Fleming v. Law

151 P. 385, 28 Cal. App. 110, 1915 Cal. App. LEXIS 313
California Court of Appeal·Decided July 20, 1915·No. Civ. No. 1346.·Published·Cited by 1 cases

Opinion

BURNETT, J.

The action was brought to recover the sum of $6,170.61 claimed as a balance due on a contract for marble shipped from Colton, California, to be used in the Monadnock Building in San Francisco, and the verdict and judgment were for plaintiff in the sum of five thousand and seventy dollars, and interest. The parties to said contract were W. A. Perrin, a manufacturer of marble, and Herbert E. Law, the owner of said building, and the plaintiff is the assignee of said Perrin.

We may state appellant’s first contention in his own language: “Law concedes that Perrin’s figures are correct as to the amount of marble placed on the cars at Colton and shipped to San Francisco, as he has no means of disputing plaintiff’s evidence in this behalf or questioning the accuracy of the various statements sent to him from time to time relating to shipments. Law also concedes and admits that plaintiff’s statement as to the amount of money paid by him is correct. Law contends, however, that he is not responsible for the total amount of marble shipped, but that the limit of his liability is made to depend upon the quantity of marble actually set in place in his building at the unit prices fixed in the contract.” It is insisted that there is no substantial conflict in the evidence but that it shows that “the contract value of the marble set in the building was $33,908.45; also that $31,315.40 was paid on the contract value of the marble set in the building since the fire. The uneontradicted and undisputed evidence was that $7,404.35 worth of marble was saved from the disaster, upon which a balance of $2,738.78 was owing and upon which there had necessarily been paid $4,665.57. This would show that the sum of $35,980.97 was the full amount paid upon all the marble set in the building, or $2,070.52 in excess of the contract price.” Indeed, it is admitted that the vital point in the controversy is involved in the amount of marble saved from the fire that is now in the building. Respondent denies that marble of the value of $7,404.35 was saved but claims that it was only of the value of $1,124.35, admitting, how *113 ever, that “the whole question, therefore, as to defendant’s liability is the value of the marble saved from the earthquake and fire.” The case was before the supreme court on a former appeal by defendant. On the former trial it was the theory of plaintiff, adopted by the trial court, that “Law was responsible for all the marble that had been shipped, and that as soon as the marble was placed upon the ears, f. o. b. at Colton, it became his property and that Perrin ceased to have any interest in it.” But the supreme court (Fleming v. Law, 163 Cal. 227, [124 Pac. 1018]) held that under the pleadings and the evidence, Law could be held only for the amount of - marble actually set in the building. The complaint, it may be said, was framed upon the theory that Law agreed to pay for all the marble shipped to him from Colton, while the answer avers that the contract was as follows: “It is agreed that payments for marble in Monadnock Building are approximate only and that the actual marble to be paid for by you (Law) will be measured set in building; the owner taking no responsibility as to sizes or condition, etc., delivered.” The pleadings were not amended in any respect at the second trial and hence the issues as thus presented were, of course, the same as at the first trial.

In said opinion it was declared by the supreme court: “Appellant, however, contends and it is without dispute that the contract price for all the marble actually set in the building and measured therein upon its completion amounted to the sum of $33,908.45; that it is equally without dispute that $7,404.35 of this amount was marble saved from the disaster; that deducting this latter sum from the former there is left $26,504.10 as the contract price of the marble shipped after the disaster and actually set in the building. . . . Also appellant still further argues and shows that immediately after the disaster there was a balance unpaid upon the marble shipped of $2,738.78; that there was marble saved to the value of $7,404.35. Deducting from this the sum of $2,738.78, which was owing, $4,665.57 had been paid upon the marble saved from the disaster and placed in the building. Upon the shipment of marble made after the disaster there has admittedly been paid $31,315.40, making a total payment for the marble actually set in the building of $35,980.97.” Of course, that decision befiame and is the law of the case (Brett v. S. H. Frank & Co., 162 Cal. 737, [124 Pac. 437]) and it is *114 the contention of appellant that the cause is presented here just as it was to the supreme court. Respondent, however, says: “Upon the former trial no evidence was introduced concerning the value of the marble saved from the fire and the earthquake, other than a statement prepared by young Perrin showing that some $7,404.35 worth of marble had been saved. It was thought by counsel at that time that the state' ment was correct and it so appeared in the transcript. No such concession is now made and it is claimed that from the evidence the jury was justified in finding that marble of the value only of $1,124.35 was saved.”

Free access — add to your briefcase to read the full text and ask questions with AI

Fleming v. Law, 151 P. 385, 28 Cal. App. 110, 1915 Cal. App. LEXIS 313 (Cal. Ct. App. 1915).

151 P. 385 (Fleming v. Law) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

R. Krasnow & Sons, Inc. v. Emerzian
247 P. 536 (California Court of Appeal, 1926)