First National Insurance Co. of America v. D.P.S. Industries, Inc.

146 F. App'x 375
CourtCourt of Appeals for the Eleventh Circuit
DecidedAugust 23, 2005
Docket04-10918
StatusUnpublished

This text of 146 F. App'x 375 (First National Insurance Co. of America v. D.P.S. Industries, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Insurance Co. of America v. D.P.S. Industries, Inc., 146 F. App'x 375 (11th Cir. 2005).

Opinion

PER CURIAM.

This appeal arises from a contract entered into between D.P.S. Industries, Inc. (GA)(“DPS”), and the Board of Education of the City of Atlanta (“the School Board”) for the performance of certain work in preparation for the construction of a new school. DPS and the surety on its statutory payment bond, First National Insurance Company of America (“FNIC”), appeal the district court’s ruling that $275,000 paid by the School Board to DPS’s subcontractor, Cheoah Construction Company, Inc. (“Cheoah”), does not apply to reduce the amount owed to Cheoah by *377 DPS. Additionally, Dave Parrish, Sr., the President of DPS, appeals the district court’s judgment against him because Cheoah asserted no claim against Parrish. Upon review of the record and the arguments of the parties, we conclude that the district committed error in including the $275,000 in the damages award to Cheoah, and we REVERSE and REMAND to the extent necessary to correct this error. Additionally, we VACATE the district court’s judgment to the extent that it includes Parrish.

I. BACKGROUND

On or about 29 April 1999, DPS, a contractor, entered into a General Contract For Sitework (“the Contract”) with the School Board. Under the Contract, DPS agreed to perform certain site preparation work for the construction of a new school in Atlanta (“the Project”). DPS, as principal, and FNIC, as surety, executed a statutory payment bond in connection with the Project.

In May 1999, DPS subcontracted with Cheoah to complete certain work required by the Contract. Cheoah came to believe that it had not been paid sufficiently by DPS for work it had completed. After Cheoah failed to obtain payment from DPS or by asserting a claim against FNIC pursuant to the statutory bond, it initiated direct negotiations with the School Board.

In a letter dated 23 December 1999, the School Board informed DPS that it “ha[d] paid DPS for a substantial portion of the work performed by Cheoah upon the Project,” Exh. 2-57 at 2, that DPS ha[d] in turn failed and refused to release these payments to Cheoah, id., and that the School Board could thus “no longer trust or have confidence that DPS [would] fulfill its payment obligations to Cheoah,” id. at 3. Accordingly, the School Board notified DPS that it would issue joint checks made payable to both DPS and Cheoah “for all remaining and outstanding funds payable to DPS for work performed by Cheoah in accordance with the contract documents,” id., and that if DPS failed to endorse properly the joint checks, it would discharge the payment obligation by issuing direct payments to Cheoah “pursuant to the terms of the Contract Documents, including but not limited to Articles 14 and 32 of the General Conditions,” id. Additionally, the School Board informed DPS that it had issued one such joint check for $50,000. The School Board stated that if DPS did not endorse the check within 72 hours, it would “issue payment directly to Cheoah, discharging this portion of DPS’s payment obligations to Cheoah ...” Id.

In a letter dated 27 December 1999, the School Board informed DPS that DPS owed Cheoah an additional payment of $225,000 and that it had issued a joint check for that amount. Again, the School Board threatened to pay Cheoah directly if DPS failed to endorse the joint check within 72 hours. Exh. 1-218 at 3. The letter further stated that “[t]he payment of an additional $225,000 [to Cheoah] coupled with the $50,000 referenced in [the 23 December] letter represents full, complete and final payment for all labor, materials and work furnished, delivered, and performed by or on behalf of Cheoah upon the Project as approved and authorized by the [School Board].” Id.

DPS refused to sign off on any joint checks to Cheoah. Exh. 1-184 at 5. On 27 December 1999, the School Board made a direct payment to Cheoah in the amount of $50,000. On 29 December 1999, it made another direct payment to Cheoah in the amount of $225,000. In connection with these payments, Cheoah’s authorized representatives executed a document entitled “PARTIAL RELEASE & PAYMENT OF CONTRACT FUNDS” (“the School Board *378 / Cheoah Release”). The School Board / Cheoah Release provided, inter alia, that “[t]he [School Board] shall pay Cheoah, for work performed by Cheoah upon the Project, approved and authorized by the [School Board], a substantial portion of which has already been paid to DPS, directly if necessary, the lump sum of $275,000, in exchange for the covenants, representations, promises, and release contained herein.” Exh. 2-7 ¶27, at 4. It specifically reserved to Cheoah all claims or causes of action which Cheoah had against DPS or Parrish.

Litigation ensued between Cheoah, DPS, Parrish, FNIC, and the School Board. By 1 July 2003, the remaining claims pending for trial that are relevant to this appeal were Cheoah’s claims against DPS for breach of contract and against FNIC for liability pursuant to the payment bond for unpaid amounts allegedly owed to it for its work on the Project as DPS’s subcontractor, and DPS and Parrish’s counterclaim against Cheoah for breach of contract, indemnity, and litigation expenses. 1 On 20 January 2004, the district court commenced a bench trial on these claims.

After the close of all of the evidence, DPS and FNIC argued that the School Board’s two payments to Cheoah totaling $275,000 should be counted as payments to Cheoah for its work on the Project and should thus reduce the amount owed to Cheoah. However, the district court ruled that Cheoah was “entitled to retain the $275,000 without restriction or any other deductions or credits.” Rll at 669. It then directed that judgment be entered for Cheoah for $294,481.80.

Before the entry of judgment, DPS and FNIC moved the district court to reconsider its ruling and apply the $275,000 payments by the School Board to Cheoah as payment for Cheoah’s work on the Project, thereby reducing the judgment to the sum of $19,481.80. The district court denied the motion and entered judgment for $294,481.80 against DPS, FNIC, and Parrish. DPS, FNIC, and Parrish timely appealed.

II. DISCUSSION

On appeal, DPS, FNIC, and Parrish advance two main arguments. First, DPS and FNIC contend that the district court erred in concluding that the $275,000 payments by the School Board to Cheoah should not be applied to reduce the amount owed to Cheoah for its work on the Project. Second, Parrish avers, and Cheoah concedes, that the district court erred by entering judgment against Parrish because Cheoah asserted no claim against him.

Because this is a diversity action, we look to the substantive law of Georgia to determine the correct measure of damages for a breach of contract. See Erie R.R. Co. v. Tompkins, 304 U.S. 64, 79, 58 S.Ct. 817, 823, 82 L.Ed. 1188 (1938). Under Georgia law,

The measure of damages in the case of breach of contract is the amount which will compensate the injured person for a loss which a fulfillment of the contract would have prevented or the breach of it entailed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Erie Railroad v. Tompkins
304 U.S. 64 (Supreme Court, 1938)
Accent Walls, Inc. v. Parker
292 S.E.2d 509 (Court of Appeals of Georgia, 1982)
Lee v. Green Land Co., Inc.
527 S.E.2d 204 (Supreme Court of Georgia, 2000)
Geriner v. Branigar Organization, Inc.
489 S.E.2d 305 (Supreme Court of Georgia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
146 F. App'x 375, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-insurance-co-of-america-v-dps-industries-inc-ca11-2005.