First Suburban Water Utility District of Davidson County v. United States

129 Ct. Cl. 8, 1954 U.S. Ct. Cl. LEXIS 73, 1954 WL 6095
CourtUnited States Court of Claims
DecidedJuly 13, 1954
DocketNo. 49445
StatusPublished
Cited by1 cases

This text of 129 Ct. Cl. 8 (First Suburban Water Utility District of Davidson County v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Suburban Water Utility District of Davidson County v. United States, 129 Ct. Cl. 8, 1954 U.S. Ct. Cl. LEXIS 73, 1954 WL 6095 (cc 1954).

Opinions

MaddeN, Judge,

delivered the opinion of the court:

The plaintiff, a Tennessee Municipal Corporation engaged in the business of supplying water, on April 23,1942, entered into a contract to supply water to the Berry Hills Air Crew Classification Center, a Government installation located near Nashville, Tennessee. The plaintiff sues for profits lost because the Government did not, during the period that the contract was in effect, take all of the water which it used from the plaintiff, as the plaintiff claims it was obligated to do, but took most of its water from another supplier.

The Classification Center was being constructed in 1942. It was at first expected that water would first be required in September or October of that year. Some time before April 23,1942, the date of the plaintiff’s contract, the Government’s contracting officer had negotiated with the plaintiff about a contract, and the plaintiff had stated what its rates would be. Four or five days before April 23, the contracting officer had made a contract with the City of Nashville for the supply of water at the project. Two local newspapers had reported the award of that contract to the city, and the plaintiff’s managing officer, Mr. Saindon, had seen those newspaper reports.

A few days later, the Government’s contracting officer Colonel Walsh called Mr. Saindon in and told him that if he would figure closely, they might be able to make a contract. He turned Mr. Saindon over to subordinate civilian officials, and the contract here in suit was agreed upon and signed. The contracting officer had in mind that water would be needed by July 1942 instead of September or October as earlier contemplated; that the City of Nashville would not be able to supply the needed amount of water at the required pressure as early as in July, and that water would be taken from the plaintiff until the city was ready to supply it, the city’s rates being substantially lower than the plaintiff’s rates. But none of these thoughts which were in Colonel Walsh’s mind were imparted to Mr. Saindon.

The plaintiff’s contract called for the expenditure of $28,000 in necessary facilities to furnish the water. It provided that the Government would advance $18,000 of this amount, and repay itself by deducting 10 percent from its [10]*10water bills. The plaintiff was to put up the other $10,000 which was the estimated salvage value of the facilities to be installed. The contract provided that it might be terminated, at the option of the Government, on 90 days notice. In the discussion during the preparation of the contract Mr. Saindon protested the fact that although the contract called for considerable expenditures by the plaintiff, it contained no provision for a minimum charge regardless of the amount of water used. He was told by the Government officials that, in view of the large quantities of water to be used, 1,500,000 gallons per day, there was no necessity for a minimum charge.

Article X of the contract was as follows:

SERVICES TO BE RENDERED
• Contractor shall supply the water required by the United States for use at the project.

The Government began using water furnished by the plaintiff in July of 1942. At first it took all or most of its water from the plaintiff but, when the facilities of the City of Nashville were completed, it began to take more water from the city and less from the plaintiff until October 1946, when it ceased taking any water from the plaintiff. On June 12,1947, it gave the plaintiff notice of the termination of the contract. The Government had not, during the period of the contract, taken enough water from the plaintiff to recoup its advance of $18,000 by the deduction of 10 percent from its water bills.

The Government would have us interpret Article X of the contract as meaning that the plaintiff was to furnish such water as the Government asked for. As language, standing by itself, it does not mean that. It says that the contractor is to supply the water required l>y the United States for use at the project. If it had said water required it might be argued that it meant some of the water, or such of the needed water as the Government might choose to take from this supplier. But the water required does not leave room for that interpretation. It is not physically possible that the water required could be furnished by the plaintiff, and at the [11]*11same time by some other supplier. We think the language used has a more than ordinarily plain meaning.

In the preceding discussion we have assumed that the word “required” as used in the contract, was synonymous with “needed.” A considerable number of decisions have dealt with variations of the word “require,” when used in contracts. In Edison Company v. Thacher, 229 N. Y. 172, 128 N. E. 124, the court held that a contract by A to furnish cover castings “as required” in B’s business for a period of twelve months bound A to furnish and B to take all such covers which B used within the period. In Ehrenworth v. Stuhmer and Co., 229 N. Y. 210, 128 N. E. 108, 24 A. L. R. 1354, a contract whereby A agreed to furnish to B as much of a specified kind of bread “as he would require for his customers” as long as the parties remained in business, bound A to furnish and B to take all such bread which B used on his route. In Minnesota Lumber Co. v. Whitebreast Coal Co., 160 Ill. 85, 43 N. E. 774, the contract provided that A should buy “its requirements of anthracite coal for the season of 1886-1887” from B. The court said that the amount of coal “required” for the business of that season was the amount of coal needed for the business, and that the contract bound the parties to furnish, and accept, all the coal needed. To the same effect is Fuchs v. United Motor Stage Co., Inc., 135 Ohio State 509, 21 N. E. 2d 669. In Wells v. Alexandre, 130 N. Y. 642, 29 N. E. 142, the contract did not use any variation of the word “require,” but the court, in discussing the contract, itself used the word “requirements” as synonymous with “needs.”

The Government cites the case of Merriam v. United States, 107 U. S. 437. In that case the contract did use the expression “as may be required” but the Supreme Court, in interpreting the expression as not equivalent to “as may be needed,” or “as may be used,” expressly found that the construction of the contract asserted by the plaintiff could not have been his understanding of the contract when it was made, but was an afterthought. The plaintiff was one of several bidders on a contract to supply oats, and several contracts were awarded to different parties for parts of the en[12]*12tire quantity on whicli bids had been asked, and each of the contracts provided that the contractor would supply a specified amount “more or less, or such other quantity, more or less as may be required for the wants of the station” within a specified period. Since, as the court found, neither party thought, when the contract was made, that it meant what the plaintiff in his suit claimed that it meant, the plaintiff’s claim was denied.

In Converse, et al., v. United States, 69 C. Cls.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

The Franklin Company v. The United States
381 F.2d 416 (Court of Claims, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
129 Ct. Cl. 8, 1954 U.S. Ct. Cl. LEXIS 73, 1954 WL 6095, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-suburban-water-utility-district-of-davidson-county-v-united-states-cc-1954.