First Home Savings Bank, FSB v. Nernberg

648 A.2d 9, 436 Pa. Super. 377, 1994 Pa. Super. LEXIS 2239
CourtSuperior Court of Pennsylvania
DecidedJuly 18, 1994
StatusPublished
Cited by43 cases

This text of 648 A.2d 9 (First Home Savings Bank, FSB v. Nernberg) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
First Home Savings Bank, FSB v. Nernberg, 648 A.2d 9, 436 Pa. Super. 377, 1994 Pa. Super. LEXIS 2239 (Pa. Ct. App. 1994).

Opinion

*381 CIRILLO, Judge:

A. Richard Nernberg t/d/b/a A.R. Building Company appeals from the judgment entered in the Court of Common Pleas of Allegheny County, granting First Home Savings Bank’s request to enforce its mortgage lien against the entire mortgaged parcel. We affirm.

The facts as stipulated by the parties are as follows: First Home Savings Bank (hereinafter “Bank”) is a savings and loan association organized and existing under the laws of the Commonwealth of Pennsylvania. Bank’s principal place of business is Pittsburgh, Pennsylvania. A. Richard Nernberg resides in the City of Pittsburgh and conducts a real estate, management and development business as a sole proprietorship under the name “A.R. Building Company.”

On December 22, 1986, A. Richard Nernberg and his wife, Susan Nernberg, executed a promissory note payable to Bank in the principal amount of $375,000.00 (“Note”). The Note is a demand note 1 with interest payable monthly at the prime rate plus 1.5 percent. Under the terms of the Note, the Nernbergs are personally liable for ten percent of the original principal amount, or $37,500.00.

On December 22, 1986, simultaneous with the execution of the Note, A. Richard Nernberg as “A.R. Building Co.” (hereinafter collectively referred to as “Developer”) granted Bank a first mortgage on Lots 6 through 15 of a townhouse development project named “Baldwin Village.” 2 The mortgage was duly recorded in the Recorder of Deeds Office in Allegheny County, Pennsylvania.

On April 3, 1987, Developer wrote to Bank as follows:

*382 Dear Mr. Vuono:

We are preparing to construct additional townhouses on the Lots 6 and 7 at the above-captioned development [Baldwin Village]. This will provide for the construction of an additional 13 townhouses.

Would you please furnish a written release figure which would be paid once the townhouses are sold?

Very truly yours,

A. Richard Nernberg,

President

On April 14, 1987, Bank, by its Vice President Robert J. Vuono, replied to Developer’s letter as follows:

Dear Dick,

I am in receipt of your letter of April 3, regarding Baldwin Village. Sorry for the delay in response. Please be advised that we are prepared to release that portion of our mortgage on Lots 6 and 7 upon receipt of $75,000.00 paydown on your existing loan.

I trust this is satisfactory for your needs. If you have any questions, please feel free to call.

Robert J. Vuono

Vice President

Mr. Vuono, as Bank’s Vice President in charge of commercial loans, had authority to write the letter of April 14, 1987. Whatever the legal effect of the exchange of the April, 1987 letters between Developer and Bank (hereinafter the “Release Agreement”), both parties agree that Bank is bound by that effect.

' On April 6,1987, Developer had not yet started construction of Buildings 6 and 7, 3 which were to contain six and eight townhouses, respectively. 4 Construction of Building 6 started *383 in June, 1987 and was completed in November, 1987 at a cost of $194,806.00. Construction of Building 7 started in July, 1987 and was completed in November, 1987 at a cost of $291,797.00.

In November of 1987, Developer sold two units in Building 6 (Units “C” and “E”), and Bank released the lien of its mortgage for both units, when paid $15,000.00 ($7,500.00 per unit) by Developer. In May of 1988, Developer sold another unit in Building 6 (Unit “A”). Again, Bank released the lien on its mortgage against Unit “A” when paid $7,500.00 by Developer.

On June 20, 1988, Bank demanded payment of the entire unpaid principal of the $375,000.00 loan, which at that date was $352,500.00 ($375,000.00 minus the $22,500.00 previously paid). At that time, Developer was current in the payment of interest on the Note and was not in the process of constructing any additional townhouses. In fact, Developer has not, since June 20, 1988, begun construction of any additional townhouses in Baldwin Village.

On June 28, 1988, Developer tendered to Bank the sum of $52,500.00, which represented the balance due under the Release Agreement, 5 and asked for release of Bank’s mortgage lien on the balance of Lots 6 and 7. Bank rejected the tender.

On June 29, 1988, a closing was held for the sale of two units in Building 6 (Units “B” and “D”). The settlement officer of these closings, acting on behalf of Developer, tendered to Bank the sum of $52,500.00 from the sale of these two units. Bank again rejected the tender of the $52,500.00. Bank indicated, however, that it would release the lien of its first mortgage with respect to Units “B” and “D” on receiving evidence that those units had been under contract of sale prior to June 20, 1988 and in return for a principal paydown of $7,500.00 per townhouse. Bank’s reasoning was that if Units *384 “B” and “D” had been under contract of sale at the time that Bank demanded payment of the unpaid principal on the Note, then under the doctrine of “equitable conversion,” the “B” and “D” units should be regarded as already sold on the date Bank put Developer into default.

On November 16, 1988, Developer paid $15,000.00 to Bank with respect to the sale of Units “B” and “D” from Budding 6, and Bank released the lien of its mortgage from those two units. Bank accepted this payment based upon the “equitable conversion” theory set forth above, Units “B” and “D” having been under contract of sale as of June 20, 1988.

On February 24, 1989, Developer entered into an “Interim Agreement” with Bank. Basically, Bank would accept the balance of the $75,000.00 principal reduction from the April, 1987 correspondence and would release the lien of its mortgage from Lots 6 and 7, but without prejudice to its contention that after June 20, 1988, it was under no obligation to release the lien of its mortgage from further units on Lots 6 and 7. Accordingly, Developer paid an additional $37,500.00 to Bank, and Bank released its mortgage from the balance of Lots 6 and 7.

Under the “Interim Agreement,” Developer agreed to accept a “conditional” personal liability for the total sale price of townhouses sold after June 20, 1988 up to the outstanding principal balance of the loan should Bank’s position be determined in litigation to be correct. Bank agreed, in turn, that should Developer’s position be accepted, then Bank’s rights would be limited to the ten percent personal liability ($37,-500.00) as set forth in the loan documents and to its mortgage on the balance of the property, Lots 8 through 15.

The “Interim Agreement” did not resolve the controversy between Developer and Bank.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Strub, M. v. Wesol, A.
Superior Court of Pennsylvania, 2026
Somerlot, S. v. Jung, S.
2025 Pa. Super. 166 (Superior Court of Pennsylvania, 2025)
J.R. Enterprises v. Hartman Snack Group
Superior Court of Pennsylvania, 2023
MENTECKY v. CHAGRIN LAND, L.P.
W.D. Pennsylvania, 2023
Royer, R. v. UNUM Life Insurance
Superior Court of Pennsylvania, 2021
WELCH v. NATIONSTAR MORTGAGE LLC
E.D. Pennsylvania, 2020
Hydrojet Services, Inc. v. Reading Area Water Authority
Commonwealth Court of Pennsylvania, 2019
Sodexomagic, LLC v. Drexel Univ.
333 F. Supp. 3d 426 (E.D. Pennsylvania, 2018)
Walney v. SWEPI LP
311 F. Supp. 3d 696 (W.D. Pennsylvania, 2018)
Giant Eagle Inc v. Commissioner IRS
822 F.3d 666 (Third Circuit, 2016)
Spagnolo, F. v. Ragano, J.
Superior Court of Pennsylvania, 2015
Stephan v. Waldron Electric Heating & Cooling LLC
100 A.3d 660 (Superior Court of Pennsylvania, 2014)
W S International, LLC v. M. Simon Zook, Co
566 F. App'x 192 (Third Circuit, 2014)
Big Mountain Imaging v. Unemployment Compensation Board of Review
48 A.3d 492 (Commonwealth Court of Pennsylvania, 2012)
Middletown Township v. Unemployment Compensation Board of Review
40 A.3d 217 (Commonwealth Court of Pennsylvania, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
648 A.2d 9, 436 Pa. Super. 377, 1994 Pa. Super. LEXIS 2239, Counsel Stack Legal Research, https://law.counselstack.com/opinion/first-home-savings-bank-fsb-v-nernberg-pasuperct-1994.