Fire Protection Equipment Co. v. Rabinowitz

194 So. 733, 1940 La. App. LEXIS 297
CourtLouisiana Court of Appeal
DecidedMarch 25, 1940
DocketNo. 16988.
StatusPublished
Cited by1 cases

This text of 194 So. 733 (Fire Protection Equipment Co. v. Rabinowitz) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fire Protection Equipment Co. v. Rabinowitz, 194 So. 733, 1940 La. App. LEXIS 297 (La. Ct. App. 1940).

Opinion

McCALEB, Judge.

The plaintiff, Fire Protection Equipment Company, Inc., a corporation engaged in the business of installing sprinkler systems, brought this suit to recover the balance due, plus certain extras, under a written contract made by it with the defendant, Jacob Rabinowitz doing business under the name of J. Rabinowitz Company.

It alleges, in substance, that, on August 3, 1937, it submitted to the defendant a proposal for the installation of a wet pipe system of automatic sprinklers in the defendant’s building located at No. 533-535 Iberville Street' in the City of New Orleans; that, in accordance with the request of the defendant, it submitted a blue print or plan showing precisely the sprinklers to be installed under the proposal and secured the approval of such plan by the Louisiana Rating and Fire Prevention Bureau and that, thereafter, on August 30, 1937, it entered into a written contract with the defendant whereby it agreed to install the sprinkler system in consideration of a price of $1,440. It further alleges that it has complied with all of the provisions of the contract and has completed the work in accordance therewith; that, after the completion of said work, it obtained the written approval of the Louisiana Rating and Fire Prevention Bureau in conformity with the terms of the agreement and that the defendant paid on account of the contract price the sum of $1,380, leaving a balance due and owing of $60 which the defendant, without just cause, refuses to pay. It further avers that, in addition to the balance due on the contract price, the defendant is also responsible to it for the sum of $2.25 for labor and materials furnished upon the job which were not included in the contract price and that the defendant is furthermore liable for an extra charge of $63.40 because he refused to erect staging for outside sprinkler installation which staging became necessary as a consequence of the fact that certain windows of his building were boarded and could not be used during the time the work was being performed. It is also alleged that, under the terms and conditions of the contract, the defendant is liable for plaintiff’s attorney fees on the entire contract price plus extras and claim is made for the sum of $150.56 for this item.

In due course, the defendant answered plaintiff’s petition and admitted that he entered into the written contract for the erection of the sprinkler system. He denied, however, any liability to plaintiff on the ground that the latter did not perform the contract in accordance with its terms and conditions; that the agreement provides that plaintiff’s work is to be approved by the Louisiana Rating and Fire Prevention Bureau; that plaintiff did not obtain the Bureau’s full approval of the work after its completion because the letter of said Bureau stated that its representative found that the plaintiff failed to provide all of the necessary sprinklers which were required to reduce the exposure charge and that the windows at the rear wall of the *735 building are exposed by the building in the rear of the property. He further alleged that he paid to plaintiff on account of the contract the sum of $1,380 without prejudice to his rights and that he withheld the balance of $60 on the contract price because plaintiff stated to him that it would cost that amount to install the additional window sprinklers which were required by the Louisiana Rating and Fire Prevention Bureau. He further denied that he was indebted to plaintiff for the extras sought to be recovered.

The defendant also filed a reconventional demand in which he specifically set forth plaintiff’s failure to comply with the contract ; that the cost of providing the necessary sprinklers to complete the job amounted to the sum of $196; that, in addition thereto, plaintiff had damaged the plaster of the ceilings of his building in installing the sprinkler system; that it would cost the sum of $85 to repair this damage; that he was also entitled to a credit in the amount of $1.75 for a certain standpipe which had been purchased from him by the plaintiff and that he was further entitled to recover the sum of $3.90 per month from September 30, 1937, representing the increase in his insurance rate as the result of plaintiff’s failure to install the additional sprinklers required by the Louisiana Rating and Fire Prevention Bureau as provided by the contract.

After a hearing in the lower court on the foregoing issues, the trial judge dismissed plaintiff’s suit as well as the defendant’s re-conventional demand as of non-suit. Both litigants have appealed to this court from the adverse decision.

The main facts of the case are not seriously disputed and we find them to be as follows: The defendant, Rabinowitz, had, just prior to the time the contract was entered into, erected a six-story concrete building for the purpose of operating a merchandizing business. Being desirous of having this building adequately protected against fire and also in order to obtain a reduction in his insurance rates, he contacted a number of firms engaged in the business of installing sprinkler systems for the purpose of having such a system installed in his new building. The plaintiff concern was the successful bidder on the job and agreed to do the necessary work for the sum of $1,440. A written contract between the parties was accordingly entered into on a standard form prepared by the National Automatic Sprinkler Association (and furnished by the plaintiff) whereby the plaintiff agreed, for the above stated price, to install the “necessary Automatic Sprinklers and necessary Open Sprinklers” in the building. This contract further provided that the plaintiff would erect and install in the building a “wet pipe system of automatic sprinklers and/or fire extinguishing apparatus as described in the specifications consisting of 1 sheet which are hereto attached and made part hereof, and subject to inspection by Louisiana Rating & Fire Prevention Bureau acting as the Agent of both parties, whose inspection and approval of the work done hereunder by the Seller shall be conclusive evidence of the. proper performance and completion of the Seller’s obligations hereunder.”

Prior to the signing of the contract by the parties, the plaintiff prepared a plan or blue print of the system it intended to install in the building. This plan shows the number of automatic sprinklers and open sprinklers which would be furnished by the plaintiff. Mr. Hiller, President of the plaintiff corporation, and Mr. Korn, its engineer, testified that this blue print was made at the request of the defendant because the latter was anxious to determine exactly what he was getting under the agreement. These statements are vigorously denied by Mr. Bronfin who appears to have represented the defendant throughout the negotiations. Mr. Bronfin declares that he did not know anything about the plan until sometime after the work had begun when Mr. Korn informed him that a blue print of the installation work had been made for the Louisiana Rating and Fire Prevention Bureau. Mr. Dixey, one of the engineers of the Bureau, testifying for the defendant, stated that, in an installation job of the magnitude of the one in contest, the Bureau requires that plans or blue prints be submitted to it for its approval.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

West Bros. v. Pierson
2 So. 2d 71 (Louisiana Court of Appeal, 1941)

Cite This Page — Counsel Stack

Bluebook (online)
194 So. 733, 1940 La. App. LEXIS 297, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fire-protection-equipment-co-v-rabinowitz-lactapp-1940.