Firth v. Rehfeldt

51 N.Y.S. 980
CourtAppellate Division of the Supreme Court of the State of New York
DecidedMay 24, 1898
StatusPublished
Cited by1 cases

This text of 51 N.Y.S. 980 (Firth v. Rehfeldt) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Firth v. Rehfeldt, 51 N.Y.S. 980 (N.Y. Ct. App. 1898).

Opinion

WILLARD BARTLETT, J.

The owner of the property against .which the plaintiff seeks to enforce a mechanic’s lien appeals from a judgment of foreclosure and sale. The work was done upon premises on Henry street, in Brooklyn, under a written contract, which provided that the owner should pay the sum of $3,825 therefor as soon after the completion of the work as she could raise a first mortgage on the premises for a sufficient sum of money to pay a then-existing mortgage, and the cost of the improvements contemplated by the agreement, together with the expenses of procuring such first mortgage. The contract further provided for the payment of 6 per cent, interest on $3,825 to the plaintiff, from the date of the completion of the work to the date when the principal sum should be paid, and declared that said principal sum and interest should be secured by the bond and- mortgage of the owner. The particular property on which the work was to be done was not indicated in the ■body of the contract; but at the beginning of the specifications attached thereto it was described as “Ño. 379 Henry Street.” Further on, however, the specifications provided for building up “the door opening in party wall between Nos. 379 and 381.” The contract was dated June 5, 1895, and required that the work should be completed on September 1, 1895." It was not in fact finished until 10 weeks " later, but the referee excuses the plaintiff for the delay on account [981]*981of the interference of the defendant with the due progress of the alterations. The referee finds that the plaintiff substantially performed the contract on his part, although making a small deduction from his claim; and he also allows the plaintiff a small sum for extra work, making an aggregate of §53,808, for which amount, together with interest, he directed judgment.

As to the lien, the referee reports as follows:

“When plaintiff had completed Ms contract, plaintiff expressed to the defendant, Catherine A. C. G. Rehfeldt, a willingness to accept a mortgage upon the premises hereinbefore described for the amount of his claim, together with the bond of Mrs. Rehfeldt, to be secured by said mortgage, as was provided by his contract with Mrs. Rehfeldt that he was to take in satisfaction of Ms claim for Ms work and material; but Mrs. Rehfeldt refused to execute or deliver them to him, and the plaintiff thereupon became entitled to be paid M cash for his said work and materials, and, not being paid therefor, did on the 28th day of December, 1895, -within Mnety days after the completion of his contract, file a notice of lien in writing with the clerk of Kings county, claiming, under the statute in such case made and provided, a lien upon the premises hereinbefore described, for the amount due to him for the work performed and materials furnished by him in making alterations on the building on said premises.”

The lien thus filed was against the lot comprising the street numbers 379 and 381 Henry street. The language which I have quoted from his decision indicates that the learned referee supposed that the plaintiff’s request to the defendant to execute the mortgage, in satisfaction of his claim under the contract, was made before he filed his notice of lien. This, however, appears to be a mistake. The notice of lien was filed on December 28, 1895; while the plaintiff himself fixes February 21, 1896, as the date when he asked Mrs. Eehfeldt to execute the bond and mortgage, and when she declined to do so.

Mr. Firth adds:

“On that occasion I offered to make her a loan on her property, which I had altered, sufficient to take up the first mortgage that was on the property, and the amount of my contract and extras. This she refused.”

Thereupon the present suit to foreclose the lien was commenced on March 6, 1896.

The appellant insists that the contract between the parties precluded the plaintiff from filing a mechanic’s lien, and that his appropriate remedy was a suit for specific performance. The provisions as to the giving of the mortgage and the manner of payment are declared to be entirely inconsistent with the assertion of a lien, and to amount to a distinct waiver of any right thereto which the plaintiff might otherwise have had. By a contract of this kind, it is argued, the parties have provided for a different sort of security inconsistent with the statutory lien, the right to which must therefore be deemed to have been abandoned. The position of the appellant in this respect is sustained to some extent by authority elsewhere, but not, as it seems to me, by the decisions in this state. The strongest casein the appellant’s favor appears to be Weaver v. Demuth, 40 N. J. Law, 238, where the Few Jersey supreme court expressed the opinion that a stipulation in a building contract for payment by means of a mortgage operated as a waiver of the statutory lien. [982]*982It was conceded by counsel in that case that the right to enforce the mechanic’s lien would be lost if the agreement to give the mortgage had been carried out; but the court was asked to hold that the contractor might resort to the lien provided for by the statute, inasmuch as the promised mortgage had not been given. To this the court answered that the case stood on the contract made between the parties, and declared that the remedy for its breach must be ■Sought within and not outside of the agreement. “The contractor,” said Scudder, J., “must obtain the lien promised, or its equivalent in damages, and not the lien by statute which he has constructively agreed to abandon without any condition or reservation.” No other case cited by the appellant goes as far as this in asserting the doctrine of waiver. In Willison v. Douglas, 66 Md. 99, 6 Atl. 530, the defendant agreed to pay in cash and by giving a mortgage. He made the cash payments, and offered to give the mortgage; and, under these circumstances, the court held that “the plaintiff should be estopped in the further prosecution of his claim for lien upon the property.” In other words, the offer to pay in the manner stipulated authorized the court to treat the agreement as an executed contract, which prevented the enforcement of the mechanic’s lien. In Barrows v. Baughman, 9 Mich. 213, the builder’s contract provided that payment should be made within five years after the work was done, and should be secured by a first mortgage on the premises; and it was held that the statute of Michigan did not give a mechanic’s lien for the purpose of compelling the debtor to furnish collateral security for the debt. “The lien authorized by the statute is intended as a security for the payment of the debt, and can only be enforced as a means of compelling payment,” said Christiancy, J.; but he added: “Doubtless, such lien may attach and be enforced to compel payment, whether the debt be payable in cash or otherwise.” The remedy could not be invoked for that purpose in that case, as the debt was not yet due. It is important to note in the case at bar that the time for payment had come, before the plaintiff attempted to enforce his lien, by reason of the defendant’s ability to raise the required amount, and that the object of the present suit is not to obtain the collateral security for which the contract also provided, but to compel satisfaction of the plaintiff’s claim. In Grant v. Strong, 18 Wall. 623, the acts of the parties were so inconsistent with the idea of a mechanic’s lien that the supreme court of the United States declared that no such lien ever attached.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rolewitch v. Harrington
107 N.W. 207 (South Dakota Supreme Court, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
51 N.Y.S. 980, Counsel Stack Legal Research, https://law.counselstack.com/opinion/firth-v-rehfeldt-nyappdiv-1898.