Fletcher v. State, Department of Roads

344 N.W.2d 899, 216 Neb. 342, 1984 Neb. LEXIS 921
CourtNebraska Supreme Court
DecidedFebruary 3, 1984
DocketNo. 82-554
StatusPublished
Cited by12 cases

This text of 344 N.W.2d 899 (Fletcher v. State, Department of Roads) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fletcher v. State, Department of Roads, 344 N.W.2d 899, 216 Neb. 342, 1984 Neb. LEXIS 921 (Neb. 1984).

Opinion

Grant, D.J.

Plaintiff, Douglas N. Fletcher, brought this action to recover for his personal injuries incurred when a pickup truck in which he was riding as a passenger was driven into a bridge abutment at the entrance to [343]*343a bridge. Plaintiff properly filed his tort claim under Neb. Rev. Stat. §§ 81-8,209 et seq. (Reissue 1981). After denial of his claim plaintiff filed his amended petition alleging generally that the accident and his resulting injuries were proximately caused by the negligence of defendants, State of Nebraska, Department of Roads, and the State of Nebraska (hereinafter collectively defendant), in “permitting unreasonable delays by their contractors of the repairs and maintenance of the approach to said bridge,” in “negligently and carelessly permitting the contractor to remove the existing guardrails for an unreasonable period of time,” and in failing to install and maintain safety beam guardrails on the approach to the bridge. Trial was had to the district court, sitting without a jury, as required by § 81-8,214. The court found for the plaintiff, made certain “conclusions of fact,” and entered judgment against defendant for $741,859.46. Defendant appeals.

With regard to plaintiff’s allegations concerning “permitting unreasonable delays,” the trial court found that “[djefendant was negligent in failing to supervise and/or take appropriation action against the Nider-Jergensen Construction Company to prevent the unreasonable delays in this project” and “in permitting the Nider-Jergensen Construction Company to remove the guardrail in question for an unreasonable period of time,” and that each recited act of negligence “was a proximately-contributing cause of the injuries sustained by the plaintiff.” Lengthy testimony was adduced at the trial to establish that on March 21, 1977, a contract was executed between defendant and Nider-Jergensen to resurface and generally rebuild some 4 miles of roadway on U.S. Highway 6 from the vicinity of the Platte River to the junction of Highway 31 and Highway 6. On the same day, defendant entered into a contract with Joseph T. Grof Construction Company to erect new guardrails at bridge 34157, a bridge over a stream just east of the Platte River, the site of the [344]*344accident. Various dates of beginning work were established, such as July 25, 1977, for Nider-Jergensen’s asphalting, and September 6, 1977, for Grof’s guardrail work. For unexplained reasons Nider-Jergensen did not complete its work within the contractual 25 working days, and indeed did not complete its contract until November 23, 1977, on which date the project was “temporarily suspended” by the State, due to winter conditions. On December 12, 1977, defendant advised Nider-Jergensen that the State had accepted Nider-Jergensen’s work as of November 23, 1977, and that the company was relieved of further responsibility for the job. During the course of its contract, Nider-Jergensen had removed the guardrails at the bridge in question on October 5 and 6, 1977. Grof was not called on to install the new guardrails on the bridge until May of 1978. The accident in question happened on December 16, 1977.

Insofar as the trial court predicated defendant’s liability for plaintiff’s injuries on defendant’s action or lack of action under contracts with third parties, such holding is in error. Only legal confusion could result if members of the general traveling public were in some way considered to be third-party beneficiaries of every construction contract entered into by the State of Nebraska with outside contractors, or if it be determined that the duty the State owes to the traveling public could be measured by the State’s performance under such contracts. The actions of the State in entering into, and in the performance under, such contracts are “discretionary functions” of the State and cannot afford the general public a basis for tort claims negligence actions against the State. In Dalehite v. United States, 346 U.S. 15, 73 S. Ct. 956, 97 L. Ed. 1427 (1953), the U.S. Supreme Court considered the “discretionary function” exclusion of the Federal Tort Claims Act. That exclusion, as set out in 28 U.S.C. § 2680 (1976), is essentially the same as § 81-8,219(1)(a), which provides that the provisions of the State Tort Claims [345]*345Act shall not apply to any claim “based upon the exercise or performance or the failure to exercise or perform a discretionary function or duty on the part of a state agency . . .

In Dalehite, supra at 35-36, the Court stated: “It [a discretionary function] also includes determinations made by executives or administrators in establishing plans, specifications or schedules of operations.” Negligence against the State ordinarily cannot be predicated on the State’s alleged failure to “take appropriate action” against a construction company for contractual delays alleged to be unreasonable. Such appropriate actions are the responsibility of the executive branch of the government, and the ultimate control over such action or inaction is at the ballot box, not in individual negligence cases.

Such a disposition of the first two findings of negligence, however, does not in any way dispose of this case, but that disposition does clear away unnecessary underbrush. The basic holding of the trial court in determining responsibility in this case rests on the trial court’s finding that “[d]efendant was negligent in maintaining this location in an unreasonably unsafe condition, to-wit: with an exposed bridge rail, unprotected by a guardrail, barricades, or other temporary protective devices, and such negligence was a proximately-contributing cause of the injuries sustained by the plaintiff.” Such a finding, if legally proper and factually supported by the evidence, would determine a violation of defendant’s duty to the traveling public, which the trial court had properly determined to be the duty “to maintain its highways in a reasonably safe condition for travel by persons using the same, and to use ordinary care to protect such persons from dangerous places near the traveled portion thereof.” That statement accurately reflects Nebraska law as set out in Clouse v. County of Dawson, 161 Neb. 544, 74 N.W.2d 67 (1955), King v. Douglas County, 114 Neb. [346]*346477, 208 N.W. 120 (1926), and Richardson & Gillispie v. State, 200 Neb. 225, 263 N.W.2d 442 (1978), supp. op. 200 Neb. 781, 265 N.W.2d 457.

In this case defendant had released Nider-Jergensen from all responsibility and had accepted its work as of November 23, 1977, and the defendant had chosen not to require guardrails to be installed until the following spring. Defendant’s “discretionary function” planning in that regard may not be the basis for a tort claims action, but defendant’s actual conduct in maintaining its highways and bridges as it did after the contractor was released falls squarely within the State Tort Claims Act.

The facts in that regard follow. As set out above, guardrails on the approach to the bridge in question had been removed on October 5 and 6, 1977.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Childers v. PHELPS COUNTY, NEB.
568 N.W.2d 463 (Nebraska Supreme Court, 1997)
Jasa Ex Rel. Jasa v. Douglas County
510 N.W.2d 281 (Nebraska Supreme Court, 1994)
First Nat. Bank of Omaha v. State
488 N.W.2d 343 (Nebraska Supreme Court, 1992)
Security Investment Co. v. State
437 N.W.2d 439 (Nebraska Supreme Court, 1989)
Bean v. State
382 N.W.2d 360 (Nebraska Supreme Court, 1986)
Tank v. Peterson
363 N.W.2d 530 (Nebraska Supreme Court, 1985)
Priest v. McConnell
363 N.W.2d 173 (Nebraska Supreme Court, 1985)
Wickersham v. State
354 N.W.2d 134 (Nebraska Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
344 N.W.2d 899, 216 Neb. 342, 1984 Neb. LEXIS 921, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fletcher-v-state-department-of-roads-neb-1984.