First National Oil, Inc. v. Federal Energy Regulatory Commission, Panhandle Eastern Pipe Line Company Indiana Gas Company, Inc. Oklahoma Independent Petroleum Association Panhandle Field Services Company Colorado Interstate Gas Company, Intervenors. First National Oil, Inc. v. Federal Energy Regulatory Commission, Colorado Interstate Gas Company Indiana Gas Company, Inc. Citizens Gas & Coke Utility Panhandle Field Services Company Panhandle Eastern Pipe Line Company Oklahoma Independent Petroleum Association East Ohio Gas Company Panhandle Customer Group Michigan Consolidated Gas Company, Intervenors
This text of 102 F.3d 1094 (First National Oil, Inc. v. Federal Energy Regulatory Commission, Panhandle Eastern Pipe Line Company Indiana Gas Company, Inc. Oklahoma Independent Petroleum Association Panhandle Field Services Company Colorado Interstate Gas Company, Intervenors. First National Oil, Inc. v. Federal Energy Regulatory Commission, Colorado Interstate Gas Company Indiana Gas Company, Inc. Citizens Gas & Coke Utility Panhandle Field Services Company Panhandle Eastern Pipe Line Company Oklahoma Independent Petroleum Association East Ohio Gas Company Panhandle Customer Group Michigan Consolidated Gas Company, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the First Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
Util. L. Rep. P 14,136, 97 CJ C.A.R. 3
FIRST NATIONAL OIL, INC., Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
Panhandle Eastern Pipe Line Company; Indiana Gas Company,
Inc.; Oklahoma Independent Petroleum Association;
Panhandle Field Services Company;
Colorado Interstate Gas
Company, Intervenors.
FIRST NATIONAL OIL, INC., Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
Colorado Interstate Gas Company; Indiana Gas Company, Inc.;
Citizens Gas & Coke Utility; Panhandle Field Services
Company; Panhandle Eastern Pipe Line Company; Oklahoma
Independent Petroleum Association; East Ohio Gas Company;
Panhandle Customer Group; Michigan Consolidated Gas
Company, Intervenors.
Nos. 95-9531, 95-9553.
United States Court of Appeals,
Tenth Circuit.
Dec. 23, 1996.
Maria M. Seidler, Tulsa, OK, for Petitioners.
Edward S. Geldermann, Attorney (Susan Tomasky, General Counsel; Jerome M. Feit, Solicitor; and Joseph S. Davies, Deputy Solicitor, with him on the briefs), Federal Energy Regulatory Commission, Washington, DC, for Respondents.
Brian D. O'Neill, LeBoeuf, Lamb, Greene & MacRae, Washington, DC (David P. Sharo, LeBoeuf, Lamb, Greene & MacRae, Washington, DC; Merlin E. Remmenga, Panhandle Eastern Pipe Line Company, Houston, TX; and Dennis J. Kelly, Panhandle Field Services Company, Denver, CO, with him on the briefs), for Intervenors.
Before SEYMOUR, ANDERSON, and BRORBY, Circuit Judges.
STEPHEN H. ANDERSON, Circuit Judge.
Petitioner First National Oil, Inc. ("First National") seeks review of certain orders issued by the Federal Energy Regulatory Commission ("FERC" or "Commission"). See Panhandle Eastern Pipe Line Co., 70 F.E.R.C. p 61,178 (preliminary determination on abandonment application and declaration of jurisdictional status of facilities), modified, 71 F.E.R.C. p 61,201 (1995); Panhandle Eastern Pipe Line Co., 71 F.E.R.C. p 61,336 (order authorizing refunctionalization and abandonment of facilities), reh'g denied, 73 F.E.R.C. p 61,137 (1995). First National contends that the Commission improperly permitted Panhandle Eastern Pipe Line Company ("Panhandle") to abandon certain natural gas gathering facilities by "spinning down" those facilities to its wholly-owned subsidiary, Panhandle Field Services Company ("Field Services"). We hold that First National lacks standing to bring this petition because it has not been "aggrieved" by the orders within the meaning of section 19(b) of the Natural Gas Act ("NGA"), 15 U.S.C. § 717r(b).
BACKGROUND
Panhandle owns and operates an interstate natural-gas pipeline. Prior to the orders cited above, Panhandle also provided gathering services through facilities located in Colorado, Kansas, Texas, and Oklahoma ("the West End"). Through these gathering facilities, Panhandle collected gas from local wellheads and prepared it for delivery into the interstate pipeline.
In response to a changing regulatory environment, many interstate pipeline companies, including Panhandle, decided it was no longer advantageous to offer both gathering and transportation services. Several pipelines have sought authorization from the FERC to abandon gathering facilities, and transfer the facilities to corporate subsidiaries ("spin down"). A principal purpose behind spin downs is to create affiliate gathering companies not subject to FERC jurisdiction.1
On December 21, 1993, Panhandle filed a petition with the FERC requesting authorization to abandon its West End gathering facilities by transferring them to Field Services. R. Vol. IV. Concurrently, Field Services sought a declaratory ruling that its ownership and operation of the transferred gathering facilities would be exempt from FERC jurisdiction under section 1(b) of the Natural Gas Act ("NGA"), 15 U.S.C. § 717(b).
First National, as well as many other parties, intervened in the Panhandle proceedings to protest the proposed spin down. First National is a natural gas producer with wellheads within the West End system. First National sells gas from these wellheads to independent marketers. These marketers then move the gas through the West End gathering facilities in preparation for its shipment on Panhandle's interstate pipeline.
First National's opposition to the proposed spin down was based on its fear that Field Services, as Panhandle's non-jurisdictional affiliate, would exploit its alleged monopoly control over certain West End gathering facilities. First National asserted that such exploitation previously had been denied to Panhandle only by FERC regulation. First National also alleged that Field Services was colluding, and would continue to collude, with other Panhandle affiliates--Centana Gathering Company and Centana Energy--to manipulate the price and availability of West End gathering services.
The Commission rejected First National's protests, as well as those of the other intervenors, and issued a preliminary determination approving the abandonment and transfer of the West End gathering facilities from Panhandle to Field Services, and declaring that the transferred facilities were exempt from FERC jurisdiction. 70 F.E.R.C. p 61,178. However, as a precondition to a final order, the Commission required, among other things, that Field Services offer a two-year default contract to Panhandle's existing gathering customers. 70 F.E.R.C. at 61,587. The Commission required that the default contract contain "terms and conditions consistent with those under which [Panhandle] provides gathering service to its customers." Id. Rates charged under the default contract had to be the same as those previously charged by Panhandle. Id. The Commission explained that the availability of the default contract would allow existing customers a reasonable time in which to adjust to the spin down, id., and would "allow states sufficient time to implement policies deemed necessary in the absence of federal regulation of gathering." 71 F.E.R.C. at 61,731.2 Subsequently, the Commission approved the default contract prepared by Field Services, and issued final authorization for the spin down. 71 F.E.R.C. p 61,336.
Because First National sold its gas to a marketer, it was not an existing gathering customer of Panhandle, but Field Services offered First National the default contract anyway. R. Vol. II at 2709. First National refused the contract, and instead requested a reconsideration and rehearing of the Commission's previous orders. R. Vol. II at 2695. In that request, First National renewed its protests regarding the alleged collusion between Panhandle affiliates. First National also asserted that the default contract would not, in fact, provide for the same quality of service previously provided by Panhandle. The Commission denied the request for reconsideration and rehearing, 73 F.E.R.C. p 61,137, and this appeal ensued.
DISCUSSION
Section 19(b) of the NGA allows only parties "aggrieved" by FERC orders to seek review in the court of appeals. 15 U.S.C. § 717r(b); Colorado Interstate Gas Co. v.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
102 F.3d 1094, 1996 U.S. App. LEXIS 33379, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-oil-inc-v-federal-energy-regulatory-commission-panhandle-ca1-1996.