Fleming Building Co., Inc. v. Northeastern Oklahoma Building and Construction Trades Council

532 F.2d 162, 91 L.R.R.M. (BNA) 2794, 1976 U.S. App. LEXIS 12308
CourtCourt of Appeals for the Tenth Circuit
DecidedMarch 19, 1976
Docket75-1278
StatusPublished
Cited by16 cases

This text of 532 F.2d 162 (Fleming Building Co., Inc. v. Northeastern Oklahoma Building and Construction Trades Council) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fleming Building Co., Inc. v. Northeastern Oklahoma Building and Construction Trades Council, 532 F.2d 162, 91 L.R.R.M. (BNA) 2794, 1976 U.S. App. LEXIS 12308 (10th Cir. 1976).

Opinion

BARRETT, Circuit Judge.

Fleming Building Company, (Fleming), appeals from a judgment denying its claim for damages against the Northeastern Oklahoma Building and Construction Trades Council, (Council).

This action is based upon Section 303 of the Labor Management Relations Act, 29 U.S.C.A. § 187. The controversy giving rise to this suit occurred during the construction of a Pontiac dealership building in Tulsa, Oklahoma. Fleming was the general contractor for the construction of the building. A subcontract was entered into between Fleming and Beasley Plumbing and Heating Company. Beasley, a non-union plumbing contractor, agreed to perform plumbing work on the building. After Beasley commenced work at the job site, Fleming was informed that the Plumber Local Union No. 176 (Union) intended to picket the job. The *163 purpose of the picketing was to protest Fleming’s subcontract with a non-union plumbing contractor.

Fleming attempted to avoid any dispute with the Union by soliciting Ifids from approved union plumbing contractors. Presumably, if a union contractor could equal Beasley’s bid for the job, Beasley would be replaced. Fleming, however,,,.subsequently informed Robert Smith, business agent for the Council, 1 that it was unable to attain any union bids as low as Beasley’s and that it therefore intended to honor the subcontract with Beasley. ^

No agreement having been reached with Fleming, the Union picketed the job site on July 28 and 30,1971. The Trial Court made the following finding concerning the picketing: c

The picketing on July 28; 1971, commenced sometime around 3:0.0 p.m. in the afternoon and the normal workday ceased at 4:30 p.m. That as a result of picketing, some individuals.,;working on the job did not cross the* picket line. That on July 30 the picketing ceased at approximately 3:00 p.m. and no further picketing or job stoppage of any' type took place on the job as a Result of the union picket. [R. Yol. 1, at; 133]

Suit was brought against Union by Fleming. That action was settled by an agreement approved by the Regional Director of the National Labor Relations Board on August 23, 1971. By the terms of the agreement, Fleming withdrew charges filed with the N.L.R.B. against the Union. 2

The controversy before us stems from charges filed by Fleming against the Council on August 19, 1971. Fleming asserted that the Council had committed unfair labor practices under Section 8(b)(4)(ii)(B) of the N.L.R.A., 29 U.S.C.A. § 158: 3 The charges against Council were heard before the Trial Examiner of the N.L.R.B. on October 21, 1971. His decision was rendered on December 30, 1971. He held that the Council had exerted pressure on Fleming to force Fleming to cease doing business with Beasley and that the threat of Union picketing violated Section 8(b)(4)(ii)(B) of the N.L.R.A., supra.

Following the Trial Examiner’s decision, Fleming filed this suit seeking damages from Council under Sec. 303 of the L.M. R.A., supra.

A Motion for Summary Judgment was filed by Fleming on the issue of liability. Fleming asserted that this issue had been determined by the Trial Examiner. The motion was granted by the Trial Court. The remaining issue of damages resulting from the conduct of Council was then tried to the Trial Court. Judgment was entered on September 3,1974, denying Fleming any damage award. This appeal is taken from that judgment.

Fleming poses these issues on appeal: (1) Whether the Trial Court erred in finding that Fleming suffered no damage as a result of the illegal conduct of Council; (2) Whether the Trial Court erred in requiring Fleming to prove the amount of its damages by clear and convincing proof; and (3) *164 Whether the Trial Court erred in modifying its Partial Summary Judgment.

I.

Fleming challenges the Trial Court’s finding that it suffered no damage from the illegal conduct of Council, 4 on the ground that the Court imposed a greater quantum of proof than that required in order to maintain a § 303 suit. Fleming argues that it need only establish the existence of damages by a preponderance of the evidence, rather than by clear and convincing proof. We agree.

This Court has not heretofore considered the issue of the quantum of proof necessary to establish the existence of damages under § 303, supra. Indeed, there is scant authority on the issue. We are aided in our decision, however, by those cases which have considered the “clear proof” standard under § 6 of the Norris-LaGuardia Act, 29 U.S. C.A. §§ 101-115. 5

The “clear proof” standard of § 6 of the Norris-LaGuardia Act, supra, was reviewed in Ramsey v. Mine Workers, 401 U.S. 302, 91 S.Ct. 658, 28 L.Ed.2d 64 (1971), wherein certain coal mine operators sued the United Mine Workers of America (UMWA) alleging violations of the Sherman Act. The operators claimed that UMWA was attempting to eliminate the marginal operators and to control production thereby, i. e. in effect by reserving production for the large operator by imposing the provisions of the National Bituminous Coal Wage Agreement on all coal mine operators. The operators contended that UMWA knew that small operators could not meet the contract’s terms, and that UMWA was acting in conjunction with the major coal producers. The issue thus posed was what is the standard of proof required to show a Sherman Act violation by a labor union.

The District Court held that the “clear proof” standard found in § 6 of the Norris-LaGuardia Act was the applicable standard. The Supreme Court, however, disagreed:

. § 6, with its requirement that when illegal acts of any individual are charged against one of the major antagonists in a labor dispute — whether employer or union — the evidence must clearly prove that the individual’s acts were authorized or ratified . . .We find no support in the legislative material for the notion that Congress intended broadly to modify the standard of proof when union and employer are sued separately or together in civil actions for damages incurred in the course of labor disputes. 401 U.S. at 310, 91 S.Ct. at 663, 28 L.Ed.2d at 70.

We interpret the above quoted language as clearly implying that the preponderance of the evidence standard is applicable in civil actions against labor unions with the exception of those situations triggering the application of § 6 of the Norris-LaGuardia Act which requires the “clear proof” standard. Supportive of our interpretation of Ramsey, supra, is Kayser-Roth Corporation v. Textile Workers Union of America, AFL-CIO, 479 F.2d 524 (6th Cir. 1973), cert. denied, 414 U.S. 976, 94 S.Ct. 292, 38 L.Ed.2d 219 (1973).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
532 F.2d 162, 91 L.R.R.M. (BNA) 2794, 1976 U.S. App. LEXIS 12308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fleming-building-co-inc-v-northeastern-oklahoma-building-and-ca10-1976.