Finne v. Maryland Casualty Co.

173 P. 501, 102 Wash. 651, 1918 Wash. LEXIS 983
CourtWashington Supreme Court
DecidedJune 21, 1918
DocketNo. 14664
StatusPublished
Cited by4 cases

This text of 173 P. 501 (Finne v. Maryland Casualty Co.) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Finne v. Maryland Casualty Co., 173 P. 501, 102 Wash. 651, 1918 Wash. LEXIS 983 (Wash. 1918).

Opinion

Mitchell, J.

The evidence in this case shows that respondents, plaintiffs, are partners, and on June 1, 1916, were already under contract with the board of regents of the University of Washington to construct a building, known as the Home Economics Building, and complete it by September 12, 1916, with a penalty of $100 for each day’s delay thereafter that would interfere with the use of the class rooms and entrances. On June 1,1916, respondents, by written contract, sublet the lathing and plastering of the building to defendant, Tom Hogart, who was to furnish material and labor, his work to start upon notice from respondents and continue in harmony with the other work on the building, and complete it without delay. Respondents agreed to pay defendant $5,774, as follows: On the 10th of the month, eighty-five per cent of the value of material and labor actually put in the building during the preceding month, according to approved estimates. On June 17, 1916, appellant, Maryland Casualty Company, delivered to respondents a bond assuring performance of the Hogart contract without loss or dam[653]*653age to respondents. The bond, inter alia, contains these words:

“Provided, however, that this bond is executed upon the following express conditions, the performance of each of which shall be a condition precedent to any right of recovery thereon:
“First: That in the event of any default on the part of the principal, a written statement of the particular facts showing such default and the date thereof shall be delivered to the surety by registered mail, at its office in the city of Baltimore, Maryland, promptly and in any event within ten days after the obligee or his representative, or the architect, if any, shall learn of such default; the surety shall have the right within thirty days after the receipt of such statement to proceed, or procure others to proceed, with the performance of such contract.”

Tom Hogart signed the bond as principal. Hogart proceeded with the lathing and plastering (subletting the lathing to one L. E. Nelson) until Saturday, August 19, 1916, when Hogart’s bank account was garnisheed, by reason of which the pay checks given his craftsmen on that day were dishonored. Plasterers could not be had for this work until the checks were paid. Hogart failed to take up the checks, and on August 23,1916, respondents had a conference with the soliciting agent of appellant for Seattle, at that time explaining the situation; and on that same day, by registered mail, sent written notice to appellant at its home office in Baltimore, stating therein financial delinquencies of Hogart with respect to "this contract; that his bank account had been garnisheed; that he was unable to pay or take care of his pay-roll of the last week. The notice further says as follows:

“Mr. Hogart’s men have refused to continue on the job until, they are paid for their last week’s work, and in order to have the job completed it has become necessary for us to take up the checks issued by Mr. Hogart [654]*654last Week, and it appears that we will-have to take care of the pay roll from now on. We are charging these items to the account of Tom Hogart and are looking to your company as surety of his bond to see that we ¿re' reimbursed. ”

At this time, August 23, 1916, the work remaining undone under the Hogart contract included the two entrances to the building. Hogart did not return to work after August 19, 1916, and the work was at a standstill until August 24,1916, when respondents, took up the dishonored cheeks of Hogart and proceeded faithfully with the job, completing it about October 6; 1917, at prices for labor and material as low as pos7 sible. Seattle lawyers for appellant, on August 22, 1916, had notice of the situation, and on .that day nofiT fied the home office by wire that Hogart had probably defaulted, and on August 28, 1916, according to reply instructions, the lawyers requested respondents to furnish a statement of the Hogart account and condition of the contract, which was done on August 29, 1916. Appellant never signified any wish to complete the work, and in no way objected to respondents completing it. Finne and Gjarde, respondents, then brought this action, declaring on the lathing and plastering contract of June 1,1916, as to defendant Hogart, and on the bond as to both Hogart and the Maryland Casualty Company, demanding judgment in the sum of $3,573.25 and interest, alleging that amount to be the cost to appellant in excess of the contract price of $5,774, and some extras amounting to $161.25. Defendant Hogart, in his answer, counterclaimed for extra labor and material in the sum of $3,873.785 while the answer of appellant, Maryland Casualty Company, in addition to substantial denials, alleged affirmative matter (now most strongly relied on) that respondents, without appellant’s consent, failed; to perform [655]*655certain express and enumerated conditions contained in the bond, which it is claimed are conditions precedent to a recovery on the bond. Replies were filed denying the new matter in each answer. There was a trial without a jury, findings and conclusions were made, and judgment was entered for respondents in the sum of $3,016.58 against Hogart, and in the sum of $2,093.68 against the Maryland Casualty Company, the latter amount being also included in the judgment against Hogart; and it is further provided in the judgment that defendants may pay, and take credit on the judgment, the claims of L. E. Nelson for $481.72, and Sam' Hunter & Company for $1,060.95. The Maryland Casualty Company appeals.

The facts above stated are supported by a preponderance of the evidence and so found by the trial court, as' well as the following additional facts: Tom Hogart’s' counterclaim was established to the extent of $318.07 and no more; there were extras in the amount of $161.25; there was a balance of $481.72 due L. E. Nelson for lathing under his subcontract with Hogart, for which claim had been filed with the board of regents; there was a claim of $1,060.95 due Sam Hunter & Company for material furnished before default of Hogart, for which notice of delivery was given and claims filed with the board of regents; and the totail cost to respondents was $9,472.50, which included $1,-125.50, consisting of expenditures after Hogart’s default or because of failure to file claims for work or material furnished Hogart, and hence no liability against respondents. The judgment of $2,093.68 against the company is arrived at by taking from the whole cost of $9,472.50 the sum of $1,125.50, made up of claims for which respondents are not liable and cost of construction to them after Hogart’s default, which leaves $8,347, from which last amount take the Hogart [656]*656counterclaim, allowed, of $318.07, thus leaving $8,-028.93, from which subtract $5,774 (the original Hogart contract price), plus extras of $161.25, equalling $5,935.25, thus finally leaving $2,093.68. So that the judgment complained of provides only enough to pay what had already been paid on Hogart’s account before default or was unpaid at that time and supported by proper lien notices filed, and does not cover the cost of any work or material after Hogart’s default, nor of either work or material furnished Hogart or Nelson where there was no lien or claim notice filed, and hence no liability therefor against respondents and their bondsman to the board of regents. It is also to be noticed that respondents had, prior to Hogart’s default, paid him $5,400, a large portion of which, without question, was expended on the building.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bekins Moving & Storage Co v. Maryland Cas. Co.
244 P.2d 1100 (Idaho Supreme Court, 1952)
City of Tacoma v. Peterson
25 P.2d 1034 (Washington Supreme Court, 1933)
John Dower Lumber Co. v. New Amsterdam Casualty Co.
277 P. 696 (Washington Supreme Court, 1929)

Cite This Page — Counsel Stack

Bluebook (online)
173 P. 501, 102 Wash. 651, 1918 Wash. LEXIS 983, Counsel Stack Legal Research, https://law.counselstack.com/opinion/finne-v-maryland-casualty-co-wash-1918.