Fischbach & Moore, Inc. v. Presteel Corp.

398 A.2d 397, 1979 Me. LEXIS 627
CourtSupreme Judicial Court of Maine
DecidedMarch 1, 1979
StatusPublished
Cited by6 cases

This text of 398 A.2d 397 (Fischbach & Moore, Inc. v. Presteel Corp.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fischbach & Moore, Inc. v. Presteel Corp., 398 A.2d 397, 1979 Me. LEXIS 627 (Me. 1979).

Opinion

WERNICK, Justice.

This is an appeal by defendant J. B. Brown & Sons (Brown) from a May 3, 1978 judgment of the Superior Court (Cumberland County) adjudicating that plaintiff Fischbach & Moore, Inc. had perfected a valid and enforceable lien against Brown’s interest in certain real property upon which the contractor had made installations with Brown’s consent. Brown contends on appeal that the Superior Court Justice committed error in finding (1) that the labor and materials were “lienable” under 10 M.R.S.A. § 3251 (Supp.1978), which grants a lien on a structure to one who supplies labor and materials for “erecting, altering, moving or repairing” it, and (2) that Brown had “consented” to the work, within the meaning of the same statutory provision.

While we deny the appeal, for reasons subsequently discussed we modify the judgment to reflect that 20% of the work performed was non-lienable.

In consequence of a concerted effort by Portland’s commercial community, Presteel Corporation determined to relocate in Portland and there engage in the manufacture of pressed steel products. Although Pre-steel wished to purchase a building suitable for its operations, its financial condition *399 compelled it to lease. To facilitate Pres-teel’s move, Brown agreed to make the necessary purchase of a building and to lease it to Presteel.

Paragraph 29 of the lease executed by Brown and Presteel “authorize[d] [tjenant to install, if [t]enant so elects, ... all electric, gas and air piping, and all footings and pits for machinery as are necessary for [t]enant’s operations.” The landlord Brown was obligated to execute “instruments embodying the approval of [l]andlord” so that Presteel could obtain “any license or permit for the making of such . . . installations in, to or upon . . . [the] [l]eased [p]remises . . . .” In addition, the lease indicated that the parties recognized that the installation work tenant was authorized to have done might be “lienable”, by the provision:

“Tenant agrees to pay promptly when due all charges for labor and materials in connection with any work done by Tenant or anyone claiming under Tenant to or upon the Leased Premises so that the Leased Premises shall at all times be free of liens. ... If the improvements by Tenant exceed $10,000, then Tenant shall provide appropriate security protecting Landlord against such liens.”

Pursuant to the authorization to install “all electric, gas and air piping . necessary for [t]enant’s operations”, the tenant Presteel contracted with plaintiff for the performance of work that ended up as more than $55,000.00 worth of wiring and installation of equipment. Plaintiff was able to achieve payment of only $1,000.00 of this obligation from Presteel.

Brown has stipulated that plaintiff contractor met the statutory requirements for asserting and perfecting a claim of lien against its building, but Brown challenges the validity of the claim on the grounds that (1) the work done was not “lienable” in nature, and (2) even if it was, Brown as the “owner” of the building had not in fact given consent for the performance of the work.

1.

Except to the extent defined in part 3 of this opinion, we sustain the decision of the presiding Justice that plaintiff contractor’s work was “lienable” within the contemplation of Section 3251 and the cases construing it. The evidence sufficiently shows that the items supplied and installed were

“so connected with and attached to the building, so adapted to and necessary for the use for which it was . . . [designed], as to lead to the conclusion that it was intended to be permanently a part of it, and ... a part of the realty.” Baker v. Fessenden, 71 Me. 292, 293 (1880).

The work done was equivalent to the plainly “lienable” work of rewiring a home to accommodate such modern conveniences as air conditioning, an electric range or clothes dryer. While the tenant supplied many of the terminals, junction boxes, switches and panels that made up the system linking its machines to a 550-watt transformer, plaintiff contractor supplied all of the remaining interstitial necessities comprising a complete electrical distribution system. The work included imbedding steel grid structures in a concrete pad, as well as drilling holes in concrete and brick walls, ceilings, and floors to receive expandable lead anchors for bolting into place the boxes, conduit, busduct, panels and switches the contractor was furnishing.

Brown would characterize these alterations as within the rule that a lien cannot arise against a building where the putative lienor’s improvements were “not intended ‘to constitute a part of the building’, but were designed ‘for its more convenient use’ ”, Marshall v. Mathieu, 143 Me. 167, 171, 57 A.2d 400, 402 (1948), quoting Lambard v. Pike, 33 Me. 141, 144 (1851), and were “not essential to the use and purpose for which the building was designed by its owner . . . .” Hanson v. News Publishing Co., 97 Me. 99, 102, 53 A. 990, 991 (1902). However, unlike the temporary partitions of Hanson, supra, or the portable restaurant tables of Marshall, supra, plaintiff contractor’s work here, as de *400 scribed above, constituted the installation of fixtures and was thus lienable. Hanson, supra, at 102, 53 A. 990. An installation may facilitate the tenant’s “more convenient use” of the premises and still provide the basis for a lien enforceable against the landlord’s interest in the building. See, e. g., York v. Mathis, 103 Me. 67, 80, 68 A. 746 (1907). Even if these improvements may have been necessitated by the peculiar requirements of the tenant’s machinery, it is clear as well that they satisfy the traditional test for a fixture: annexation to the realty of an item adapted for use with that realty, with the intention that the item annexed shall become a permanent accession to the realty. Bangor Hydro-Electric Co. v. Johnson, Me., 226 A.2d 371, 378 (1967). As indicia of the intention that the annexation be permanent we note (1) the uncontroverted testimony to the effect that the wiring system installed was adaptable to a variety of manufacturing uses; (2) the provision of the lease by which the tenant was granted an option to purchase at a figure $400,000 higher than the price just paid by the landlord; (3) the provisions of Par. 29 of the lease giving the tenant authorization to go forward with “toilet facilities and related plumbing, all electric, gas and air piping”, subject to the condition that if the cost exceeded $10,000, “[tjenant shall provide appropriate security protecting Landlord against . . .' liens”; (4) the nature of the work and the manner in which it was performed, as described above; and (5) “the relation of the parties”, see Bangor Hydro-Electric, supra,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
398 A.2d 397, 1979 Me. LEXIS 627, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fischbach-moore-inc-v-presteel-corp-me-1979.