Finlay Properties, Inc. v. Hoosier Contracting, LLC

802 N.E.2d 453, 2003 WL 23193253
CourtIndiana Court of Appeals
DecidedJanuary 23, 2004
Docket49A02-0307-CV-644
StatusPublished
Cited by4 cases

This text of 802 N.E.2d 453 (Finlay Properties, Inc. v. Hoosier Contracting, LLC) is published on Counsel Stack Legal Research, covering Indiana Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Finlay Properties, Inc. v. Hoosier Contracting, LLC, 802 N.E.2d 453, 2003 WL 23193253 (Ind. Ct. App. 2004).

Opinion

OPINION

FRIEDLANDER, Judge.

Finlay Properties, Inc. (Finlay) appeals the trial court's grant of an Emergency Motion to Compel Arbitration brought by Hoosier Contracting, LLC (Hoosier). The sole issue on appeal is: Did the trial court err in finding that Hoosier did not waive its contractual right to arbitration?

We affirm.

*454 The facts most favorable to the ruling demonstrate that in the fall of 2000, Finlay and Hoosier entered into two separate construction contracts relating to the renovation of the Bedford Park apartment complex (Bedford Project). Both contracts contained arbitration clauses providing for arbitration in accordance with the Construction Industry Arbitration Rules of the American Arbitration Association (AAA) in the event of a claim arising out of or relating to the respective contracts. During the Bedford Project, a dispute arose between Finlay and Hoosier regarding Finlay's obligation to pay for Hoosier's extra work claims. At the completion of the Bedford Project, Hoosier requested a $582,251.99 payment, representing the balance owed on the contracts and extra work Hoosier had performed. Finlay refused to pay the additional monies.

On May 17, 2002, Hoosier filed a complaint in Indiana state court against Fin-lay, in addition to other consensual and non-consensual len holders involved in the Bedford Project. As stated by Hoosier in its Emergency Motion to Compel Arbitration:

The initiation of state court proceedings was necessary under Indiana's mechanic's lien statute, to foreclose Hoogier's lien interest against numerous consensual and non-consensual lien holders, and of arguably greater significance, to pursue the Mountbatten Surety Company, which provided a bond in favor of Hoosier Contracting on the Bedford Park project. Hoosier is not in contractual privity with Mountbatten and cannot compel its participation in arbitration.

Appellee's Appendix at 165. Soon thereafter, on July 15, 2002, Hoosier asserted its contractual right to arbitrate its claims against Finlay for the dispute arising out of the Bedford Project by demanding arbitration and advancing a $6,000 filing fee to the AAA. 1 Finlay did not object to Hoosier's demand for arbitration. Further, in response to Finlay's counterclaims, Hoosier asserted as an affirmative defense that all claims between Hoosier and Finlay were subject to binding arbitration.

Thereafter, the parties attempted to resolve the dispute through mediation under Indiana ADR rules. In preparation for the mediation and in order to facilitate an informed and meaningful mediation, Hoosier took three depositions and served limited discovery on Finlay. Finlay did not object to the discovery requests or the depositions and was present and participated in the depositions. Finlay did not undertake its own discovery but Hoosier produced certain documents to Finlay that it felt supported its claim. Mediation occurred in October 2002, but was unsuceessful.

Finlay's original counsel withdrew its appearance in February 2003. 2 Previous *455 ly, Finlay's original counsel had never objected to Hoosier's commencement of arbitration proceedings in the AAA pursuant to the construction contracts governing the Bedford Project. Finlay's current counsel filed an appearance in March 2008. For the next two months, Hoosier and Finlay prepared for arbitration, including selection of arbitrators to hear the dispute. On May 7, 2003, however, during a preliminary hearing with the AAA, Finlay's counsel suggested he might object or move to quash the arbitration. Hoosier immediately filed an Emergency Motion to Compel Arbitration on May 13, 2008. Finlay filed a Motion to Quash on May 22, 2003, and the matter was set for a hearing on May 30, 2008.

At the hearing, Finlay asserted that Hoosier had waived its right to compel arbitration of the dispute by instituting state court litigation and pursuing the matter in a judicial forum. Hoosier countered that it had acted consistent with its right to arbitrate the dispute, had only instigated state court litigation to preserve its substantive rights against related entities, and had engaged in limited discovery-without Finlay's objection-for purposes of the October mediation. After the hearing, the trial court found that Hoosier had not waived its right to arbitrate and granted Hoogier's Emergency Motion to Compel Arbitration. Finlay moved to stay the order pending appeal, Hoosier filed its objection, and the trial court sustained the objection. 3

On appeal, Finlay contends that the trial court's ruling compelling arbitration was error. Specifically, Finlay asserts that Hoosier actively engaged the judicial process and availed itself of the benefits of litigation in such a way that return to arbitration would be inconsistent with principles of waiver and fundamentally unfair.

As an initial matter, neither party contests the validity of the arbitration agreements at issue. The sole issue presented is if Hoosier waived its ability to compel arbitration through inconsistent actions. We agree with the general proposition that despite a request for. arbitration in the initial complaint, a party may waive its right to arbitration by subsequent actions that are inconsistent with that right. Mid-America Surgery Ctr., L.L.C. v. Schooler, 719 N.E.2d 1267, 1270 (Ind.Ct.App.1999) ("[alithough a written agreement. to submit a dispute to arbitration is valid and enforceable, the right to require such arbitration may be waived by the parties ... [and] waiver need not be in express terms, but may be implied by the acts, omissions or conduct of the parties") (citations omitted).

Waiver is a question of fact under the cireumstances of each case. Kilkenny v. Mitchell Hurst Jacobs & Dick, 733 N.E.2d 984 (Ind.Ct.App.2000). In determining if waiver has occurred, courts look at a variety of factors, including the timing of the arbitration request, if dispositive motions have been filed, and/or if a litigant is unfairly manipulating the judicial system by attempting to obtain a second bite at the apple due to an unfavorable ruling in another forum. See, e.g., JKL Components Corp. v. Insul-Reps, Inc., 596 N.E.2d 945 (Ind.Ct.App.1992) (refusing to *456 compel arbitration as appellant made no effort to specifically request arbitration at any time before appeal), trans. denied; Aetna Cas. & Sur. Co. v. Dalson, 421 N.E.2d 691 (Ind.Ct.App.1981) (holding plaintiffs had waived their right to arbitrate where they had consistently resisted arbitration and only when an unfavorable judgment was entered against them at trial did they seek to compel arbitration); Shahan v. Brinegar, 181 Ind.App. 39, 390 N.E.2d 1036

Free access — add to your briefcase to read the full text and ask questions with AI

Related

JK HARRIS & CO., LLC v. Sandlin
942 N.E.2d 875 (Indiana Court of Appeals, 2011)
Tamko Roofing Products, Inc. v. Dilloway
865 N.E.2d 1074 (Indiana Court of Appeals, 2007)
Safety National Casualty Co. v. Cinergy Corp.
829 N.E.2d 986 (Indiana Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
802 N.E.2d 453, 2003 WL 23193253, Counsel Stack Legal Research, https://law.counselstack.com/opinion/finlay-properties-inc-v-hoosier-contracting-llc-indctapp-2004.