Flatiron/Dragados/Sukut Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedApril 3, 2023
Docket63019, 63020
StatusPublished

This text of Flatiron/Dragados/Sukut Joint Venture (Flatiron/Dragados/Sukut Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flatiron/Dragados/Sukut Joint Venture, (asbca 2023).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeals of - ) ) Flatiron/Dragados/Sukut Joint Venture ) ASBCA Nos. 63019, 63020 ) Under Contract No. W91238-17-C-0025 )

APPEARANCES FOR THE APPELLANT: Michael A. Branca, Esq. Patrick J. Greene, Jr., Esq. Nick R. Hoogstraten, Esq Pecker & Abramson, P.C. Washington, DC

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Colby K. Stewart, Esq. Amanda R. Fuller, Esq. Alfred L. Faustino, Esq. Timothy A. Holiday, Esq. Schuyler Lystad, Esq. Robert W. Scharf, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Sacramento

OPINION BY ADMINISTRATIVE JUDGE MCNULTY ON THE GOVERNMENT’S MOTION TO DISMISS

Before the Board is the government’s motion to dismiss for failure to state a claim. Appellant, Flatiron/Dragados/Sukut Joint Venture (FDS) opposes the motion. For the reasons stated below, we deny the motion.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

1. Under date of September 18, 2017, the government’s contracting officer advise FDS in writing that it had been awarded Contract No. W91238-17-C-0025, the Isabella Lake Dam Safety Modification Project (DSMP), Phase II, Dams and Spillway (R4, tab 16).

2. The contract incorporated by reference the following standard Federal Acquisition Regulation (FAR) contract clauses pertinent to the issues raised by the motion - 52.233-3, PROTEST AFTER AWARD (AUG 1996) and 52.242-14, SUSPENSION OF WORK (APR 1984) (R4, tab 12 at 31-32). The Protest After Award clause states in pertinent part:

(a) Upon receipt of a notice of a protest . . . the Contracting Officer may, by written order to the Contractor, direct the Contractor to stop performance of the work called for by this contract. The order shall be specifically identified as a stop-work order issued under this clause. . . . Upon receipt of the final decision in the protest, the Contracting Officer shall either-

(1) Cancel the stop-work order; or

... (2)

(b) If a stop-work order issued under this clause is canceled either before or after a final decision in the protest, the Contractor shall resume work. The Contracting Officer shall make an equitable adjustment in the delivery schedule or contract price, or both, and the contract shall be modified, in writing, accordingly, if-

(1) The stop-work order results in an increase in the time required for, or in the Contractor’s cost properly allocable to, the performance of any part of this contract; and

(2) The Contractor asserts its right to an adjustment within 30 days after the end of the period of work stoppage; provided, that if the Contracting Officer decides the facts justify the action, the Contracting Officer may receive and act upon a proposal submitted at any time before final payment under this contract.

(Emphasis in original)

2 3. By letter dated October 4, 2017, the contracting officer advised FDS that a bid protest had been filed. The contracting officer directed FDS to suspend any performance pending resolution of the protest and further notice from the government. The letter did not advise under which contract clause the stay was directed. (R4, tab 17)

4. By letter dated January 4, 2018, the contracting officer advised FDS that the protest had been denied and that a Notice to Proceed (NTP) would be forthcoming (R4, tab 18).

5. By letter dated January 18, 2018, the contracting officer issued the NTP to FDS (R4, tab 19).

6. By letter dated February 2, 2018, FDS notified the contracting officer that the joint venture intended to seek an equitable adjustment pursuant to the Protest After Award clause of the contract for the delay and additional costs it claimed to have experienced by reason of the bid protest (R4, tab 20 at 1-2).

7. By Serial Letter No. H-0005 dated April 16, 2018, FDS submitted a request for an equitable adjustment (REA) seeking $9,812,107 for several discrete items of work that it asserted had experienced cost impacts and a time extension of 40 days due to the delay caused by the bid protest (R4, tab 21 at 13).

8. Bilateral Modification No. P000001with an effective date of May 24, 2018, extending the contract performance period 83 calendar days pursuant to the authority of the Protest After Award clause, was issued. In pertinent part the modification stated:

The need to increase the period of performance from 1,177 calendar days to 1,260 calendar days stems from the delayed of issuance of the Noticed to Proceed (January 18, 2018 in lieu of October 16, 2017) due to a protest after contract award. USACE's original solicitation dictated a period of performance of 1,260 calendar days; however, the contractor proposed a shorter period of performance of 1,177 days which the Government accepted and incorporated into the contract. As a result of the delayed Notice to Proceed, the contractor is no longer able to perform the contract in 1,177 days; therefore, as an equitable adjustment to the Contractor, the period of performance must be increased back to 1,260 days for a projected completion date of July 01, 2021.

It is understood and agreed that pursuant to the above, the contract time is extended the number of calendar days stated. It is also understood that any contract price increases related to the

3 modification of contract will be discussed and negotiated separately from this modification and settled in conjunction with the Request for Equitable Adjustment dated April 16, 2018 and titled Request for Equitable Adjustment for Delivery Schedule and Contract Price due to Protest after Award.

(R4, tab 13)

9. Bilateral Modification No. P00003 with an effective date of September 14, 2018 awarded FDS $133,716 for “ . . . additional costs incurred during the period of stop work from October 4, 2017 to January 4, 2018.” The modification indicates the authority for the modification was provided by the contract’s Protest After Award clause. The modification also states: “This modification only addresses what the Contractor refers to in serial letter H-0005 as ‘Cost Element A’, Tab D ‘Impacts of Bid Protest’. The rest of the cost elements listed in H-0005 are still under review and are pending negotiations.” (R4, tab 14)

10. After the parties were unable to negotiate the quantum amount for the asserted remaining cost increases, FDS updated its REA, breaking it into two parts, REA 1A and 1B. REA 1A was for the increased costs of rebar material in the amount of $2,535,617.08 1. The Protest After Award clause was again asserted to be the basis for the authority for the adjustment sought. (R4, tab 27 at 3-4) REA 1B included costs for environmental related impacts, project escalations and overheads associated with the delay that had been related to the bid protest. The Protest After Award clause was also asserted to provide authority for this additional adjustment sought (R4, tab 28 at 7). REA 1B totaled $7,003,937.63 2 (Id. at 2).

11. By letter dated April 9, 2020, FDS converted REA 1A into a formal Contract Disputes Act, 41 U.S.C. §§ 7101-7109 (CDA) claim and requested a final contracting officer’s decision (R4, tab 3). It did the same with REA 1B under date of June 24, 2020, revising the amount claimed to $8,429,578 (R4, tab 7).

12. The contracting officer denied the claims arising from REA 1A and 1B under date of August 2, 2021, except for $3,592.10 and $821,498.12 for the costs sought in REA 1A and 1B, respectively (R4, tabs 5, 9).

13. FDS timely appealed the decisions of the contracting officer, which were docketed as ASBCA Nos. 63019 and 63020 respectively (R4, tabs 2, 6).

1 Subsequently revised to $2,516,488 (R4, tab 2). 2 Subsequently further revised to $8,254,665 (R4, tab 6). 4 14.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cary v. United States
552 F.3d 1373 (Federal Circuit, 2009)
Kellogg Brown & Root Services, Inc. v. United States
728 F.3d 1348 (Federal Circuit, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Flatiron/Dragados/Sukut Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flatirondragadossukut-joint-venture-asbca-2023.