Fieldcrest Builders, Inc. v. Antonucci

Procedural entryThis page is a short order in Fieldcrest Builders, Inc. v. Antonucci. Read the opinion of the Court — 311 Ill. App. 3d 597
Appellate Court of Illinois·Decided December 30, 1999·No. 1-98-4337·Published

Opinion

                                                                                       FIFTH DIVISION

                                                                                       December 30, 1999                      

No. 1-98-4337

FIELDCREST BUILDERS, INC.,             ) Appeal from the          

Plaintiff and Appellee and        ) Circuit Court of

Cross-Appellant and               ) Cook County

    Defendant-Counterdefendant,       )  

                                      )

v.                                )

GREGORY ANTONUCCI and                  )

JENINE ANTONUCCI,                      )

Defendants and Appellants and     )

Cross-Appellees and               )

Plaintiffs                        )

(B and D Custom Homes, Inc., and       )    

Mayfair Lumber Company,               ) Honorable  

Intervenors and                   ) Clifford L. Meacham,

    Counterplaintiffs).               ) Judge Presiding.

JUSTICE GREIMAN delivered the opinion of the court:  

This appeal follows a bench trial of consolidated actions in the mechanics' lien section of the circuit court of Cook County.  The controversies arise out of a construction contract between Fieldcrest Builders, Inc., the general contractor, and Gregory and Jenine Antonucci, the homeowners, for the extensive renovation of and addition to their single-family residence in Glenview, Illinois.  B & D Custom Homes, Inc. (B & D), a carpentry subcontractor, and Mayfair Lumber Company (Mayfair), a material supplier, also asserted mechanics' liens.  

On October 16, 1998, the trial court entered judgment in favor of Fieldcrest on its quantum meruit count in the amount of $84,148.25, after allowing setoffs for certain claims of the Antonuccis.  The trial court also allowed the total lien claim of Mayfair and allowed, in part, the lien claim of B & D.  Later, on January 25, 1999, the trial court ordered the Antonuccis to pay costs ($5,673.28) to Fieldcrest.  The Antonuccis then filed the instant appeal and, in turn, Fieldcrest filed a cross-appeal.  

On direct appeal, the Antonuccis raise five issues as to whether (1) the judgment in favor of the general contractor (Fieldcrest) includes the principal amounts claimed by two subcontractors (B & D and Mayfair); (2) the trial court erroneously failed to deduct from Fieldcrest's judgment the $10,000 paid by the Antonuccis when the construction contract was executed; (3) Fieldcrest's quantum meruit damages should exclude the amounts attributed to overhead and general conditions; (4) the trial court erred in not awarding certain alleged remedial and delay damages; and (5) the trial court erred in taxing costs against the Antonuccis.  

For all of the reasons that follow, we remand the matter to the circuit court to find whether the amounts claimed by B & D and Mayfair were included within the amount awarded to Fieldcrest and to determine whether it failed to credit the Antonuccis in the amount of $10,000, i.e. , the amount paid at the time the parties entered into the contract.  We affirm the trial court's order relating to the damages awarded to Fieldcrest for overhead and general conditions.  We affirm the trial court's decision as to the amount of remedial damages awarded to the Antonuccis and the denial of damages for delay.  We reverse the order awarding costs to the Antonuccis.       

On cross-appeal, Fieldcrest asserts that the trial court erred in denying its claim for a mechanic's lien, failing to award attorney fees under section 17 of the Illinois Mechanic's Lien Act (Act)  (770 ILCS 60/17 (West 1994)), and denying its motion for reconsideration for leave to file an amended complaint against Roxanne Malo, alleging tortious interference with contract.  We affirm all of the trial court's rulings challenged by Fieldcrest.

In addition, B & D filed a separate brief in this appeal to assert that the Antonuccis waived any issue regarding the validity of the money judgment or mechanic's lien in favor of B & D because the Antonuccis failed to argue the efficacy of B & D's awards in their appellate brief.  In its brief, B & D thoroughly detailed the arguments and issues presented by the Antonuccis on appeal, none of which challenge the efficacy of the awards to B & D.  Accordingly, the Antonuccis have waived the issue on appeal pursuant to Supreme Court Rule 341(e)(7) (177 Ill. 2d R. 341(e)(7)), which mandates that "[p]oints not argued are waived and shall not be raised in the reply brief, in oral argument, or on petition for rehearing."

From March 1993 through May 1994, the Antonuccis prepared to have extensive renovations done on their home.  Preparations included the hiring of an architect to draw up the plans, the submission of bids by contractors, the modification of the plans to meet the approval of the village, applying for and obtaining building permits from the village, obtaining a construction loan with Harris Bank, and establishing a construction loan escrow trust and disbursing agreement with Chicago Title Insurance Company.  Eventually, on April 2, 1994, the Antonuccis and Fieldcrest entered into a building construction agreement in the amount of $846,978.  The work was to commence in May 1994 and be completed by March 1995.

On May 2, 1994, after vacating their home, the Antonuccis delivered their house to Fieldcrest for commencement of the project.  Throughout the course of the project, problems and concerns developed between Fieldcrest and the Antonuccis.  Ultimately, on August 20, 1994, the Antonuccis gave notice to terminate the contract based upon Fieldcrest's alleged breach of the contract, including substandard construction work, lack of proper insurance and failure to maintain a clean and environmentally safe jobsite.  On August 22, 1994, Fieldcrest ceased work on the project.  Subsequently, the Antonuccis hired another general contractor to complete the project and remediate the allegedly defective work done by Fieldcrest.  

Fieldcrest's position regarding the problems encountered on the project was that the drawings and specifications for the project contained deficiencies, inaccuracies and incomplete areas.  Errors, such as improper dimensions, caused the architect and others to visit the project site on numerous occasions to resolve the problems and resulted in additional labor and time on the part of Fieldcrest.  Fieldcrest also maintained that the deficiencies of the drawings, the delays by the Antonuccis in making certain decisions, and the numerous additional changes made by the Antonuccis increased the costs of the project.  

The Antonuccis maintained that Fieldcrest was to blame for the problems on the project, arguing in general that Fieldcrest's workmanship was poor and its performance was deficient.

Free access — add to your briefcase to read the full text and ask questions with AI

Fieldcrest Builders, Inc. v. Antonucci, (Ill. Ct. App. 1999).

Fieldcrest Builders, Inc. v. Antonucci (Fieldcrest Builders, Inc. v. Antonucci) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

J.R. Sinnott Carpentry, Inc. v. Phillips
443 N.E.2d 597 (Appellate Court of Illinois, 1982)
Contract Development Corp. v. Beck
627 N.E.2d 760 (Appellate Court of Illinois, 1994)
Mani Electrical Contractors v. Kioutas
611 N.E.2d 1167 (Appellate Court of Illinois, 1993)
In Re Marriage of Plymale
526 N.E.2d 882 (Appellate Court of Illinois, 1988)
Hirsch v. Feuer
702 N.E.2d 265 (Appellate Court of Illinois, 1998)
Comet Casualty Co. v. Schneider
424 N.E.2d 911 (Appellate Court of Illinois, 1981)
Ambrose v. Biggs
509 N.E.2d 614 (Appellate Court of Illinois, 1987)
Grund v. Donegan
700 N.E.2d 157 (Appellate Court of Illinois, 1998)
Folk v. Central National Bank & Trust Co.
567 N.E.2d 1 (Appellate Court of Illinois, 1991)
R.W. Dunteman Co. v. C/G Enterprises Inc.
692 N.E.2d 306 (Illinois Supreme Court, 1998)
Premier Electrical Construction Co. v. American National Bank
658 N.E.2d 877 (Appellate Court of Illinois, 1995)
Oakleaf v. Oakleaf & Associates, Inc.
527 N.E.2d 926 (Appellate Court of Illinois, 1988)
Meade v. Kubinski
661 N.E.2d 1178 (Appellate Court of Illinois, 1996)
In Re Marriage of Breslow
713 N.E.2d 642 (Appellate Court of Illinois, 1999)
Evans and Associates, Inc. v. Dyer
615 N.E.2d 770 (Appellate Court of Illinois, 1993)
Mor-Wood Contractors, Inc. v. Ottinger
562 N.E.2d 1247 (Appellate Court of Illinois, 1990)
Delaney Elec. Co., Inc. v. Schiessle
601 N.E.2d 978 (Appellate Court of Illinois, 1992)
Koester v. Huron Development Co.
185 N.E.2d 196 (Illinois Supreme Court, 1962)