Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp.

994 S.W.2d 830, 1999 Tex. App. LEXIS 4007, 1999 WL 339339
CourtCourt of Appeals of Texas
DecidedMay 27, 1999
Docket01-98-00543-CV
StatusPublished
Cited by301 cases

This text of 994 S.W.2d 830 (Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp., 994 S.W.2d 830, 1999 Tex. App. LEXIS 4007, 1999 WL 339339 (Tex. Ct. App. 1999).

Opinion

OPINION

SAM NUCHIA, Justice.

This is an appeal of a summary judgment in favor of defendants in a lawsuit alleging breach of contract, anticipatory repudiation, economic duress/business coercion, fraud, negligent misrepresentation, and violation of the Texas Deceptive Trade Practices Act. We affirm.

BACKGROUND

In 1992, Pennzoil Caspian Corporation (“PCC”) became involved with the State Oil Company of the Azerbaijan Republic (“SOCAR”) in a major Gas Utilization Project in the Caspian Sea. PCC was to provide and install turbine-driven compressors and related process equipment and pipeline for the project and was to operate and maintain the compressors and related equipment for a period of time after installation.

PCC contracted with VECO Corporation to construct the compressor station and to provide engineering and procurement logistics for the project. VECO searched for a parts supplier and, after discussions with several potential suppliers, recommended to PCC that plaintiff, Flameout Design & Fabrication, Inc. (“Flameout”), become the parts supplier. VECO represented to PCC that Flameout was offering to supply original equipment manufacturer (“OEM”) parts for the commissioned start up and for replacement parts.

An internal memo on PCC letterhead dated August 18, 1998 briefly summarized proposals by different equipment suppliers. This memo stated:

Flameout has presented a quotation of $937,882.24 and has promised delivery of commissioning items within 4 weeks with tools and balance of items 3 months except the spare impellars at 4 months. Flameout is offering original manufacturer parts....
Our recommendation is to proceed with Flameout.

On September 10, 1993, Allan Hardison, VECO employee and Procurement and Logistics Manager for the project, issued a letter of intent to Flameout on PCC letterhead. This letter confirmed PCC’s intention:

to purchase from your company turbine commissioning spare parts per the lists which are being developed by Mr. John Blackwelder and which have been reviewed by you. Acquisition of these parts is predicated upon finalizing these lists and appropriate unit prices for items presented to your company, and in accordance with the agreements reached at the meeting held in our offices on September 7, 1993. Payment terms for these parts must also be mutually agreed.

A document entitled “Parts Listing,” dated January 20, 1994, contains lists of parts, quantities, and prices. The quantities are in columns headed “Comm.” and “3 Year.” This list, which the parties call the Baku list, is not signed, and there is no indication on the document to show who created it.

On February 22, 1994, in a letter to Paula Jacobs of PCC, Michael Moore, President and CEO of Flameout, wrote, “Flameout certifies that all the material supplies (sic) is NEW OEM equipment. No surplus, refurbished or auctioned materials will be supplied.”

On April 28, 1994, PCC employee K.B. Whitley wrote Flameout and Transoceanic Shipping Company, “Gentlemen: Attached is the procedure for receiving spare parts at Transoceanic. This procedure should be implemented immediately.” Attached *834 to the letter is a two-page document entitled “Receiving Procedure.” It begins, “For purchase orders 010763 02, 010768 01, and future purchase orders for the three year commissioning parts, as per list compiled by Flameout Design and Fabrication, and Pennzoil Caspian Corporation and Letter of Intent dated September ll(sie), 1993, (see attached). After consultation with Transoceanic, the following basic receiving procedure will be followed.” Procedures for shipping and receiving and some special procedures for certain equipment are then stated in the document.

During the time Flameout was involved in this project, PCC issued between 1.1 and 1.6 million dollars in written, signed purchase orders to Flameout, according to Moore’s estimate. In addition, PCC gave some verbal purchase orders between midsummer and December 1993. These verbal orders were filled by Flameout, and PCC paid for the equipment ordered..

On July 29, 1994, PCC wrote a letter to Flameout confirming that PCC wished Flameout to continue to expedite the delivery of the remaining items on purchase orders 010763 and 010768.

On October 25, 1994, Flameout wrote PCC informing it that Flameout would not quote or take any new orders from Pennzoil. On October 28, 1994, Flameout wrote PCC, stating in some detail its reasons for refusing to accept new orders from PCC. 'Flameout complained of PCC’s unwillingness to abide by “the Agreement” between Flameout and PCC, Flameout’s “unworkable” attempts to accommodate PCC’s “changed positions,” and PCC’s purchase of certain parts from suppliers other than Flameout.

In January 1995, Flameout sued PCC alleging causes of action for breach of contract, anticipatory repudiation, violation of the Texas Deceptive Trade Practices Act, fraud, negligent misrepresentation, and the defense of estoppel to deny the enforceability of the agreement. Flameout later amended its petition to add Pennzoil Company and Pennzoil Exploration and Production Company as defendants (collectively referred to herein as “PCC”). It also added a cause of action for “economic duress/business coercion.”

PCC filed a motion for summary judgment under rule 166a(i) of the Texas Rules of Civil Procedure, asserting that there was no evidence to support at least one element of each of Flameout’s causes of action. PCC’s motion was granted by the trial court.

STANDARD OF REVIEW

Under rule 166a(i), a party may move for summary judgment if there is no evidence of one or more essential elements of a claim or defense on which an adverse party would have the burden of proof at trial. Tex.R. Civ. P. 166a(i). Thus, a no-evidence summary judgment is similar to a directed verdict. Jackson v. Fiesta Mart, Inc., 979 S.W.2d 68, 70 (Tex.App.—Austin 1998, no pet.); see also Hittner & Liberato, Summary Judgments in Texas, 34 Hous. L.Rev. 1303, 1356 (1998). A party may move for a no-evidence summary judgment after there has been adequate time for discovery. Tex.R. Civ. P. 166a(i). The motion may not be general, but must state the elements on which there is no evidence. Id. The trial court must grant the motion unless the nonmovant produces more than a scintilla of evidence raising a genuine issue of material fact on the challenged elements. See Tex.R. Crv. P. 166a(i) and cmt. to 1997 change. Thus, the party with the burden of proof at trial has the burden of proof in the summary judgment proceeding.

The general requirements of summary judgment practice continue to be governed by the existing rules. Id. Therefore, in reviewing a summary judgment, we must indulge every reasonable inference in favor of the nonmovant and resolve any doubts in its favor. Randall’s Food Mkts., Inc. v. Johnson, 891 S.W.2d 640, 644 (Tex.1995).

*835

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In Re Frank Kent Motor Co.
361 S.W.3d 628 (Texas Supreme Court, 2012)
Manning v. Enbridge Pipelines (East Texas) L.P.
345 S.W.3d 718 (Court of Appeals of Texas, 2011)
Martinez v. Hays Construction, Inc.
355 S.W.3d 170 (Court of Appeals of Texas, 2011)
Miles v. Lee Anderson Co.
339 S.W.3d 738 (Court of Appeals of Texas, 2011)
Aspenwood Apartment Corp. v. Coinmach, Inc.
349 S.W.3d 621 (Court of Appeals of Texas, 2011)
ALATTAR v. Ganim
355 S.W.3d 1 (Court of Appeals of Texas, 2010)
Plotkin v. Joekel
304 S.W.3d 455 (Court of Appeals of Texas, 2009)
Lucio v. John G. & Marie Stella Kenedy Memorial Foundation
298 S.W.3d 663 (Court of Appeals of Texas, 2009)
McCoy v. Rogers
240 S.W.3d 267 (Court of Appeals of Texas, 2007)
Thomas v. CNC Investments, L.L.P.
234 S.W.3d 111 (Court of Appeals of Texas, 2007)
Rabe v. Dillard's, Inc.
214 S.W.3d 767 (Court of Appeals of Texas, 2007)
Price v. Divita
224 S.W.3d 331 (Court of Appeals of Texas, 2006)
Larned v. Gateway East, Inc.
186 S.W.3d 597 (Court of Appeals of Texas, 2006)
Mathis v. RKL Design/Build
189 S.W.3d 839 (Court of Appeals of Texas, 2006)
Brown v. Swett & Crawford of Texas, Inc.
178 S.W.3d 373 (Court of Appeals of Texas, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
994 S.W.2d 830, 1999 Tex. App. LEXIS 4007, 1999 WL 339339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flameout-design-fabrication-inc-v-pennzoil-caspian-corp-texapp-1999.