First South Bank v. Bank of the Ozarks

542 F. App'x 280
CourtCourt of Appeals for the Fourth Circuit
DecidedOctober 18, 2013
Docket19-4225
StatusUnpublished
Cited by2 cases

This text of 542 F. App'x 280 (First South Bank v. Bank of the Ozarks) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First South Bank v. Bank of the Ozarks, 542 F. App'x 280 (4th Cir. 2013).

Opinion

Affirmed by unpublished PER CURIAM opinion.

Unpublished opinions are not binding precedent in this circuit.

*281 PER CURIAM:

Bank of the Ozarks appeals the district court’s judgment in favor of First South Bank in this breach of contract action. For the following reasons, we affirm.

I.

In June 2010, Woodlands Bank agreed to issue a $7.1 million development loan to Lakeside Development, LLC (the Borrower or Lakeside). Seeking another bank to help fund the loan, Woodlands approached First South Bank, and the banks eventually entered into a Participation Agreement (the Agreement), whereby First South Bank agreed to fund up to $4.15 million of the development loan. During negotiations, First South Bank demanded that Woodlands be responsible for all expenses arising from servicing the loan and would not have entered into the Agreement without this promise.

To that end, the Agreement specifically discussed the handling of expenses, providing as follows in Paragraph 4:

4. EXPENSES. Seller [Woodlands] may at its discretion make additional advances for taxes, insurance premiums and other items deemed necessary by [Woodlands] to collect, enforce, or protect the Loan and any Property securing the Loan including, but not limited to, attorneys’ fees, court costs and disbursements (Expenses). Purchaser’s [First South Bank’s] percentage of Expenses is:
A. {X} No Shared Expenses. [Woodlands] will bear all expenses.
B. {} Shared Expenses. _percent of Expenses, or if no percentage is indicated, that percentage of Expenses which [First South Bank’s] unreim-bursed investment is of the principal amount of the Loan outstanding on the date Expenses are incurred. All Expenses will be shared in the proportion indicated on the date Expenses are incurred. [First South Bank] will pay to [Woodlands] on demand [First South Bank’s] share of Expenses. [Woodlands] will remit to [First South Bank’s] share of Expenses recovered by [Woodlands].

(J.A. 25). The banks selected option A, indicating by marking with an X that Woodlands was responsible for all expenses.

In addition to expenses, the Agreement also addressed “Payments,” providing in Paragraph 3 that “[Woodlands] will receive all Payments and apply them to Borrower’s account,” and that “[First South Bank’s] percentage of all Payments is ... [First South Bank] First Out: 100 percent of Payments before Default until such time as [First South Bank] has received [First South Bank’s] Investment plus interest thereon.” (J.A. 25). “Payments” are defined in Paragraph 9 as “principal, interest, and other charges received by [Woodlands] with respect to the Loan from whatever source derived.” (J.A. 26).

Finally, Paragraph 19 addressed what would happen in the event Lakeside defaulted on the underlying development loan:

19. DEFAULT AND LIQUIDATION OF LOAN. Notwithstanding any payment terms to the contrary, in the event of default, or if [Woodlands] in its sole discretion should otherwise accelerate and liquidate the Loan, all Payments collected and received by [Woodlands] will be applied ratably as follows: first, to Expenses; second, to the unpaid principal amount of the Loan in proportion to the respective unpaid investments of [Woodlands] and [First South Bank] in the Loan at the time of Default; and third, to the respective accrued interest and other charges of [Woodlands] and *282 [First South Bank], Upon Borrower’s Default, all Payments and Borrower Fees received from Borrower, whether designated for repayment of the loan or undesignated, will be deemed intended for the repayment of the Loan in accordance with this Agreement.

(J.A. 26). Paragraph 19 does not define “payment terms,” “Payments,” or “Expenses.”

Shortly after signing the Agreement, Woodlands entered receivership under the Federal Deposit Insurance Corporation, and Bank of the Ozarks purchased the loan to Lakeside Development and became Woodlands’ successor in interest to the Agreement. Thereafter, Lakeside defaulted on the loan. Bank of the Ozarks began collecting the loan from Lakeside’s assets, including liquidating one of Lakeside’s trust accounts that had secured the initial loan. Bank of the Ozarks then deducted all of its expenses-$81,452.39-before paying First South Bank its 58.041% share of the remaining assets.

First South Bank responded by suing Bank of the Ozarks in federal district court, alleging breach of contract for deducting expenses before paying First South Bank’s share of the recovery. Bank of the Ozarks moved for judgment on the pleadings, attaching the Agreement and arguing that Paragraph 19 permitted it to deduct expenses incurred after a default. First South Bank filed a cross-motion for summary judgment, arguing that Paragraph 4 unambiguously required Bank of the Ozarks to bear all expenses. The district court denied both motions, concluding “as a matter of law that the Participation Agreement is ambiguous with regard to the issue raised in this action.” (J.A. 53-54). Thereafter, the court held a bench trial during which both parties presented extrinsic evidence regarding their understanding of the Agreement. At the close of evidence, the court ruled in favor of First South Bank and ordered Bank of the Ozarks to pay $47,275.78. First South Bank v. Bank of the Ozarks, 2012 WL 3597665 (D.S.C. Aug. 12, 2012). The court expounded upon its earlier ruling concerning the ambiguity of the Agreement, explaining that “[wjhile Paragraph 4 plainly and without qualification states that [Bank of the Ozarks] is to bear all Expenses, paragraph 19 appears to permit [Bank of the Ozarks], after default, to pay Expenses out of the proceeds that it receives.” Id. at *6. The court found that it could not “reconcile these two provisions” and that the Agreement was thus ambiguous. Id. By separate order, the court later granted attorneys’ fees and costs in the amount of $41,668.95.

II.

Bank of the Ozarks now appeals, contending that the court erred in denying its motion for judgment on the pleadings. * We review this ruling de novo, Butler v. United States, 702 F.3d 749, 751-52 (4th Cir.2012). Under South Carolina law, which applies here, an agreement is ambiguous if it is “susceptible to more than one interpretation or its meaning is unclear.” Miles v. Miles, 393 S.C. 111, 711 S.E.2d 880, 883 (2011). “Whether a contract is ambiguous is to be determined from the entire contract and not from isolated portions of the contract.” Farr v. *283 Duke Power Co., 265 S.C. 356, 218 S.E.2d 431, 433 (1975). A contract may be ambiguous because of “indefiniteness of expression,” internal inconsistency, or inclusion of “words that have a double meaning.” Crystal Pines Homeowners Ass’n v. Phillips, 394 S.C.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
542 F. App'x 280, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-south-bank-v-bank-of-the-ozarks-ca4-2013.