Fisher v. Burroughs Adding Machine Co.

121 N.W. 756, 157 Mich. 126, 1909 Mich. LEXIS 968
CourtMichigan Supreme Court
DecidedJune 7, 1909
DocketDocket No. 130
StatusPublished
Cited by2 cases

This text of 121 N.W. 756 (Fisher v. Burroughs Adding Machine Co.) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fisher v. Burroughs Adding Machine Co., 121 N.W. 756, 157 Mich. 126, 1909 Mich. LEXIS 968 (Mich. 1909).

Opinion

McAlvay, J.

Plaintiff in 1904 contracted in writing with the American Arithmometer Company to do the mason work in the construction of a factory in Detroit, according to plans and specifications of the architect, for the sum of $19,769. Defendant is the successor of the American Arithmometer Company, and as such responsible for any judgment plaintiff may recover. During the construction certain changes from the original plans and specifications were ordered and directed to be performed by the architect, which were made by plaintiff with the knowledge of the superintendent of construction. After certain delays caused by the owner not securing certain material, the work under plaintiff’s contract was completed, shortly before which time plaintiff was taken seriously ill. During the prosecution of the work, plaintiff, [127]*127by reason of delays and losses caused by the company, was unable to pay for some of the materials which were used in the construction of the building, and several mechanics’ liens were filed. Later foreclosure proceedings of one of these liens were begun. Plaintiff was also sued by one of his creditors in justice’s court, and the defendant company garnished, and on an appeal by plaintiff the president of the company signed his appeal bond. Under these circumstances, and while plaintiff was confined to his house by sickness, and was not present at any meetings between the attorneys for the parties and defendant’s agents, the following agreement in writing was made and executed

“An agreement made by and between the C. H. Little Company of the first part, and the American Arithmometer Company of the second part, and George W. Fisher of the third part, under date of May 19, 1905, was duly proven and introduced in evidence by the defendant and marked Exhibit G. and is as follows:
“It is hereby agreed by and between the C. H. Little Co., of the first part, the American Arithmometer Company of the second part, and George W. Fisher of the third part, as follows:
“ Whereas, there is a balance owing to the third party from the second party of $6,211.05 for materials furnished and labor performed in construction of the second party’s factory at the corner of Second and Amsterdam avenues, Detroit, Michigan; and, whereas, liens have been filed upon said factory premises by the following parties for materials and labor furnished to said Fisher for the amounts set opposite their respective names, to wit:
“Trussed Concrete Steel Co...................... $236 16
Philip Carey Mfg. Co........................... 264 95
The C. H. Little Co............................. 3,672 81
Michigan Pressed Brick Co_____________________ 677 50
Garner Bros.................................... 24 50
Larkins Brick Co..........-....._.............. 1,207 50.
Sheehan Artificial Stone Co. __.................. 308 75
Elmer Jones.......................-........... 1,524 72
E. B. Holmes & Co.........-___________________ 823 43
$8,739 32
[128]*128—and a suit at law has been commenced and is now pending on appeal in the circuit court for the county of Wayne by said Sheehan Artificial Stone Company against said Fisher for the same claim for which it has filed said lien, one Joseph Boyer, a stockholder in said American Arithmometer Company, being surety on the appeal bond; and, whereas, it is represented by the first and third parties that the liens of the following parties may be settled for the amounts set opposite their respective names, to wit:
“Trussed Concrete Steel Co...................... $100 00
Philip Carey Mfg. Co__________________________ 200 00
The C. H. Little Co_____________________________ 2,194 41
Michigan Pressed Brick Co...................... . 474 25
Larkins Brick Co________________________________ 1,107 50
Garner Bros.___________________________________ 14 70
$4,090 86
—and, whereas, it is represented by the said Fisher that good defense exists to the remaining lien claims and the said suit at law or to some part thereof:
“It is agreed by the respective parties, the agreement of each being in consideration of the agreements of the others as follows:
“Said the C. H. Little Company agrees:
“1. To protect and save harmless said American Arithmometer Company from all loss, costs, damages and expense on account of or by reason of any and all of the said lien claims hereinbefore referred to and all litigation thereon, and of the settlement of the claims whereof the settlement is hereby contemplated.
“3. To assume and carry on at its own expense the defense of said suit at law and of all of the lien claims hereinbefore mentioned until final adjudication or settlement thereof and to pay any amount necessary to effect a discharge and satisfaction of record of said suit, and of all of said claims as finally determined by adjudication or settlement in excess of the amount of $5,961.05, hereinafter provided to be paid from the fund in the second party’s hands.
‘ ‘ The second party agrees:
“1. To purchase the lien claims of the following named parties at the amounts set opposite their respective names if settlement can be effected at said amounts, paying [129]*129therefor from the said balance owing to third party hereto, to wit:
“ Trussed. Concrete Steel Co...........-....... 5100 00
Philip Carey Mfg. Co________________________ 200 00
The C. H. Little Co..........'............... 2,194 41
Garner Bros................................. 14 70
Michigan Pressed Brick Co................... 474 25
Larkins Brick Co............................ 1,107 50
54,090 86
—taking assignments of the claims settled in the name of some person selected by itself which assignments shall be held for the purposes hereinafter provided.
“2. To pay W illard E. W arner, attorney for said Fisher, the sum of $250.00 from said balance owing third party, this payment being made by direction of the first and third parties and for services performed for the third party.
“3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fisher v. Burroughs Adding Machine Co.
132 N.W. 101 (Michigan Supreme Court, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
121 N.W. 756, 157 Mich. 126, 1909 Mich. LEXIS 968, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fisher-v-burroughs-adding-machine-co-mich-1909.