Fitzsimonds v. MJ HUGHES CONSTRUCTION, INC.

226 P.3d 107, 233 Or. App. 447, 2010 Ore. App. LEXIS 51
CourtCourt of Appeals of Oregon
DecidedJanuary 27, 2010
Docket0602879; A138173
StatusPublished

This text of 226 P.3d 107 (Fitzsimonds v. MJ HUGHES CONSTRUCTION, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fitzsimonds v. MJ HUGHES CONSTRUCTION, INC., 226 P.3d 107, 233 Or. App. 447, 2010 Ore. App. LEXIS 51 (Or. Ct. App. 2010).

Opinion

*449 EDMONDS, S. J.

Claimant seeks judicial review in this workers’ compensation case of the board’s order ruling that no penalties or attorney fees are awardable under ORS 656.268(5)(d) and ORS 656.382(1) for the alleged unreasonable failure to respond to claimant’s request for claim closure. On review, we affirm.

Claimant suffered a compensable injury in February 2005, which employer accepted as a right shoulder condition. In March 2006, claimant’s attending physician determined that the condition was medically stationary and asked employer to schedule a physical capacities evaluation (PCE) for claimant. That evaluation was performed on April 19, 2006, and concluded that claimant was capable of performing light to medium work with occasional overhead reaching, crawling, and vertical ladder climbing. On April 24, 2006, claimant requested that a notice of closure be issued closing the claim. On May 1, 2006, employer’s representative informed claimant that the claim would not close until claimant’s attending physician had the opportunity to examine the evaluation. That same day, claimant’s attending physician considered the evaluation and concurred in its findings. Employer’s representative received the attending physician’s report on May 4, 2006, that concurred with the evaluation.

On May 5, 2006, claimant requested a hearing before the hearings division, asserting that employer had failed to timely respond to his request to close his claim. Claimant then made a second request for closure on May 11, 2006. On May 17, 2006, employer’s counsel discussed claimant’s shoulder condition with his attending physician and sent him a letter summarizing the conversation. The attending physician signed and returned the letter to employer’s attorney on May 22, 2006, and employer issued a notice of closure without a permanent disability award on May 25, 2006. On June 2,2006, claimant requested reconsideration of the closure order, and an order on reconsideration awarded claimant permanent disability.

In the hearing before the administrative law judge (ALJ), claimant sought penalties under ORS 656.268(5)(d) *450 and attorney fees under ORS 656.382C1) 1 2 for employer’s alleged unreasonable refusal to close the claim and its failure to issue a notice of closure or refusal to close within 10 days of his request. The AL J ruled in favor of claimant, and employer appealed to the board. The board held that employer’s conduct was reasonable and therefore reversed the ALJ’s award of penalties and attorney fees.

On review, claimant argues, under his first assignment of error, that employer had sufficient information to close the claim on May 4, 2006, and was required by ORS 656.268(5)(b) to issue a notice of closure or refusal to close no later than that date. As to his May 11, 2006, request for closure, claimant contends that employer was required by the statute to issue a notice of closure or refusal to close by May 21, 2006. In claimant’s view, the failure to close by those deadlines was unreasonable as a matter of law. He explains that employer’s refusal to close within the strict time period set by ORS 656.268(5)(b) cannot be deemed to be reasonable conduct absolving it of the penalties the legislature imposed to ensure compliance with the statute.

Employer counters that its

“refusals to close the claim were not unreasonable based on the medical evidence in this case. ORS 656.268(1) and OAR 436-030-0020(l)[ 2 ] provide that a self-insured employer has 14 days to close a claim from the date it receives sufficient information to warrant claim closure. Here, the Workers’ Compensation Board (board) found there was insufficient *451 sufficient [sic] information to close the claim until May 22, 2006. * * * That finding is supported by substantial evidence and substantial reason.”

In his reply brief, we understand claimant to reiterate his contention that the 10-day period provided for in ORS 656.268(5)(b) for an employer to close a claim or refuse to close a claim is an absolute requirement that cannot be extended by administrative rule and that employer had an obligation under the statute as a matter of law to respond to claimant’s requests to close his claim no later than May 4 and May 21, 2006. Alternatively, claimant argues that the board’s ruling that employer acted reasonably lacks substantial reason and that remand is required for the board to provide a rational explanation of its decision. Finally, claimant asserts:

“[I]n reviewing claimfant’s] entitlement to a penalty under ORS 656.268(5)(d), the Board was required to determine whether in response to claimant’s April 24,2006 request for claim closure!,] the employer refused to close the claim and whether that refusal was unreasonable under the circumstances then existing. The Board was then required to separately determine whether employer’s conduct in response to claimant’s May 11, 2006 request for claim closure was a refusal to close the claim and whether that refusal was unreasonable under the circumstances existing at that time. Because the Board failed to make specific determinations of these questions as required by Red Robin International v. Dombrosky, 207 Or App 476, 481, 142 P3d 493 (2006), remand to the Board is required.”

Initially, we turn to claimant’s assertion that ORS 656.268(5)(d) required the board to separately assess each request and each response or nonresponse for closure under a standard of reasonableness based on the circumstances that existed at the time of the request for closure. Claimant’s contention is correct as a matter of an abstract principle of law. Cayton v. Safelite Glass Corp., 232 Or App 454, 462, 222 P3d 1134 (2009). However, our review of the record before the board does not reveal that claimant made that argument to the board. In its opinion, the board acknowledged that claimant made two requests for closure — one on April 24, 2006, *452 and one on May 11, 2006 — but it held that that fact “does not change the outcome of this case.” Rather, it found that,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Liberty Northwest Ins. Corp. v. Verner
911 P.2d 948 (Court of Appeals of Oregon, 1996)
Cayton v. Safelite Glass Corp.
222 P.3d 1134 (Court of Appeals of Oregon, 2009)
Red Robin International v. Dombrosky
142 P.3d 493 (Court of Appeals of Oregon, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
226 P.3d 107, 233 Or. App. 447, 2010 Ore. App. LEXIS 51, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fitzsimonds-v-mj-hughes-construction-inc-orctapp-2010.