Fiske-Marshall Manufacturing Co. v. Rabus & Toeller

194 Iowa 1193
CourtSupreme Court of Iowa
DecidedDecember 15, 1922
StatusPublished
Cited by2 cases

This text of 194 Iowa 1193 (Fiske-Marshall Manufacturing Co. v. Rabus & Toeller) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fiske-Marshall Manufacturing Co. v. Rabus & Toeller, 194 Iowa 1193 (iowa 1922).

Opinion

Arthur, J.

Appellees held a patent for an office appliance, a copyholder, called the Adapto Line Guide, which they wished to manufacture, or have manufactured, and conferences were held between appellees and appellants respecting the making of dies and tools for the manufacture of the Adapto -Line Guide, in pursuance of which appellants addressed to appellees,' on November 13, 1919, a letter as follows:

“Yours of November 10th at hand, in reply will say. We can start on dies as soon as you place your order. Of course we will put our bid in writing and your order will be the acceptance. The dies can probably be finished in 6 — 8 weeks.”

Afterwards, on the same day, appellants submitted to ap-pellees a proposition in writing, as follows:

“We will build and test out all dies, punches, forms, stops and gauges to make the parts of your copyholder as per sample furnished, for the sum of $1,400. Terms: One third down with order. Balance when completed.”

On December 16th, appellees accepted appellants’ proposition, and made the initial payment on the contract of $466.67.

I. Appellees’ claim was that appellants failed to perform their part of the contract within the time agreed upon; that, by reason of such failure, appellees elected to and did rescind their agreement with appellants, and demanded damages by reason of breach of the agreement, in the amount of $466.67, the amount [1195]*1195appellees had paid on the contract, and other damages for loss of profits.

Appellants denied appellees’ right of rescission; denied that rescission had been effected; and averred that the goods mentioned in the contract had been manufactuled since about June 1, 1920, and were ready for delivery to appellees, and that they tendered delivery of the manufactured articles to appellees at the time of the trial. In their counterclaim, appellants alleged that they had in every way completed their contract, and had the goods ready for delivery, as agreed, and demanded the balance due on the contract, in the amount of $933.33.

Both appellees’ cause of action alleged in the petition and appellants’ cause of action alleged in the counterclaim were submitted to the jury. From the judgment rendered on the verdict, this appeal is prosecuted. The right of recovery of appellees for alleged breach of contract and right of recovery of appellants on their counterclaim center on whether appellees had the right to rescind, under the facts shown in evidence, and whether they did rescind: that is, whether appellees may recover from appellants the $466.67 which they had paid on the contract, or whether appellants showed that they had finished manufacturing the articles mentioned in the contract and were ready to deliver them to the plaintiff in time contemplated by the contract, and, having tendered delivery, were entitled to recover the balance due under the terms of the contract of $933.33.

II. Oral testimony was introduced by both parties, bearing on the time in which the articles mentioned in the contract were to be furnished. All the talk concerning this matter seems to have been between Marshall, of appellees’ firm, and Rabus, of the appellant firm, and to have occurred at times from late in October or early in November, 1919, to May, 1920. Marshall testified that there was talk between him and Rabus as to the length of time it would take to complete the order for making the dies, etc., and says that Rabus told him it would be from ‘ ‘ 6 to 8 weeks time. It might be delayed some little longer than that, which I agreed to, but not later than the 1st of March following our conversation,” — referring evidently to their early conversation in the fall of 1919. Marshall testified that, shortly after his firm made the initial payment, on December 16th, he [1196]*1196bad a talk witb Rabus with reference to the time that the contract would be completed, and had several talks with him after-awards on-the same point, and that Rabus said that they were working on that right along, but that they would be out, he anticipated, at least by March 1st; that, when the order was first placed, he made special inquiry of Rabus, because he had a position in Chicago which he would have to quit, so as to come out and take care of this business, “if it would be any later than March 1st;” and that Rabus said he saw no reason why it should be, for the material for the making of the dies was there. This talk was had at Christmas time. Marshall testified: “I saw Mr. Rabus on an average of twice a week until I left Cedar Rapids in May. ’ ’ When asked why he went to see Rabus, he answered, “Trying to get some satisfaction as to when 1 could get delivery of these dies. ’ ’

Rabus’s testimony was that he first met Marshall early in November, when Marshall produced some of. the parts of the Adapto Line Guide, and asked his firm to bid on the dies to manufacture same; that Marshall wanted him to limit or fix the time within which they could make the dies and punches with which to make the machine; that he told Marshall that it was impossible to fix the time limit, under the circumstances existing; that he told him of some of the difficulties that they were likely to .encounter, such as procuring “tool steel” necessary for that particular kind of work, which was hard to get and slow in delivery, and that the “labor market was very much unsettled,” and that they could hardly get help that was suitable for that work. Rabus said:

“There was no talle at any time, as I remember, between Mr. Marshall and myself that we could get his stuff out not later than the 1st of March.”

Rabus testified that the work was completed at the end of May, 1920; that the last time he had seen Marshall was about the 1st of March, 1920. Rabus said that no time was fixed for fulfilling the contract; that he wrote the letter in which the clause appears “the dies can probably be finished in six or eight weeks, ’ ’ and by that he meant:

“If conditions did not get any worse, the dies could be finished in that time. I meant to convey to Mr. Marshall in [1197]*1197that letter that the dies could be furnished in probably six or eight weeks. That was only an opinion I g’ave him. I made' no agreement giving the minimum or maximum in which we could complete the contract. I gave that letter to Mr. Marshall as a basis of price on which to accept the order.”

We have not attempted to set out all the testimony of Marshall and Rabus, but the foregoing is the substance of their testimony bearing on the time within which the articles mentioned in the contract were to be finished. Appellees’ right of recovery, based on nonperformance of the contract and right of rescission, largely depended upon whether there was an agreed time of performance, under the evidence. Also, appellants’ right to recover on their counterclaim depended on the same proposition.

III. Appellants urge that it was error to submit the issue of rescission to the jury, as they claim that there was no pleading or evidence to sustain rescission, and that their motion made at the close of all the evidence, to direct a verdict on their counterclaim, should have been sustained. Such contention is without merit. Appellees alleged election to rescind on the ground of breach on the part of appellants, and demanded return of the initial payment made on the contract. In support of their right of rescission, appellees introduced in evidence correspondence between them and appellants.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

C. L. Percival Co. v. Sea
222 N.W. 886 (Supreme Court of Iowa, 1929)
Towberman v. Des Moines City Railway Co.
211 N.W. 854 (Supreme Court of Iowa, 1927)

Cite This Page — Counsel Stack

Bluebook (online)
194 Iowa 1193, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fiske-marshall-manufacturing-co-v-rabus-toeller-iowa-1922.