Fischer v. Schram

173 A.D. 147, 159 N.Y.S. 496, 1916 N.Y. App. Div. LEXIS 10383

This text of 173 A.D. 147 (Fischer v. Schram) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fischer v. Schram, 173 A.D. 147, 159 N.Y.S. 496, 1916 N.Y. App. Div. LEXIS 10383 (N.Y. Ct. App. 1916).

Opinion

McLaughlin, J.:

On the llth of June, 1911, Nathan Herrmann, the defendants’ testator, offered to build- for and donate to the Jewish Protectory and Aid Society, a charitable organization, a building for use as a trade school. His offer was formally accepted on July 21, 1911.

Plaintiff is an architect, who, prior to the making of the offer by Herrmann, had, at his request, prepared preliminary sketches for the building. After the acceptance of the offer Herrmann, on the 25th of July, 1911, entered into two written agreements with the plaintiff. The first provided for the erection by the plaintiff as contractor of a frame and stucco building in conformity with the preliminary sketches at a cost of not to exceed $18,800. The second provided that Herrmann would pay the plaintiff six per cent of $18,800, viz., $1,128 for all architectural services required or desirable for the plan-' ning, erection and supervision of Nathan Herrmann Agricultural and Trades School Building, * * * the services to consist of the necessary conferences, the preparation of preliminary studies, working drawings, specifications, large scale and full size detail drawings, and of the general direction and supervision of the work * *

The complaint alleges, in substance, that subsequent to the making of these contracts the plans and specifications referred to therein were modified with the knowledge and consent of Dr. Charles Schram, Herrmann’s agent, which necessitated the drafting of new plans and specifications, with the result that the cost of the building was increased from $18,800 to $48,800, and that thereby the agreed and reasonable value of plaintiff’s services as architect was increased to six per cent of the latter sum, viz., $2,928, of which only $828 has been paid. Judgment was demanded for the amount remaining due. The [149]*149answer denied that there was anything due the plaintiff; that the agreements between him and defendants’ testator were ever modified or superseded, and set up a counterclaim for $30,000 damages alleged to have been caused by the plaintiff’s act in increasing the cost of the building from $18,800 to $48,800. The jury rendered a verdict in favor of the plaintiff for the amount claimed by him and against the defendants on their counterclaim. The defendants appeal from a judgment entered upon the verdict (the counterclaim not being mentioned or referred to therein) and an order denying a motion for a new trial, as well as an order granting plaintiff a certificate for costs.

The fact is undisputed that plaintiff did prepare plans and specifications for a much more elaborate building than that contemplated by the preliminary .sketches, by reason of which the construction of the building cost $18,800 instead of $18,800, as originally planned. The main points of difference were that the plans and specifications provided for a basement under the entire building instead of under only a part, for the rearrangement of rooms, the addition of a balcony, and for the use of brick and stucco instead of frame and stucco.

The question presented upon the appeal is whether or not, by reason of the changes made by the plaintiff, Herrmann became obligated to pay him a sum greater' than that fixed by the written contract of employment. There was no proof that any other or greater compensation was agreed upon. The recovery is predicated upon plaintiff’s testimony to the effect that the reasonable value of his services was six per cent of the total cost of the building. This recovery cannot be sustained imless evidence was adduced at the trial sufficient to sustain a finding that the written agreement, by which plaintiff was to be paid $1,128, was modified so as to enable him to recover six per cent upon the total cost of the building. Ho evidence was offered that Herrmann personally knew of or assented to any change in the plans for the construction of the building, or to the modification of either of the contracts of July 25, 1911. It may well be doubted whether plaintiff proved that Dr. Schram’s authority as agent was sufficient to permit him to consent to a modification or abandonment of those contracts. But even if that [150]*150fact be assumed, I am unable to discover any evidence in the record, either that the contracts of July 25, 1911, were modified, or that they were in fact abandoned and new contracts made. Substantially the only evidence bearing upon this question is the disputed testimony of the plaintiff himself to the effect that at a meeting of the board of directors of the protectory, at which he and Dr. Schram were present, the changes above referred to were suggested by the directors, and that Dr. Schram then said to the plaintiff: “You have heard what the committee desires; draw plans in accordance with those instructions. Draw the building to be of brick. Draw the building with the entire basement and provide a balcony and place the assembly room on the ground floor.” Any effect, however, which might be claimed from this testimony is completely destroyed when it was conclusively established that the meeting of the directors at which these changes were alleged to have been ordered by Dr. Schram, and the alleged statements made by him, was held on July 20, 1911 —five days before the contracts between Herrmann and the plaintiff were executed. It needs no argument to demonstrate the absurdity of the claim that these written instruments, fixing the rights and obligations of the parties to them, were modified by a conversation which took place prior to their execution. The written contracts were made for the sole purpose of fixing the rights of the parties, and any oral agreement theretofore had necessarily was merged in them. A contract cannot he changed or modified before it is made. When made, if it does not set forth the agreement, by reason of a mutual mistake, or a mistake of one of the parties and the fraud of the other, then a reformation may be had. But so long as it remains in the form in which it was executed, the rights and obligations of the parties must be determined by it. The plaintiff, doubtless recognizing the force of this rule, asserts that Dr. Schram knew of and assented to the changes which were made in the plans and specifications and the construction of the building in accordance with them, and by reason of that fact Herrmann became.bound, at least by implication, to pay the reasonable value of the services rendered, which was six per cent of the cost of the building. It may be conceded that Dr. Schram knew that the pre[151]*151liminary sketches had heen changed and the building was being constructed upon other plans, but it does not follow that he knew, at least until after Herrmann’s death, that either the cost of the building or plaintiff’s compensation would thereby be increased. The written contract as to the construction of the building provided that “the preliminary drawings may be changed or altered by the architect if deemed advisable in order to have them properly work out, but for that purpose only.” Indeed, the acts of the plaintiff himself could hardly have done otherwise than have convinced Dr. Schram that the changes would not increase either the cost of the building or plaintiff’s compensation. Thus, on September 27, 1911, he sent a letter to Dr. Schram, advising him that an application had been made to the State Board of Charities to approve the plans and specifications. In this letter he said: “I enclose a copy of original application, wherein you will notice at the bottom that I mentioned the estimated cost $30,000.00; this I did only because this amount had been published before, and has no bearing on the actual cost.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chisholm v. . Toplitz
70 N.E. 1096 (New York Court of Appeals, 1904)
Chisolm v. Toplitz
82 A.D. 346 (Appellate Division of the Supreme Court of New York, 1903)
Hecla Iron Works v. Hall
115 A.D. 126 (Appellate Division of the Supreme Court of New York, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
173 A.D. 147, 159 N.Y.S. 496, 1916 N.Y. App. Div. LEXIS 10383, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fischer-v-schram-nyappdiv-1916.