First National Stores, Inc. v. H. P. Welch Co.

8 Mass. App. Div. 385
CourtMassachusetts District Court, Appellate Division
DecidedNovember 26, 1943
StatusPublished

This text of 8 Mass. App. Div. 385 (First National Stores, Inc. v. H. P. Welch Co.) is published on Counsel Stack Legal Research, covering Massachusetts District Court, Appellate Division primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Stores, Inc. v. H. P. Welch Co., 8 Mass. App. Div. 385 (Mass. Ct. App. 1943).

Opinion

Keniston, C. J.

The plaintiff seeks to recover in an action of contract or tort, from the defendant, a Massachusetts corporation, as a carrier, for the loss of goods in its possession resulting from a fire.

The defendant, at the time the loss occurred, was the holder of a certificate as a common carrier and of a permit as a contract carrier issued by the Interstate Commerce Commission. The defendant was also the holder of a certificate as a common carrier issued by the Massachusetts Department of Public Utilities. Prior to 1938 it was the holder of a permit to operate as a contract carrier in Massachusetts. Chapter 483 of the Massachusetts Act of 1938 required the reclassification of contract carrier permits. On April 12,1939, a hearing was held by the Massachusetts Department of Public Utilities upon the defendant’s application for reclassification under the 1938 Act. At this hear[386]*386ing the examiner made a notation that the defendant was to be issued a permit as a contract carrier upon the Department being supplied with copies of its contracts and a schedule of its customers.

On June 21, 1939, the .Department wrote the defendant the usual letter when a contract carrier permit was to be issued, asking, for copies of its contracts and a schedule of minimum rates and charges as a contract carrier in Massachusetts. On August 21, 1939, the Department wrote the defendant that such a list of customers must be submitted before the contract carrier permit would be issued. On June 21, 1941, the Department issued an order which required all applicants for permits as contract carriers to file with the Department on or before September 1, 1941, acceptable contracts and three copies of a schedule of minimum rates and charges. On August 28,1941, the defendant filed a list of customers but no copies of contracts or schedule of rates and charges. The list of customers contained about thirty names including the plaintiff. The carriage of freight for these customers represented a substantial business, and such freight had been carried by the defendant continuously to date on the same general terms and the same general manner as it had been carried by the defendant prior to 1938, that is at rates fixed by contract between the defendant and the customers which rates were different from the defendant’s common carrier rates. Up to the time of the loss on September 18, 1941, the defendant had not met the requirement of filing copies of contracts and a schedule of its rates and charges. However, the Department had taken no action against the defendant. Since 1938 up to the time the fire occurred, no contract carrier permit had been issued to the defendant by the Massachusetts Department of Public Utilities.

[387]*387The defendant had been carrying merchandise for the plaintiff from the piers at Boston to the warehouses of the plaintiff in Charlestown for over ten years prior to the fire. The contract of carrying had been oral. The rate charged at the time of the fire and currently was 5%^ per hundred pounds. This rate was substantially lower than the rate at which the defendant carried goods as a common carrier. The regular practice between the parties was for the plaintiff to notify the defendant of the arrival of a cargo of goods and to deliver to the defendant a bill of lading and a check for the steamship company. The defendant delivered the bill of lading and the check to the office of the steamship company which gave the defendant a duplicate bill of lading marked “paid”. The defendant presented the duplicate bill of lading at the pier and loaded the goods onto its trailers and signed receipts for the steamship company listing the goods. The goods were then carried in the trailers to the plaintiff’s warehouses and offices to which the defendant delivered the goods. The warehouses opened about 7:30 A. M. and closed at 4:15 P. M. Warehouses numbered 34 and 35, where the fire occurred, were part of the Charles-town warehouses. The goods in question were loaded and arrived at the warehouses or offices of the plaintiff in eight trailers, at different times between noon of September 17, 1941, and 5 P. M. on, September 18, except for one trailer which had arrived on September 10 and had been about two-thirds unloaded at the time of the fire. The fire occurred about 6:00 P. M., September 18, 1941, when the plaintiff’s warehouses were burned as well as the defendant’s trailers with their contents, resulting in a substantial loss.

There was evidence tending to show that the regular practice of the parties was as follows:

[388]*388"When the defendant loaded its goods into the trailers at the pier, the receipt from the steamship company was a “loading ticket” made out in triplicate by the driver of the defendant’s truck or trailer, who gave one to the steamship company at the pier and then carried the goods to the plaintiff’s warehouses at Charlestown. Upon arriving there the driver gave one copy to the plaintiff’s foreman at the warehouse and the third copy to the “lumper” who had charge of a crew of the defendant’s men who were stationed permanently at the plaintiff’s Charlestown warehouse for unloading purposes.

When the plaintiff’s foreman received his copy of the “loading ticket” he told the defendant the particular door of the particular warehouse where the goods in the truck or trailer were to be unloaded. The plaintiff had at least three large warehouses in Charlestown numbered 33, 34 and 35, respectively. There were some twenty-two loading doors, each of which accommodated two trailers at warehouse 35 alone. The defendant set the trailer or truck at the place specified by the plaintiff, or, if so instructed, the truck or trailer was set temporarily against the warehouse. The unloading of the trucks or trailers was a joint operation, the defendant’s men working in two man teams took the goods from the truck or trailer and placed them in delivery trucks or “dollies”. The plaintiff’s men working in four man teams inside the warehouses took the goods on their delivery trucks or “dollies” and stored the goods in the warehouses. At this time a receipt for the goods was signed by the plaintiff and given to the defendant. The defendant did not start unloading any truck or trailer until the plaintiff notified the defendant to do so and had its crew ready to store the goods.

The warehouses were very large and were very full. The plaintiff’s crew at the warehouses also unloaded [389]*389freight cars. Bach day the plaintiff notified the defendant of the number of men it desired the defendant to have on hand for unloading the following day and usually the defendant was able to supply the number of men requested. The actual practice followed with respect to the transportation of the destroyed goods was according to the usual practice.

On the day of the fire, the defendant had at least four men present. It took from one and one-half to two hours to unload a truck or trailer, depending upon its size and the nature of the goods. Pour men could have unloaded in one day, the eight trailers present on the day of the fire. The warehouses were sometimes kept open after the regular closing time and the defendant’s men were always glad to get overtime work. The warehouses closed at the regular time, 4:15 P. M. on the day of the fire.

The plaintiff seasonably filed seven requests all of which were allowed by the Court except requests numbered 5 and 6 which were as follows:

“5.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Michigan Public Utilities Commission v. Duke
266 U.S. 570 (Supreme Court, 1925)
Smith v. Cahoon
283 U.S. 553 (Supreme Court, 1931)
Buckland v. Adams Express Co.
97 Mass. 124 (Massachusetts Supreme Judicial Court, 1867)
Houle v. Lewonis
140 N.E. 427 (Massachusetts Supreme Judicial Court, 1923)
Farr v. Whitney
156 N.E. 863 (Massachusetts Supreme Judicial Court, 1927)
Commonwealth v. New England Transportation Co.
185 N.E. 23 (Massachusetts Supreme Judicial Court, 1933)
Stowe v. Mason
289 Mass. 577 (Massachusetts Supreme Judicial Court, 1935)
Goodman v. New York, New Haven & Hartford Railroad
3 N.E.2d 777 (Massachusetts Supreme Judicial Court, 1936)
Short Line, Inc. v. Quinn
10 N.E.2d 112 (Massachusetts Supreme Judicial Court, 1937)
Leveillee v. Wright
15 N.E.2d 247 (Massachusetts Supreme Judicial Court, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
8 Mass. App. Div. 385, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-stores-inc-v-h-p-welch-co-massdistctapp-1943.