First National Bank v. Carroll

88 P. 1012, 35 Mont. 302, 1907 Mont. LEXIS 81
CourtMontana Supreme Court
DecidedFebruary 26, 1907
DocketNo. 2,374
StatusPublished
Cited by15 cases

This text of 88 P. 1012 (First National Bank v. Carroll) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Bank v. Carroll, 88 P. 1012, 35 Mont. 302, 1907 Mont. LEXIS 81 (Mo. 1907).

Opinion

ME. JUSTICE HOLLOWAY

delivered the opinion of the court.

This action was commenced by the First National Bank of Portland, Oregon, as assignee of the Wolff & Zwieker Iron Works, a corporation, to recover from Eugene Carroll the sum of $22,342.10 as balance due for material furnished under certain contracts. The complaint, as amended, sets forth the fact of the execution of three contracts by.Wolff & Zwieker Iron Works and Carroll, as follows:

Contract “A” was executed April 20, 1899, and provided that the Wolff & Zwieker Iron Works should furnish to Carroll' eighteen thousand eight hundred and eighty feet of water pipe and should properly lay the same, for $71,797.90. The work under this contract was to be fully completed on or before Oeto[307]*307ber 10, 1899, provided “that a proportionate time be given to the party of the second part (Wolff & Zwieker Iron Works) to complete the delivery and the laying of the last item, namely, four thousand feet of No. 8 B. W. Gr. steel pipe in its bid set forth.” This contract concludes with this provision: “This contract is subject to strikes and delays beyond the control of the party of the second part.”

Contract “B” was executed on June 6, 1899. It provided that Wolff & Zwieker Iron Works should furnish to Carroll eighteen thousand two hundred feet of pipe and should properly lay the same for the sum of $75,450. The time allowed for the completion of the work under this contract was to be proportionate to the time allowed for completing the work under contract “A.”

Contract “C” was executed January 6, 1900; but its terms are not material here.

It is alleged that work under contracts “A” and “B” was completed, on November 23, 1900, and on contract “C” on February 2, 1901. The complaint then alleges certain facts which, it is claimed, operated to excuse Wolff & Zwieker Iron Works from completing the contracts within the time limited, as follows: (1) Carroll’s failure to furnish the specifications within the time agreed upon; (2) his modifications of the specifications after they were furnished; (3) his request that work under contract “B” should be completed before the work under contract “A” was completed; (4) the failure of certain inspectors appointed by Carroll to properly perform their work; and (5) the failure of Byerson & Son, with whom Wolff & Zwieker Iron Works had a contract for certain material, to furnish the material within a reasonable time. All of these allegations are put in issue by the answer.

The answer admits the amount due upon the contracts, but, by way of a counterclaim, the defendant alleges that he was damaged in the sum of $35,000 by reason of the failure of Wolff & Zwieker Iron Works to complete contracts “A” and “B” within the time limited, and that he was further damaged in [308]*308the sum of $1,164.15, by reason of the failure of Wolff & Zwicker Iron Works to complete contract “C” within the time agreed upon.

The cause was tried to the court sitting with a jury. A verdict was returned in favor of the plaintiff for $21,177.95, and from the judgment entered on the verdict and from the order denying him a new trial, the defendant appeals.

It appears from the verdict that the jury found in favor of the defendant for the special damages alleged, and further consideration of contract “ C ” need not be had.

1. Upon the trial of the case a witness for the plaintiff was permitted to testify as to the contents of a telegram sent by the Wolff & Zwicker Iron Works from Portland to Uyerson & Son in Chicago, without having made proof of plaintiff’s inability to procure the original telegram. The ruling of the court, we think, was erroneous; but, since the evidence appeared to be wholly immaterial, and could not have influenced the jury, the error was without prejudice.

2. During the course of the trial the defendant was asked the following question: “Q. Mr. Carroll, what would be the reasonable value of one million gallons of water delivered in Butte, under the conditions existing here in the summer of 1900, from June until September ? ” A question somewhat similar was propounded to.the witness Probst. An objection to each of these questions was sustained, and error is predicated upon these rulings.

The materials to be furnished by the Wolff & Zwicker Iron Works were to be used by Carroll as a part of a pipe-line to bring waters from Divide creek and from Big Hole river into the city of Butte, to be sold to the citizens of that place. The apparent purpose of these questions was to show the profits which might have been realized from the plant from the time it should have been completed under the contracts with the Wolff & Zwicker Iron Works, to the time when it was actually completed. The early English and American cases are quite [309]*309generally agreed in excluding from recoverable damages for'the breach of a contract, profits which might have been realized from the business if the contract had been performed. But, under the later decisions, recovery of profits as damages is not precluded merely because they are claimed as profits per se, and the question whether they may or may not be recovered is now made to depend upon the facts of each particular case, under -the well-recognized rule that, if they depend upon such changing circumstances or vicissitudes of business as to make them uncertain of ascertainment, or if they are clearly speculative and not capable of being correctly ascertained under the recognized rules of evidence, they may not be recovered; while, on the other hand, if the loss of such profits is the natural and proximate result of the breach of the contract, and such profits are made reasonably certain of ascertainment by proof of the facts which form a rational basis for estimating the amount, they may be recovered as damages, upon the principle of compensation. (See 4 Cyc. 49, where the authorities are collected.)

In the present instance the defendant, in his own behalf, testified as to the reasonable value of the use of'the plant from the time it should have been completed under the contracts until it was actually completed, and clearly this was the correct standard for estimating his damages. Upon this question there is practically no difference of opinion. But considering the various contingencies upon which the profits from this plant necessarily depended, we think the court was correct in its ruling.

3. The defendant -was asked to state how the failure of the Wolff & Zwieker Iron Works to complete the pipe-line during the summer of 1900 could have made a shortage of water during the winter of 1901. An objection to the question was sustained, and error is assigned. There does not appear to have been any offer of proof made, and, as the question is not of such character that we can say that it appears what answer was sought, we are unable to determine whether the ruling of the court was correct or erroneous. (Tague v. John Caplice Co., 28 Mont. 51, 72 Pac. 297.)

[310]*3104. It is alleged in the complaint, and admitted in the answer, that the work under contracts “A” and “B” was completed on November 23, 1900. Upon the trial plaintiff offered in evidence a letter from the Wolff & Zwicker Iron Works to Carroll, dated October 22, 1900, which letter notified Carroll that the work under those contracts was then completed and ready for tests and inspection.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stenberg v. Beatrice Foods Co.
576 P.2d 725 (Montana Supreme Court, 1978)
State v. Souhrada
204 P.2d 792 (Montana Supreme Court, 1949)
Surman v. Cruse
187 P. 890 (Montana Supreme Court, 1920)
Herzig v. Sandberg
172 P. 132 (Montana Supreme Court, 1918)
C. W. Kettering Mercantile Co. v. Sheppard
142 P. 1128 (New Mexico Supreme Court, 1914)
Cuerth v. Arbogast
136 P. 383 (Montana Supreme Court, 1913)
Blaustein v. Pincus
131 P. 1064 (Montana Supreme Court, 1913)
Kuphal v. Western Montana Flouring Co.
114 P. 122 (Montana Supreme Court, 1911)
Neary v. Northern Pacific Railway Co.
110 P. 226 (Montana Supreme Court, 1910)
Cassidy v. Slemons & Booth
109 P. 976 (Montana Supreme Court, 1910)
State v. Trosper
109 P. 858 (Montana Supreme Court, 1910)
Rand v. Butte Electric Railway Co.
107 P. 87 (Montana Supreme Court, 1910)
Shandy v. McDonald
100 P. 203 (Montana Supreme Court, 1909)
Shane v. Butte Electric Ry. Co.
97 P. 958 (Montana Supreme Court, 1908)

Cite This Page — Counsel Stack

Bluebook (online)
88 P. 1012, 35 Mont. 302, 1907 Mont. LEXIS 81, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-bank-v-carroll-mont-1907.