First National Bank of Minot v. MacDonald Construction Co.

137 N.W.2d 667, 1965 N.D. LEXIS 117
CourtNorth Dakota Supreme Court
DecidedOctober 21, 1965
Docket8100
StatusPublished
Cited by11 cases

This text of 137 N.W.2d 667 (First National Bank of Minot v. MacDonald Construction Co.) is published on Counsel Stack Legal Research, covering North Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First National Bank of Minot v. MacDonald Construction Co., 137 N.W.2d 667, 1965 N.D. LEXIS 117 (N.D. 1965).

Opinion

BURKE, Chief Justice.

In this case the First National Bank of Minot sought to recover from A & A Contractors, Inc., and the MacDonald Construction Company, a balance of $40,000.00 alleged to be due the Bank upon an indebtedness of A & A.

Judgment was entered by default in favor of the Bank against A & A. The issues arising upon the Bank’s claim against MacDonald were tried to the court without a *669 jury. The trial court resolved these issues in favor of MacDonald and judgment was entered dismissing the Bank’s claim against MacDonald. The Bank has appealed from the judgment and has demanded a trial de novo in this court.

The Bank founded its claim against MacDonald upon (1), An assignment by A & A to the Bank of all monies due or to become due A & A from MacDonald upon a construction contract between A & A and MacDonald. (2), A guaranty by MacDonald of Loans made by the Bank to A & A up to the amount of $50,000.00 but limited to the amount of MacDonald’s indebtedness to A & A and (3), claimed representations on the part of MacDonald which it is urged create an estoppel to deny the claim.

MacDonald was the prime-contractor for the erection of certain housing units at the Minot Air Force Base. On July 31, 1958, A & A entered into a contract with MacDonald to make the heating and ventilating installations in these housing units for $420,000.00. A & A was a corporation engaged in the contracting business with its principal place of business located at Minot. From 1956 and thereafter it had done its principal banking business with the First National Bank of Minot. At sometime late in the fall of 1958, the Bank, agreed to finance A & A upon this building project by making advances based on completed work estimates. Thereafter on November 18, 1958, and on December 23, 1958, A & A executed assignments to the Bank of all monies due or to become due to it from MacDonald. The assignment of November 18, was general in character while that of December 22, was specifically limited to amounts to become due under the contract of July 31, 1958. Receipt of both of these assignments was acknowledged by MacDonald.

Paragraph III of the contract between MacDonald and A & A provided:

“III Method of Payment. Payments shall be made by the Contractor to the Sub-contractor monthly as the work progresses, as follows:
“On the day of each month designated by the Contractor, the Sub-contractor shall submit to the Contractor for inclusion in the Contractor’s estimate to the Owner, an estimate of the work installed during the preceding month by the Sub-contractor. Upon approval and payment of the Contractor’s estimate by the Owner, said Subcontractor shall be paid 90% of the amount of its approved estimate. 10% of such estimate shall be retained by the Contractor until final completion of the project. Final payment shall be made when written acceptances and payment in' full have been received from the Owner by the Contractor, provided satisfactory evidence has been furnished by Sub-contractor that all claims for labor and materials have been satisfied and paid -in full.”

Paragraph XHIb of the contract provides in part:

“ * * ⅜ if ⅛6 Sub-contractor shall fail to pay and satisfy any such claim, demand, judgment or expense the Contractor may do so, with or without notice to the Sub-contractor, as it may elect, and charge any sum so paid to the Sub-contractor. * *
Paragraph VI of the contract provided:
“ * * * Should the Sub-contractor fail to do so to the satisfaction of the Contractor, or should it become insolvent, or refuse to follow the plans and specifications or to perform the work in a good and workmanlike manner, or cause by any action the stoppage of the work of the other trades upon the structure, or fail to comply in any other respect with any of the articles of this agreement, then the Contractor may, after giving forty-eight (48) hours notice of such failure, neglect, default, interference or breach of contract, in writing, by mail directed to the Sub *670 contractor at his last known residence or place of business, or delivered at such place, or to the foreman in charge of the-work for the Sub-contractor, enter into and take possession of the said premises and work, materials, tools, applicances and equipment and workmen (The Sub-contractor agreeing that in this event it will turn over to the Contractor all necessary material contracts, bills of lading for material en-route and any other information that would tend to lessen the cost of completion), and may provide such other material, appliances and workmen as may be necessary to complete this work, and the expense of such notice and of the completion of such work shall be deducted from the amount due or to become due to the Sub-contractor >}« ⅝ ⅜

All payments made by MacDonald upon its subcontract with A & A were made to A & A and the Bank jointly. These payments totaled $300,325.53. The first payment was made February 4, 1959, and the last on January 11, 1960.

These payments were made upon estimates of percentage of work completed which were submitted from time to time by A & A. Each of the estimates bore an endorsement that it was approved by MacDonald’s representative upon the construction job. In addition to submitting these estimates to MacDonald, A & A also furnished copies to the Bank and the Bank made loans to A & A up to 80% of the amounts shown to be due A & A from MacDonald upon such estimates. The contract called for the construction of 932 units at $450.00 apiece. The estimates contained a detailed statement of the percentage of completion of the units under construction and ended with a summary of the total work completed to the date of the estimate. In the last estimate submitted, dated November 30, 1959, this summary stated:

"Total work completed to date $332,238.82
Less previous estimates 215,302.61
Net due this estimate 116,876.21”

Each of the other estimates contained an item designated as retainage in accordance with the contract between MacDonald and A & A which provided that MacDonald in making partial payments to A & A pursuant to estimates should retain 10% of the value of the completed work. Thus the summary of the estimate of September 10, 1959, showed the following:

"Total work completed to date $294,300.00
Less previous estimate 148,700.00
Less retainage 10% 29,300.00
Net due this estimate $110,170.00”

If retainage had been deducted in the estimate of November 30, 1959, in accordance with the contract between MacDonald and A & A the net amount shown by this estimate would have been reduced from $116,876.21 to $83,642.22. Of this the Bank, was aware or should have been aware, both from the estimates previously submitted and from the contract between MacDonald and A & A, a copy of which was in the Bank’s possession.

On December 1, 1959, A & A’s indebtedness to the Bank was $82,000.00.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Global Financial Services, Inc. v. Duttenhefner
1998 ND 53 (North Dakota Supreme Court, 1998)
Tetzloff v. Tetzloff
1998 ND 47 (North Dakota Supreme Court, 1998)
First Interstate Bank of Fargo, N.A. v. Larson
475 N.W.2d 538 (North Dakota Supreme Court, 1991)
Industrial Indemnity Co. v. Anderson
697 F. Supp. 1532 (D. North Dakota, 1988)
McKenzie County Social Services Board Ex Rel. Sax v. V.G.
392 N.W.2d 399 (North Dakota Supreme Court, 1986)
State ex rel. Moug v. North Dakota Automobile Assigned Claims Plan
341 N.W.2d 623 (North Dakota Supreme Court, 1983)
State v. Cheers
306 N.W.2d 676 (Wisconsin Supreme Court, 1981)
Pioneer State Bank v. Johnsrud
284 N.W.2d 292 (North Dakota Supreme Court, 1979)
First National Bank of Aberdeen v. Jacobs
273 N.W.2d 743 (South Dakota Supreme Court, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
137 N.W.2d 667, 1965 N.D. LEXIS 117, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-national-bank-of-minot-v-macdonald-construction-co-nd-1965.