Fineberg v. S & S BUILDING COMPANY INC.
This text of 249 S.W.3d 242 (Fineberg v. S & S BUILDING COMPANY INC.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.
Opinion
ORDER
Daniel R. Fineberg and Lynn M. Fine-berg appeal the judgment entered upon a jury verdict in favor of the builder, S & S Building Co. Inc., in this dispute over a sale contract for a residential villa. The jury found in favor of the builder on both the Finebergs’ breach-of-contract claim for the return of a $25,000 earnest money deposit and on the builder’s counterclaim for damages for the Finebergs’ breach of the sale contract. A written opinion would have no precedential value. We have furnished the parties with a memorandum, for their information only, explaining the reasons for our decision. We affirm the judgment of the trial court. Rule 84.16(b)(5). 1
. We grant the builder’s motion for attorney’s fees on appeal, in the amount of $15,307.50.
Free access — add to your briefcase to read the full text and ask questions with AI
Related
Cite This Page — Counsel Stack
249 S.W.3d 242, 2008 Mo. App. LEXIS 427, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fineberg-v-s-s-building-company-inc-moctapp-2008.