Fisk Electric Company v. Webcor Builders, Inc.

CourtDistrict Court, N.D. California
DecidedApril 7, 2023
Docket3:18-cv-07671
StatusUnknown

This text of Fisk Electric Company v. Webcor Builders, Inc. (Fisk Electric Company v. Webcor Builders, Inc.) is published on Counsel Stack Legal Research, covering District Court, N.D. California primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fisk Electric Company v. Webcor Builders, Inc., (N.D. Cal. 2023).

Opinion

1 2 3 4 UNITED STATES DISTRICT COURT 5 NORTHERN DISTRICT OF CALIFORNIA 6 7 FISK ELECTRIC COMPANY, Case No. 18-cv-07671-EMC

8 Plaintiff, ORDER GRANTING PLAINTIFF’S 9 v. MOTION FOR LEAVE TO FILE THIRD AMENDED COMPLAINT 10 OBAYASHI CORPORATION, et al., Docket No. 137 11 Defendants.

12 13 14 This case relates to the Transbay Transit Center Project. In 2009, the Transbay Joint 15 Powers Authority (“TJPA”) entered into a written contract with the Webcor/Obayashi Joint 16 Venture (“WOJV”) related to the construction of the Project. Under the contract – hereinafter 17 referred to as the Prime Contract – WOJV was to provide certain pre-construction services, serve 18 as the construction manager/general contractor, and manager/administer subcontracts with trade 19 subcontractors. WOJV subsequently entered into a written contract – hereinafter referred to as the 20 Subcontract – with Fisk Electric Company (“Fisk”), under which Fisk agreed to provide electrical 21 work for the Project. 22 In the case at bar, Fisk has sued, inter alia, the WOJV in federal court, primarily for breach 23 of contract. For example, Fisk asserts that it was not compensated for the extra work that it did on 24 the Project (resulting from, e.g., changes to the work that WOJV made) or even for some of the 25 work that it was originally contracted to do. Fisk also asserts that WOJV failed to complete 26 precedent work necessary to allow Fisk to timely perform its scope of work and that WOJV 27 improperly “de-scoped” portions of the Subcontract and assigned the work to other contractors. 1 (“TAC”). Specifically, Fisk seeks to add a claim for damages against the WOJV Defendants1 2 based on a violation of a statutory duty. The statute at issue is California Public Contract Code § 3 4107 which provides, inter alia, that a “prime contractor whose bid is accepted may not: (a) 4 Substitute a person as subcontractor in place of the subcontractor listed in the original bid,” except 5 where the awarding authority consents to substitution in certain limited circumstances. Cal. Pub. 6 Contract Code § 4107(a). As indicated by this language, the new proposed claim relates to Fisk’s 7 existing allegations in the operative second amended complaint (“SAC”) that WOJV improperly 8 de-scoped portions of the Subcontract and gave the work to other contractors. See SAC ¶ 27(f) 9 (alleging that WOJV Defendants breached the Subcontract by “improperly de-scoping portions of 10 the . . . Subcontract and assigning said work to other contractors in violation of California law”). 11 Having considered the parties’ briefs and accompanying submissions as well as the oral 12 argument of counsel, the Court hereby GRANTS Fisk’s motion. 13 I. DISCUSSION 14 A. Legal Standard 15 A motion for leave to amend is subject to Federal Rule of Civil Procedure 15. Rule 15 16 provides in relevant part that a “court should freely give leave [to amend] when justice so 17 requires.” Fed. R. Civ. P. 15(a)(2). Factors that a court considers in determining whether to give 18 leave to amend include “undue delay, the movant’s bad faith or dilatory motive, repeated failure to 19 cure deficiencies by amendments previously allowed, undue prejudice to the opposing party, and 20 futility.” Brown v. Stored Value Cards, Inc., 953 F.3d 567, 574 (9th Cir. 2020). In the instant 21 case, WOJV simply argues that amendment – i.e., adding a claim for breach of statutory duty – 22 would be futile. 23 B. California Public Code § 4107 24 As noted above, the statute that is implicated in Fisk’s proposed amendment is California 25 Public Contract Code § 4107. Section 4107 provides as follows:

26 A prime contractor whose bid is accepted may not: 27 1 (a) Substitute a person as subcontractor in place of the subcontractor listed in the original bid, except that the awarding authority . . . 2 may . . . consent to the substitution of another person as a subcontractor in any of the following situations: 3 (1) When the subcontractor listed in the bid, after having had a 4 reasonable opportunity to do so, fails or refuses to execute a written contract for the scope of work specified in the 5 subcontractor’s bid and at the price specified in the subcontractor’s bid, when that written contract . . . is 6 presented to the subcontractor by the prime contractor.

7 (2) When the listed subcontractor becomes insolvent or the subject of an order for relief in bankruptcy. 8 (3) When the listed subcontractor fails or refuses to perform his 9 or her subcontract.

10 (4) When the listed subcontractor fails or refuses to meet the bond requirements of the prime contractor as set forth in 11 Section 4108.

12 (5) When the prime contractor demonstrates to the awarding authority . . . that the name of the subcontractor was listed as 13 the result of an inadvertent clerical error.

14 (6) When the listed subcontractor is not licensed pursuant to the Contractors License Law. 15 (7) When the awarding authority . . . determines that the work 16 performed by the listed subcontractor is substantially unsatisfactory and not in substantial accordance with the 17 plans and specifications, or that the subcontractor is substantially delaying or disrupting the progress of the work. 18 (8) When the listed subcontractor is ineligible to work on a 19 public works project pursuant to Section 1777.1 or 1777.7 of the Labor Code. 20 (9) When the awarding authority determines that a listed 21 subcontractor is not a responsible contractor.

22 Prior to approval of the prime contractor’s request for the substitution, the awarding authority, or its duly authorized 23 officer, shall give notice in writing to the listed subcontractor of the prime contractor’s request to substitute and of the reasons for 24 the request. The notice shall be served by certified or registered mail to the last known address of the subcontractor. The listed 25 subcontractor who has been so notified has five working days within which to submit written objections to the substitution to 26 the awarding authority. Failure to file these written objections constitutes the listed subcontractor’s consent to the substitution. 27 subcontractor of a hearing by the awarding authority on the 1 prime contractor’s request for substitution.

2 (b) Permit a subcontract to be voluntarily assigned or transferred or allow it to be performed by anyone other than the original 3 subcontractor listed in the original bid, without the consent of the awarding authority . . . . 4 (c) Other than in the performance of “change orders” causing 5 changes or deviations from the original contract, sublet or subcontract any portion of the work in excess of one-half of 1 6 percent of the prime contractor’s total bid as to which his or her original bid did not designate a subcontractor. 7 8 Cal. Pub. Contract Code § 4107. 9 In Southern California Acoustics Co. v. C.V. Holder, Inc., 71 Cal. 2d 719 (1969), the 10 California Supreme Court commented on the legislative history of § 4107. It noted that, before 11 the Subletting and Subcontracting Fair Practices Act was adopted in 1963, “it was settled that the 12 Government Code sections governing subcontracting, which the act superseded, conferred no 13 rights on subcontractors.” Id. at 724. The Government Code sections at issue were designed “to 14 provide an opportunity to the awarding authority to investigate and approve the initial 15 subcontractors and any proposed substitutions.” Id. at 725.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Danica Brown v. Stored Value Cards, Inc.
953 F.3d 567 (Ninth Circuit, 2020)
In re Buckley
10 P. 69 (California Supreme Court, 1886)
Southern California Acoustics Co. v. C. V. Holder, Inc.
456 P.2d 975 (California Supreme Court, 1969)

Cite This Page — Counsel Stack

Bluebook (online)
Fisk Electric Company v. Webcor Builders, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/fisk-electric-company-v-webcor-builders-inc-cand-2023.