Fields Engineering & Equipment, Inc. v. Cargill, Inc.

651 F.2d 589, 31 Fed. R. Serv. 2d 1280, 1981 U.S. App. LEXIS 12321
CourtCourt of Appeals for the Eighth Circuit
DecidedJune 15, 1981
Docket80-1685
StatusPublished
Cited by34 cases

This text of 651 F.2d 589 (Fields Engineering & Equipment, Inc. v. Cargill, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fields Engineering & Equipment, Inc. v. Cargill, Inc., 651 F.2d 589, 31 Fed. R. Serv. 2d 1280, 1981 U.S. App. LEXIS 12321 (8th Cir. 1981).

Opinion

ARNOLD, Circuit Judge.

Fields Engineering & Equipment, Inc., brought suit against Cargill, Inc., for damages for an alleged breach of a construction contract. Cargill counterclaimed and sought damages, including lost profits. The District Court ruled in favor of Cargill and awarded it $117,578.62. Fields appeals from that decision.

Fields Engineering & Equipment, Inc., is a Texas corporation with its principal place of business in Lubbock, Texas, and is primarily engaged in millwright construction work. Cargill, Inc., is a Delaware corporation with its principal place of business in Minneapolis, Minnesota, and is engaged in grain distribution. In 1975, the parties entered into an agreement for the construction of an overhead conveyor-belt system between two grain-storage facilities owned by Cargill in Clarion, Iowa. Fields had previously performed construction work for Cargill in both Nebraska and Texas.

Fields commenced work on the project on September 1, 1975. Two months later, Fields forwarded its first monthly invoice for payment on the basis of time spent in performance of the job and the cost of materials used in construction, that is, a “time and materials” method of billing. Subsequently, on or about November 19, 1975, a formal written agreement was drafted by Cargill and sent to Fields for approval. Fields Elton Kessler, then presi *591 dent of Fields Engineering, 1 executed the contract and returned it to Cargill. There is no evidence in the record, however, that the contract was ever executed by Cargill. 2

The contract provided, among other items, that work on the project must be commenced by Fields, the contractor, on or before December 1, 1975, and completed no later than August 1, 1976. Time was said to be of the essence of the agreement. The contract further stated that Cargill must pay Fields “for the construction and work to be performed and materials to be furnished” the sum of cost plus 15%, with the total amount in no event to exceed $270,-000. Additionally, the contract gave Cargill the authority to “add to or otherwise alter the construction and work to be performed,” subject, however, to modification of the contract price by written agreement between the parties prior to the commencement of any changes.

A number of changes were made in the project at the request of Cargill, but without any express modification of the contract price. 3 Fields made these changes both before and after the deadline of August 1, 1976. Monthly payment invoices were sent to Cargill that reflected the fact that total billing had greatly exceeded the $270,000 cost limitation of the contract. Fields claims that Cargill raised no objections to the billings. Although assurances had been given to Cargill by Fields’s representative, George Carter, that the project would be completed on time and within the cost limit, Fields continued working on the conveyor system until December 16, 1976. At that time, Cargill ordered Fields to leave the Clarion job site and thereafter hired the Jarvis Construction Company to finish the project, which it did in November, 1977. 4

On February 2, 1978, Fields filed this action seeking $232,612.10 5 in damages for breach of contract. 6 The District Court, however, found that Fields had breached the written contract by failing to complete the construction work properly by the August 1 deadline and by exceeding the cost ceiling of $270,000.00. It further found that Cargill had been damaged in the amount of $37,885.00 paid to Jarvis Construction Company to finish the conveyor-belt system and $136,000.00 in two seasons’ lost profits as a result of delay in completion. Fields was given credit for the amount Cargill owed for work done under the contract and for additional work performed at Cargill’s request. This credit was found to be $56,306.38, reducing Car-gill’s recovery to $117,578.62.

Fields urges three points for reversal: that it was unlawfully denied a trial by jury in this action at law; that the District Court’s findings of fact are insufficient and clearly erroneous; and that the District Court failed to rule on any of plaintiff Fields’s evidentiary objections. In the main, we reject these arguments. We do hold, however, that the award for lost profits was erroneous in part, and the judgment against Fields will be reduced accordingly.

*592 I. Jury Trial

Fields contends that its right to a trial by jury was violated when the case was transferred to a non-jury docket without its consent entered on the record, as required by Fed.R.Civ.P. 39(a). This contention has only its audacity to commend it. Although Fields filed a demand for a jury trial on two separate occasions prior to trial, the record indicates that at the pretrial conference Fields, through its counsel, orally agreed to trial before the court. Under Rule 39(a), the parties or their attorneys may stipulate that trial will be without a jury, even though a jury trial has been previously properly demanded. All parties must consent to the stipulation, which must either be made in a writing filed with the court or, as in the present case, by oral stipulation made in open court and somehow reflected in the record. Wright & Miller, Federal Practice and Procedure: Civil § 2332; see Collins v. Government of the Virgin Islands, 366 F.2d 279, 286 (3d Cir. 1966), cert. denied, 386 U.S. 958, 87 S.Ct. 1026, 18 L.Ed.2d 105 (1967). The pretrial order in this case, to which Fields did not object, recites the waiver of jury trial by the parties during pretrial conference. This is a sufficient entry in the record to satisfy the requirements of Fed.R.Civ.P. 39(a). See General Business Services, Inc. v. Fletcher, 435 F.2d 863 (4th Cir. 1970). It is immaterial that the pretrial conference itself was not on the record. The agreement to waive a jury, made at this conference, was recorded in the pretrial order.

II. The Findings of Fact

Fields asserts that the District Court erred in rendering judgment for Cargill for breach of contract and failed to make sufficient findings of fact and conclusions of law on Fields’s own theories of recovery. We examine the merits of each specific point raised in turn.

A. Contract

The District Court found that the parties had entered into a written contract for the construction of an overhead convey- or-belt system and that appellant Fields had breached the contract by failing to complete the construction work properly by August 1,1976, and by exceeding the cost ceiling of $270,000. Under Fed.R.Civ.P. 52

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Alcoa Inc. v. Alcan Inc.
D. Delaware, 2020
In Re Borowiak IGA Foodliner, Inc.
879 F.3d 848 (Eighth Circuit, 2018)
Residential Funding Co. v. Terrace Mortgage Co.
850 F. Supp. 2d 961 (D. Minnesota, 2012)
Americans Un. for Sep. of Church v. Prison Fellow.
395 F. Supp. 2d 805 (S.D. Iowa, 2005)
Securities & Exchange Commission v. Guenthner
395 F. Supp. 2d 835 (D. Nebraska, 2005)
Goldstein v. Lincoln National Convertible Securities Fund, Inc.
140 F. Supp. 2d 424 (E.D. Pennsylvania, 2001)
Goldstein v. LINCOLN NAT. CONVERTIBLE SEC. FUND
140 F. Supp. 2d 424 (E.D. Pennsylvania, 2001)
Meeks v. Harrah's Tunica Corp. (In Re Armstrong)
260 B.R. 454 (E.D. Arkansas, 2001)
Brian Elkins v. Rex Berry & William Bolin
Court of Appeals of Tennessee, 2001
Highlander Golf, Inc. v. Wal-Mart Stores, Inc.
115 F. Supp. 2d 1157 (D. South Dakota, 2000)
Meeks v. Harrah's Tunica Corp. (In Re Armstrong)
231 B.R. 723 (E.D. Arkansas, 1999)
Kahn v. General Motors Corp.
865 F. Supp. 210 (S.D. New York, 1994)
Tray-Wrap, Inc. v. Six L'S Packing Co., Inc.
984 F.2d 65 (Second Circuit, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
651 F.2d 589, 31 Fed. R. Serv. 2d 1280, 1981 U.S. App. LEXIS 12321, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fields-engineering-equipment-inc-v-cargill-inc-ca8-1981.