FirstEnergy Corp. v. Public Utilities Commission

95 Ohio St. 3d 401
CourtOhio Supreme Court
DecidedJune 5, 2002
DocketNo. 2001-0573
StatusPublished
Cited by6 cases

This text of 95 Ohio St. 3d 401 (FirstEnergy Corp. v. Public Utilities Commission) is published on Counsel Stack Legal Research, covering Ohio Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
FirstEnergy Corp. v. Public Utilities Commission, 95 Ohio St. 3d 401 (Ohio 2002).

Opinion

Alice Robie Resnick, J.

[402]*402{¶ 1} With the passage of Am.Sub.S.B. No. 3 (“S.B. 3”) in 1999, the General Assembly enacted a comprehensive statutory scheme to implement competition in Ohio’s retail electricity market. Most of the provisions of S.B. 3 are contained in newly enacted R.C. Chapter 4928, and most provisions became effective on October 5, 1999. R.C. 4928.31, part of S.B. 3, requires that each eleptric utility file a transition plan with the Public Utilities Commission of Ohio regarding the utility’s provision of competitive electric service in Ohio.

{¶ 2} In December 1999, FirstEnergy Corp. (“FirstEnergy”)-, on behalf of its Ohio operating companies (Ohio Edison Company, the Cleveland Electric Illuminating Company, and the Toledo Edison Company), filed with the commission its proposed transition plan together with applications for tariff approval. Stipulated settlement agreements were entered into among the parties and evidentiary hearings and local public hearings were held. These proceedings resulted in an opinion and order, dated July 19, 2000, in which the commission approved the settlement agreements and FirstEnergy’s transition plan as modified by the settlement agreements and the commission order, subject to final approval of FirstEnergy’s compliance tariffs to be filed pursuant to the order, and approved FirstEnergy’s proposed tariff amendments.

{¶ 3} After informal review of FirstEnergy’s proposed compliance tariffs by interested parties and after informal comments by the parties, FirstEnergy modified its proposed compliance tariffs and made a final submission to the commission on August 28, 2000. One of the compliance tariff provisions is the subject of this appeal: the Net-Energy Metering Rider (the so-called August Rider) that FirstEnergy proposed for inclusion in the tariff of each of its Ohio operating companies. By its entry, dated November 21, 2000, the commission found that FirstEnergy’s proposed August Rider should be modified as recommended by the commission’s staff, and ordered FirstEnergy to make those modifications. The question in this appeal as of right is whether, as claimed by FirstEnergy, the commission acted unlawfully and unreasonably in issuing its November 21, 2000 entry, which failed to approve FirstEnergy’s proposed August Rider and, instead, ordered modifications to it.

I

Net-Metering Requirements

{¶ 4} S.B. 3 included a provision requiring retail electric service providers to develop a standard contract or tariff providing for net metering, a service introduced in S.B. 3. R.C. 4928.67. The term “net metering” is defined as “measuring the difference in an applicable billing period between the electricity supplied by an electric service provider and the electricity generated by a customer-generator which is fed back to the electric service provider.” R.C. [403]*4034928.01(A)(31). A customer-generator is a user of a net-metering system. R.C. 4928.01(A)(30). A net-metering system is a facility for the production of electrical energy that (a) uses as its power source either solar power, wind, biomass, landfill gas, or hydropower, or uses a microturbine or fuel cell; (b) is located on a customer-generator’s premises; (c) operates in parallel with the electric utility’s transmission and distribution facilities; and (d) is intended primarily to offset part or all of the customer-generator’s requirements for electricity. R.C. 4928.01(A)(32). As FirstEnergy points out, a customer-generator may consume electricity from an electric service provider during one period of time but feed back the electricity that is generated in excess of consumption in another period.

{¶ 5} Under R.C. 4928.67, the charges associated with net metering are determined by reference to the charges in the underlying tariff rate schedules under which a customer takes electric service. As a result, for ease of administration, FirstEnergy chose to provide for net metering through a tariff rider, rather than create a separate tariff or a separate set of tariff schedules applicable solely to net metering. FirstEnergy filed its proposed rider as a part of its transition plan filing in December 1999, and supplemented its December filing by submitting a revised net-metering rider in April 2000 (the so-called April Rider). On April 6, 2000, pursuant to R.C. 4928.11, the commission adopted a set of rules entitled “Electric Service and Safety Standards” to be included as Ohio Adm. Code Chapter 4901:1-10.

{¶ 6} Ohio Adm.Code 4901:1-10-28, the net-metering rule, includes requirements for meters: “Net metering shall be accomplished using a single meter capable of registering the flow of electricity in each direction. A customer’s existing single-register meter that is capable of registering the flow of electricity in both directions satisfies this requirement.” Ohio Adm.Code 4901:1-10-28(C).

{¶ 7} As FirstEnergy points out, under the net-metering rule, a customer-generator could use a meter with a wheel showing electrical usage by movement both forward (to show consumption) and backward (to show generation being supplied to the electric distribution company). Such a meter shows the net flow of electricity but cannot show separately the amounts of electricity that flowed in each direction as would the type of meter that would have been required under FirstEnergy’s April Rider, and as FirstEnergy claimed is required by R.C. 4928.67(A)(2).

{¶ 8} As a result of the commission’s net-metering rule and in consequence of the commission’s July 29, 2000 order, FirstEnergy revised its April Rider and submitted its August Rider as a part of its proposed compliance tariffs. The August Rider varied from the April Rider in three relevant respects: First, it complies with the commission’s net-metering rule, permitting a customer-generator to use a single meter that measures the net flow of electricity, so long as the [404]*404meter’s register runs both forward and backward, eliminating the necessity of installation of a new meter. Second, the August Rider eliminates the April Rider’s requirement that the customer-generator pay distribution, transmission, and ancillary charges to FirstEnergy upon electricity provided to FirstEnergy. Third, the August Rider credits customer-generators for all unbundled charges contained in the underlying service tariff with respect to the electricity they supply, to the extent that it offsets their consumption for a given period.

II

August Rider

Commission-ordered Modifications

{¶ 9} On November 21, 2000, the commission issued an entry that disapproved the August Rider and, instead, ordered FirstEnergy to modify it as set forth in Attachment B to the entry. While FirstEnergy disagrees with the necessity or desirability of most of the ordered modifications, this appeal deals only with modifications respecting the assessment of charges and the allowance of credits to net generators, i.e., those customer-generators that generate more electricity than they consume.

{¶ 10} FirstEnergy’s proffered August Rider credited net generators only with the applicable generation charge of the underlying service tariff, based on the amount of electricity they supplied in excess of the amount they consumed in a given time period.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Windway Technologies, Inc. v. Midland Power Cooperative
696 N.W.2d 303 (Supreme Court of Iowa, 2005)
FirstEnergy Corp. v. Pub. Util. Comm.
2002 Ohio 2430 (Ohio Supreme Court, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
95 Ohio St. 3d 401, Counsel Stack Legal Research, https://law.counselstack.com/opinion/firstenergy-corp-v-public-utilities-commission-ohio-2002.