First Nat. Bank of McGregor v. Collins

266 S.W.2d 506, 1954 Tex. App. LEXIS 2036
CourtCourt of Appeals of Texas
DecidedMarch 24, 1954
DocketNo. 10207
StatusPublished
Cited by2 cases

This text of 266 S.W.2d 506 (First Nat. Bank of McGregor v. Collins) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Nat. Bank of McGregor v. Collins, 266 S.W.2d 506, 1954 Tex. App. LEXIS 2036 (Tex. Ct. App. 1954).

Opinion

ARCHER, Chief Justice.

This suit was instituted by The First

National Bank of McGregor, hereinafter called appellant, against M. Z. Collins, doing business as Collins Construction Company and W. K. Montgomery, doing business as Montgomery Construction Company, hereafter called appellees, irrespective of the fact that in some phases of this case such parties may be appellants, to recover judgment for $15,220 growing orit of the execution by Montgomery to the Bank of notes- aggregating $15,220 and the signing and delivery of a letter, statement by Collins that he would pay 90% of the amounts of certain certificates, and the signing and delivery of such completion certificates by Collirisl

Appellee Collins had a contract to construct a housing project at McGregor, Texas and Montgomery was given two subcontracts to make certain excavation and concrete work.

[508]*508Plaintiff alleged in its pleading that Montgomery was given the contract by Collins to do certain grading, masonry and concrete work for a total consideration, of $23,550, and that Montgomery contacted plaintiff and requested that the Bank advance money to finance the subcontract and to pay for work, materials, etc., in the performance of the subcontract; and that the Bank was unwilling to advance the money to Montgomery based on an assignment of the contract, and that Collins wrote a letter dated October 28, 1952, herein set out, but that the Bank still refused to advance the money solely upon the subcontract and upon the letter, and that Collins contacted the Bank and told the Bank that he would receive payments on his general contract at intervals upon completion of portions of the work, and promised that he would have prepared at weekly intervals an estimate of the amount of work completed by Montgomery, setting forth the amount of money due for work, and requested the Bank to advance funds to finance the subcontract and agreed that he would pay the Bank 90% of all completion estimates authorized by himself or his company ; that it was to the interest of Collins for the Bank to advance the funds, was benefitted thereby, and he assumed the said liability as a primary obligation.

That in carrying out the plan, contract and agreement Collins at various times sent completion estimates to the Bank by Montgomery showing to the Bank that Montgomery had completed portions of said subcontract and was entitled to various sums of money, which plaintiff Bank in the alternative says were false and fraudulently made; that the Bank in reliance upon Collins’ promises, representations and agreements advanced 90% of such completion orders from time, to time, in a total sum of $15,220. That Montgomery signed notes acknowledging the receipt of the money and promising to pay the said sums to the Bank, that none of the notes sued on had been paid; that Collins in violation of his contract and agreement paid certain sums of money to other persons in derogation of the plaintiff’s rights; that Collins having induced plaintiff to advance the sums of money by his actions, promises and conduct, knowing that plaintiff would probably suffer damages is now estopped to deny liability for the sums of money. Defendant Collins answered that the alleged promises were not in writing and are within the Statute of frauds and denied the allegations of the plaintiff, and further plead that' Montgomery had failed to perform the work except to the amount of $15,726.75, and alleged that before the commencement of this suit Montgomery released Collins from all terms and claims under the subcontract.

Further allegation was made that before the filing of this suit that defendant Collins made payments to or for Montgomery in excess of the amount due said Montgomery, or a sum of $18,025.07 in payment for obligations incurred by Montgomery in attempting to perform his subcontract; and further answer was made that all obligations, if any due the Bank by Collins, which are denied, that such obligation was satisfied and paid by payments to other laborers and materialmen, and that the retention of a check for $2,995.53 by plaintiff constitutes an acceptance thereof in full satisfaction of the cause of action.

Montgomery filed his answer and cross-action, pleading the subcontracts, and that he began the performance of the contracts until prevented by Collins, and that Collins did not make the payments as provided by the subcontract; that Collins supervised and directed the work and knew that Montgomery would have to make expenditures, etc. and in failing to make the payments caused Montgomery to be forced to sell his equipment at a loss and sought damages.

The contract is as follows:

“(Contract) M. Z. Collins Construction Co.
Box 5065, Austin, Texas
“To: Montgomery Construction Co.
Killeen, Texas.
“Please furnish all necessary labor, materials, and equipment to perform the work [509]*509listed below in strict accordance with the plans and specifications for the subject job:
“1. Street work, curbs, gutters, curb and gutters, site grading, and building foundations ready for masonry work; batterboards for buildings to be erected by general contractor and reinforcing steel to be furnished FOB trucks, job-site, by general contractor; garbage can slabs and clothesline pole foundations are included in this lot; for the lump sum price of $23,550.00.
“Terms and conditions of this contract are:
******
“4. Invoices received prior to the first of the month will be paid on or before the 20th of the following month, less 15% retainage, for work and materials approved by the Architect. Retainage will be paid within 30 days after completion of the job. Make invoices in triplicate. * * *
“Please sign and return one copy of this order to us.
“Yours very truly,
M. Z. Collins Construction Co.
By --------m-
“Accepted: Montgomery Construction Co..
By W. K. Montgomery
“Note: All concrete used in the performance of this sub-contract shall be purchased from N. R. Smith for prices listed in our Material Order No. 1052-1, a copy of which is attached.”

The letter from Collins is as follows:

“(Letterhead) M. Z. Collins Construction Co.
Box 5065, Austin, Texas
“28 October, 1952
“Montgomery Construction Co. Killeen, Texas
“Gentlemen:
“Please be advised that all payments made by us for your performance of our Work Orders 1052-500 and 1052-2401 will be made jointly to you and to the First National Bank, McGregor, Texas, for certain items of work in the construction of Project Texas 102-1 for the Housing Authority of the City of McGregor, Texas.
“Yours very truly,
M. Z. Collins Construction Co.
By: s/ M. Z. Collins.
“Acknowledgements: 1. Montgomery Construction Co.
s/ W. K. Montgomery.
2.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Compton v. Polonski
567 S.W.2d 835 (Court of Appeals of Texas, 1978)
Wilkinson v. SOUTHERN FARM SUPPLY ASS'N
409 S.W.2d 435 (Court of Appeals of Texas, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
266 S.W.2d 506, 1954 Tex. App. LEXIS 2036, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-nat-bank-of-mcgregor-v-collins-texapp-1954.