Fla. Ch. of Sierra Club v. Orlando Util. Com'n

436 So. 2d 383
CourtDistrict Court of Appeal of Florida
DecidedAugust 18, 1983
Docket83-77
StatusPublished
Cited by7 cases

This text of 436 So. 2d 383 (Fla. Ch. of Sierra Club v. Orlando Util. Com'n) is published on Counsel Stack Legal Research, covering District Court of Appeal of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fla. Ch. of Sierra Club v. Orlando Util. Com'n, 436 So. 2d 383 (Fla. Ct. App. 1983).

Opinion

436 So.2d 383 (1983)

The FLORIDA CHAPTER OF the SIERRA CLUB, a Non-Profit Corporation, Appellant,
v.
ORLANDO UTILITIES COMMISSION, Appellee.

No. 83-77.

District Court of Appeal of Florida, Fifth District.

August 18, 1983.

*384 Irby G. Pugh, Orlando, for appellant.

Thomas B. Tart, Staff Counsel, Orlando Utilities Commission, Orlando, and Ken Van Assenderp of Young, Van Assenderp, Varnodoe & Benton, P.A., Tallahassee, for appellee.

J. Alan Cox, Asst. Gen. Counsel, Dept. of Environmental Regulation, Tallahassee, for appellee Dept. of Environmental Regulation.

William H. Green, Gary P. Sams and Elizabeth C. Bowman of Hopping, Boyd, Green & Sams, Tallahassee, for amicus curiae, Florida Electric Power Coordinating Group, Inc.

COBB, Judge.

The Florida Chapter of the Sierra Club (Sierra) appeals from a certification order for the proposed Curtis H. Stanton Energy Center, Unit 1, a 415-megawatt coal-fired power plant to be built by the Orlando Utilities Commission in Orange County. We affirm.

The order, issued by the Governor and Cabinet under the Florida Electrical Power Plant Siting Act (FEPPSA), sections 403.501 to 403.517, Florida Statutes (1981), is the final step in the process for certification of power plants in Florida. Before turning to the facts of the instant appeal, a brief outline of the statutory process of certification is in order.

The FEPPSA was adopted initially in 1973, with the legislative intent clearly spelled out in section 403.502, Florida Statutes (1981), which states in pertinent part:

The Legislature finds that the efficiency of the permit application and review process at both the state and local level would be improved with the implementation of a process whereby a permit application *385 would be centrally coordinated and all permit decisions could be reviewed on the basis of standards and recommendations of the deciding agencies. It is the policy of this state that, while recognizing the pressing need for increased power generation facilities, the State shall ensure through available and reasonable methods that the location and operation of electrical power plants will produce minimal adverse effects on human health, the environment, the ecology of the land and its wildlife, and the ecology of state waters and their aquatic life. It is the intent to seek courses of action that will fully balance the increasing demands for electrical power plant location and operation with the broad interest of the public. Such action will be based on these premises:
(1) To assure the citizens of Florida that operation safeguards are technically sufficient for their welfare and protection.
(2) To effect a reasonable balance between the need for the facility and the environmental impact resulting from construction and operation of the facility, including air and water quality, fish and wildlife, and the water resources and other natural resources of the state.
(3) To provide abundant, low-cost electrical energy.

The process of certification involves four agencies of the state government: The Department of Environmental Regulation, The Department of Veteran and Community Affairs, the applicable water management district, and the Public Service Commission (PSC). The initial application for certification is filed with the DER § 403.504(3), which then furnishes the application to the other three agencies, with each having a specific responsibility in the application process.

The Department of Veteran and Community Affairs reports to the DER on the compatibility of the proposed electrical power plant with the state comprehensive plan. The water management district, in whose jurisdiction the proposed electrical plan is located, prepares a report on matters within its field of expertise, and the Public Service Commission prepares a report on the present and future need for the electrical generating capacity to be supplied by the power plant. § 403.507. The affirmative determination of need by the PSC is a condition precedent to the conduct of a certification hearing. § 403.508(3). These reports are collected by the DER, which then recommends either to grant or to deny the power plant application in a report submitted to the certification hearing officer. § 403.504(8).

While the DER is collecting the reports from the other agencies, a land use hearing is conducted in the county of the proposed site of the plant. The sole issue for determination at this hearing is whether or not the proposed site is consistent and in compliance with existing land use plans and zoning ordinances. The order of the hearing officer from this hearing is then reviewed by the Siting Board, which consists of the Governor and Cabinet, for final approval. § 403.508(2).

The final stage of the certification process is a certification hearing held by a hearing officer from the Division of Administrative Hearings. § 403.508(3). Following the hearing and the officer's recommendation and findings of fact and law, the Board reviews that order. If the order is approved and certification granted, the construction and operation of the power plant may begin. § 403.511. The issuance or denial of the certification by the Board constitutes final administrative action required as to the application. § 403.509(3). The proceedings under Chapter 403 are reviewable as provided in Chapter 120. § 403.513.

In the instant case, no issue is raised regarding the reports filed by the Department of Veteran Affairs or the St. Johns Water Management District, both of which agreed that the power plant was acceptable in their respective areas. Additionally, the zoning and land use hearing, which the Sierra Club attended in August, 1981, but at which it produced no witnesses or evidence, *386 led to a determination that the power plant was in compliance with existing land use plans and zoning ordinances of Orange County. This recommendation was approved by the Siting Board on October 21, 1981.

The focus of this appeal is the report issued by the PSC on October 9, 1981, finding that a need exists for the proposed power plant. In the report, the PSC found that the plant will provide significant economic benefits to Florida in terms of supplying alternatives to oil-fuel generation, displacing approximately 3,750,000 barrels of foreign oil per year. The Commission found that the plant will lead to lower costs to the utility customers by 1987, and lead to fuel diversity free from foreign embargoes. The PSC reached this determination after two days of public hearings on August 13 and 14, 1981. Sierra did not participate at any point in the PSC hearings, but sent a letter to the PSC, urging it to consider alternative conservation measures.

Following the submission of the reports, the DER issued an analysis recommending certification of the plant, subject to some 34 conditions, which were agreed to by the Orlando Utilities Commission.

The certification hearing in the instant case was held on March 15-22, 1982, with the Sierra Club, as well as other parties, participating in the hearing. Following the taking of much testimony, as well as the receiving of the DER's report, the hearing officer issued his findings of fact, conclusions of law and recommended order on November 12, 1982. In the order, the hearing officer described the background of the area, the plans for the plant, its effect on air, water and wildlife, and the testimony presented at trial regarding these matters. The officer concluded that:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Seminole Electric Cooperative, Inc. v. Department of Environmental Protection
985 So. 2d 615 (District Court of Appeal of Florida, 2008)
Seminole Elec. Co-Op. v. Dep
985 So. 2d 615 (District Court of Appeal of Florida, 2008)
Florida Sugar Cane League v. State
580 So. 2d 846 (District Court of Appeal of Florida, 1991)
Bean v. CNA Insurance
15 Fla. Supp. 2d 142 (State of Florida Division of Administrative Hearings, 1985)
Collier Med. Center v. STATE, DEPT. OF H. & RS
462 So. 2d 83 (District Court of Appeal of Florida, 1985)
Department of Education v. Gardener
7 Fla. Supp. 2d 165 (State of Florida Division of Administrative Hearings, 1984)
Gaines v. City of Orlando
450 So. 2d 1174 (District Court of Appeal of Florida, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
436 So. 2d 383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fla-ch-of-sierra-club-v-orlando-util-comn-fladistctapp-1983.