigned all of the proceeds from the Bloomingdale subcontract to Southeastern. The Bloomingdale assignment occurred on July 7, 1988, prior to the liquidation of Southeastern. When Southeastern was liquidated, the Peerless and Bloomingdale subcontracts were not yet completed. The receiver monitored the completion of the subcontracts.

The subcontract between GSW and Bloomingdale required Bloomingdale to furnish all the landscaping work in connection with two parking structures referred to as “A” side parking garage and “B” side parking garage. After Southeastern failed to perform the work on the “B” side, GSW subcontracted most of the remaining work on the “B” side to Morgan Brothers (“Morgan”). A letter from GSW to Southeastern dated September 2, 1988, indicated that Morgan was to finish the “B” side for the sum of $36,000. After Morgan was selected to complete the “B” side, GSW and Southeastern executed a document called change order number 2. The effect of the change order was to allow GSW a credit for the work Morgan was doing on the “B” side.

[649]*649On January 25, 1989, Mr. Amatulli of CPC wrote to the president of Morgan and advised him that no extra work should be undertaken on the project without written approval from CPC’s field representative. On November 22, 1989, Mr. Szalapski, on behalf of the receiver, wrote a letter to the president of Morgan advising him that there was no written approval and no documentation for a $29,516.28 payment and that the receiver would therefore not authorize the charge. After the receiver learned that GSW had paid Morgan $29,516.28 for overtime, Mr. Szalapski wrote a letter to the president of GSW stating that Morgan had been fully paid and that the payment was not justified.

In May of 1990, GSW filed proofs of claim in the receivership court stating a claim of unknown amount on both the Peerless and Bloomingdale bonds. On December 2, 1991, in accordance with section 631.154, Florida Statutes, the receiver made a demand on GSW to deliver $185,256 plus accrued interest on the Peerless subcontract and $37,-482.69 plus accrued interest on the Bloomingdale subcontract, which the receiver claimed were funds belonging to the receiver.

GSW and Centex-Rooney Enterprises, Inc., GSW’s parent corporation, filed a response to demand and claim of right which set forth a right to a set-off. In their response, the corporations alleged that the receivership owed money in other bond claims to Centex-Rooney Enterprises, Inc. The receiver moved for partial summary judgment on the corporations’ defense, alleging that the parent company had no right to a set-off because the corporations were separate legal entities. The trial court entered partial summary judgment in favor of the receiver. The trial court also ordered GSW to report to the court, in accordance with section 631.154(1), Florida Statutes, the value of any property or funds held and what action had been taken by GSW to preserve and protect the property or to preserve the funds pending determination of the dispute between GSW and the receiver.

In response to the court’s order, GSW reported that the Peerless and Bloomingdale subcontracts had been completed and reported the balance due under the subcontracts. The receiver filed a motion to strike the report and a motion for an evidentiary hearing pursuant to section 631.154(2) on the grounds that the report failed to comply with the court’s order and was statutorily deficient because the report failed to set out the alleged value of property or the amount of funds held and what action had been taken by GSW to preserve and to protect the property or to preserve the funds pending determination of the dispute. After a hearing on the receiver’s motion to strike, the court ordered GSW to deposit $222,738.69, the entire amount in dispute, in a court controlled interest bearing account pursuant to section '69.031, Florida Statutes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Nova Ins. Group v. Dept. of Ins.
606 So. 2d 429 (District Court of Appeal of Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
639 So. 2d 646, 1994 Fla. App. LEXIS 6519, Counsel Stack Legal Research, https://law.counselstack.com/opinion/florida-department-of-insurance-v-centex-great-southwest-corp-fladistctapp-1994.