Flint Hills Resources Alaska, LLC v. Federal Energy Regulatory Commission

627 F.3d 881, 393 U.S. App. D.C. 247, 178 Oil & Gas Rep. 1025, 2010 U.S. App. LEXIS 24826, 2010 WL 4909462
Court of Appeals for the D.C. Circuit·Decided December 3, 2010·No. 08-1270, 08-1271, 09-1025, 09-1026, 09-1030, 09-1031, 09-1033, 09-1215, 09-1222, 09-1223, 09-1229, 09-1232·Published·Cited by 4 cases

Opinion

Opinion for the Court filed by Senior Circuit Judge WILLIAMS.

WILLIAMS, Senior Circuit Judge:

This case arises primarily out of the stresses involved in a shift from one system of regulatory ratemaking to another.

For many years the oil pipeline companies owning and operating the Trans Alaska Pipeline System (“TAPS”) charged shippers rates based on a 1985 settlement agreement between them (initially six of the carriers, but ultimately all eight) and the state of Alaska. (Alaska’s anticipation of royalties and tax receipts gave it a stake in the matter; the shippers in the early years, by contrast, were largely affiliates of the pipeline companies, and so had little adversity of interest.) The TAPS Settlement Agreement (“TSA”) established the TAPS Settlement Methodology or “TSM,” a ratemaking methodology to be used for computing interstate rates until 2011, the end of the pipeline’s then projected useful *884 life. Although no shippers joined the agreement, the Federal Energy Regulatory Commission, by this time the agency with authority to regulate oil pipeline rates under the Interstate Commerce Act, 49 U.S.C. §§ 1 et seq. (“ICA”), 1 approved it as “fair and reasonable and in the public interest.” 18 C.F.R. § 385.602(g); see Trans Alaska Pipeline System, 33 FERC ¶ 61,064, 61,138 (1985) (“TAPS /”); Trans Alaska Pipeline System, 35 FERC ¶ 61,425, 61,977 (1986) (“TAPS II”). The Commission’s order left shippers free to later protest rates as unjust or unreasonable. TAPS II, 35 FERC at 61,977. In practice, the TSM governed the pipeline’s interstate rates through 2004.

But when the carriers filed rates for 2005 and 2006, Alaska and two shippers (Anadarko Petroleum for both years, Tesoro Corporation for 2006) protested. Alaska, exercising rights it preserved in the TSA, alleged that the proposed rates violated the non-discrimination and anti-preference provisions of the ICA, as they were higher than the intrastate rates set by the Regulatory Commission of Alaska (“RCA”). The shippers argued that the rates were unjust, unreasonable, and otherwise unlawful. The Commission responded by scuttling the TSM. Instead it applied a methodology that it had developed for oil pipeline ratemaking generally in Williams Pipe Line Co., 31 FERC ¶ 61,377 (1985) (“Opinion No. 154-B”).

Stated in very general terms, the Commission’s orders found the rates filed for 2005 and 2006 to be unjust and unreasonable, but not discriminatory or unduly preferential. Though deciding that the just and reasonable rates would be below the 2004 rates, it limited refunds, in accordance with § 15(7) of the ICA, to the difference between the 2005 and 2006 filed rates and the prior unchallenged (2004) rate. BP Pipelines (Alaska) Inc. v. BP Pipelines (Alaska) Inc., 123 FERC ¶ 61,287 (2008) (“Opinion No. 502”); BP Pipelines (Alaska) Inc. v. BP Pipelines (Alaska) Inc., 125 FERC ¶ 61,215 (2008) (“First Rehearing Order”); BP Pipelines (Alaska) Inc. v. BP Pipelines (Alaska) Inc., 127 FERC ¶ 61,317 (2009) (“Second Rehearing Order").

The carriers assert a host of methodological errors in these decisions; we are unpersuaded. Alaska seeks relief against the Commission’s refusal to provide remedies for the alleged price discrimination; we find that even if there was discrimination, Alaska has not made the showing necessary to justify reparations. The Commission also issued a number of orders that either have not jelled in clear enough form for judicial review or present an undue likelihood of piecemeal review; we find these unripe.

We review FERC’s orders under the familiar standard for agency actions: we must set them aside if they are not supported by substantial evidence or are “arbitrary, capricious, an abuse of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2)(A).

Commission use of rate base balances from the TSM era. In calculating the maximum just and reasonable rate for service after 2004, it is obviously important *885 to know how much of the rate base (essentially the pipeline’s initial capital cost) the carriers had recovered as of December 31, 2004. A just and reasonable rate would allow it to recover thereafter only such sums as it had not recovered before. The carriers had recovered accelerated depreciation under the TSM, and the Commission found that they should use the amounts so calculated to determine the unrecovered balance as of the end of 2004. The Commission rejected their contrary proposal — to use straight-line depreciation figures shown in their filings of FERC Form 6, the carriers’ annual financial reports — on the simple ground that it would enable them “to receive benefits related to accumulated depreciation more than one time.” Opinion No. 502, P 76. See also id. P 82. The carriers assert before us that there “is also no double-recovery when Opinion No. 15J/.-B is consistently applied, as the Carriers’ presentation did,” Joint Pet. Br. at 21. While their submission, see Prepared Rebuttal Testimony of Robert G. Van Hoecke, J.A.852, indicates that revenues received under the TSM were less than the hypothetical revenue flow under Opinion No. 15U-B, it does not show why this required the Commission to recharacterize TSM return of capital as something different for purposes of estimating the post-TSM rate base balance.

Instead, they claim that FERC’s ruling violates their right not to have the TSA used as precedent against them — a right enshrined, as we just saw, in the Commission’s approval of the TSA and in our Arctic Slope decision affirming that approval. See Arctic Slope Regional Corporation v. FERC, 832 F.2d 158, 163 (D.C.Cir.1987). In a slightly different variant of the same point, they say that the shippers, because they were not parties to the TSA, cannot benefit from it.

But FERC’s use of the rate balances created by the TSA’s operation is not a “precedential” use of the TSA. Since 1985, the carriers have justified the rates that they charged shippers based on an accelerated depreciation schedule. It makes no difference what the cause of the carriers’ having characterized a portion of their rates in this manner may have been — the TSA, the tax implications, rolling dice, arm-wrestling, etc. The past is what it was. For the Commission to rely on those justifications to determine how much of the rate base has been recovered is not arbitrary and capricious.

Our rejection of the carriers’ claims here encompasses not only those claims related to accelerated depreciation but two additional categories that appear to be functionally equivalent. One of these is $450 million in previously disputed costs that the carriers amortized under the TSA.

Free access — add to your briefcase to read the full text and ask questions with AI

Flint Hills Resources Alaska, LLC v. Federal Energy Regulatory Commission, 627 F.3d 881, 393 U.S. App. D.C. 247, 178 Oil & Gas Rep. 1025, 2010 U.S. App. LEXIS 24826, 2010 WL 4909462 (D.C. Cir. 2010).

627 F.3d 881 (Flint Hills Resources Alaska, LLC v. Federal Energy Regulatory Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related