Flaherty v. Atlantic Lumber Co.

44 A. 186, 58 N.J. Eq. 467, 13 Dickinson 467, 1899 N.J. Ch. LEXIS 64
CourtNew Jersey Court of Chancery
DecidedAugust 18, 1899
StatusPublished
Cited by1 cases

This text of 44 A. 186 (Flaherty v. Atlantic Lumber Co.) is published on Counsel Stack Legal Research, covering New Jersey Court of Chancery primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Flaherty v. Atlantic Lumber Co., 44 A. 186, 58 N.J. Eq. 467, 13 Dickinson 467, 1899 N.J. Ch. LEXIS 64 (N.J. Ct. App. 1899).

Opinion

Grey, V. C.

There are two claims which are disputed and denied the right to participate in the fund by the other claimants. As to the remaining claims, the parties at the hearing admitted the correctness of the amounts of claims and the notices served thereunder, as stated in the bill and answers, without formal proofs; and it was also agreed as to those other claims that the materials and labor furnished and performed actually went into the building in question and that the proper demand was made for payment and refused.

By the construction given by the court of appeals in Slingerland v. Binns, 11 Dick. Ch. Rep. 413, and Bayonne Building and Loan Association v. Williams, 43 Atl. Rep. 669, the fifth section of the supplement of 1895 (Gen. Stat. p. 2074) was declared to give to workmen and materialmen (subject to the expense of completing the contract work) an inchoate lien ab initio upon the liability of the owner to the contractor, which lien becomes perfect only on service of the statutory notice, based on demand and refusal of payment before that liability matures, and expires on such maturity if no notice has been given. This ruling makes it necessary to determine in each case, when a contest arises as to the applicability of installments coming due under the contract, what is the exact time when the liability of the owner to the contractor matures. Before that time the inchoate lien may be perfected by service of notice in conformity to the statute; after that time, so much of the installment which has matured as is not necessary to complete the contract work or to satisfy inchoate liens then perfected by notice, is at the disposal of the contractor and subject to attack by his outside creditors. Donnelly v. Johnes, ante p. 442.

The moneys in dispute in this cause came to be due under the last installment. By the terms of the contract the building was to be wholly finished on the 1st day of May, 1897. The final installment of 1884 became payable “ when the building is finished, it being understood that the fiual payment shall be made thirty days after this contract is completely finished.” There seems to be no dispute that the building was completed, as testi[470]*470fied by the contractor, according to the contract. Thirty days after May 1st, 1897, was May 31st, 1897. At that date the liability of the owner to the contractor for the last installment matured. Up to that time any workman or materialman entitled to give the statutory notice to retain might do so, and thus perfect his inchoate lien; after that date they lost their privilege, and the contractor and his outside creditors might claim so much of the fund as was not needed to complete the contract and to pay the notices served, in compliance with the statute.

The notices served are to be paid in succession, in the order of their service. Bayonne Building and Loan Association v. Williams, supra.

The first notice was that of Daniel B. Ingersoll, served on April 9th, 1897, one of the two claims, payment of which is disputed. The written notice of Ingersoll was, in its essentials, in conformity to the statute, and gave notice to the owner to retain $872.60. The other claimants defend the fund against Ingersoll’s claim upon the ground that “ Ingersoll served notice for too much money.” The basis of this contention is not that the amount demanded by Ingersoll was not owing to him when demanded, but that, by what the opponents insist were the terms of Ingersoll’s contract, it was not, when demanded, payable. This defence rests wholly upon the claim that by the contract between Ingersoll and the contractor, Myers, the price of the bricks which Ingersoll furnished was fixed to be paid at certain specified times, which, the opponents insist, only arrived when Myers got his payments from Flaherty; and they say that on the day when Ingersoll served his notice Myers was not entitled to, and had not received, enough to pay Ingersoll the amount owing to him by $6, and as Myers had not received it Ingersoll had no right to demand it. The argument is exhibited by the following schedule submitted -by the counsel opposing Ingersoll’s claim :

“ Myers’ contract with Flaherty was for payment of.................... $4,884 00
“ Flaherty paid Myers during March, 18'97, the first two payments under the contract, $1,500 each........................................ 3,000 00
“ Flaherty owed Myers, May 1, 1897........................................ $1,884 00
[471]*471‘‘Ingersoll furnished bricks up to March 31, 1897, to the value of... §1,166 60
“ Myers paid Ingersoll, March 20, 1897.................................... 300 00
§866 60
“This is the amount for which Ingersoll should have served notice, as he sold §6.00 of brick on April 1st. Under his contract this was not due until May 1st. April 9th, Ingersoll served notice for §872.60, or for §6 more than was due him, at that time

It should be noticed that all the bricks had been delivered by Ingersoll more than a week before notice served by him. The criticism of his claim depends, as stated, wholly upon the assertion that $6 of his demand, though owing to him when noticed, had not then become payable because, by his contract, it was not payable until Myers had received'his contract-money, and it is claimed that Myers did not become entitled to receive it until, at the earliest day, May 1st, 1897.

The statement of this argument of Ingersoll’s opponents, by the foregoing schedule which seeks to illustrate and enforce it, is not supported by the proofs. Assume that Ingersoll was to be paid for his bricks as Myers got his contract-money from Flaherty — that is, Ingersoll s bill became due and payable when Myers actually received enough money from Flaherty to pay it. The schedule states that Myers had received from Flaherty during March, 1897, $3,000, a sum largely in excess of Ingersoll’s bill for bricks, all furnished during March, except $6 worth on April 1st; but the statement that payments were made to Myers of $3,000 “ during March ” is largely assumption. Myers was put on the stand to prove when payments were made, and was unable to name the date of a single payment which he received. He “guessed” the first payment was in March, and “ guessed ” the second was three weeks after the first. As the work was only begun on March 4th, and Myers was obliged to get an architect’s certificate to entitle him to each payment, and to demand his money from Mr. Flaherty and procure him to pay the amount earned, my impression from the evidence is that the money was paid him (at least the second $1,500) after April 1st, and therefore after Ingersoll had furnished all the bricks for which he now by his stop-notice claims payment. By this [472]*472second $1,500 Myers would have received enough to have fully paid Ingersoll, and thus the latter’s money would have been payable under any construction of the contract between Ingersoll and Myers.

But the evidence does not sustain the assertion that, by the contract between Ingersoll and Myers, the time of the payment for the bricks was fixed to depend upon Myers’ receipt of his contract-money.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anchor Steam Bottling Works v. Baumle
1916 OK 156 (Supreme Court of Oklahoma, 1916)

Cite This Page — Counsel Stack

Bluebook (online)
44 A. 186, 58 N.J. Eq. 467, 13 Dickinson 467, 1899 N.J. Ch. LEXIS 64, Counsel Stack Legal Research, https://law.counselstack.com/opinion/flaherty-v-atlantic-lumber-co-njch-1899.