Field v. BOARD OF WATER COMMISSIONERS

804 F. Supp. 2d 1160, 2011 U.S. Dist. LEXIS 37085, 2011 WL 1119893
CourtDistrict Court, D. Colorado
DecidedMarch 28, 2011
DocketCivil Action 09-cv-02247-ZLW-MEH
StatusPublished
Cited by1 cases

This text of 804 F. Supp. 2d 1160 (Field v. BOARD OF WATER COMMISSIONERS) is published on Counsel Stack Legal Research, covering District Court, D. Colorado primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Field v. BOARD OF WATER COMMISSIONERS, 804 F. Supp. 2d 1160, 2011 U.S. Dist. LEXIS 37085, 2011 WL 1119893 (D. Colo. 2011).

Opinion

ORDER

ZITA LEESON WEINSHIENK, Senior District Judge.

The matter before the Court is the Motion For Summary Judgment filed by Defendant Board of Water Commissioners, City and County of Denver (Denver Water or Defendant) (Doc. No. 51). The Court has reviewed carefully the moving and responding papers and the applicable legal authority.

I. Background

Plaintiff Bruce R. Field worked for Denver Water as a Construction Project Manager from October 2002 until he was terminated in October 2008. Starting in 2007, Plaintiff began making allegations of fraud and criminal conduct in connection with the contracting process on three construction projects at Denver Water. Plaintiffs supervisors repeatedly requested that Plaintiff provide substantiation for his allegations, but Plaintiff failed to do so. He continued to assert fraud and wrongdoing in the contracting process, and refused to authorize project payments, placing Denver Water at risk of legal claims by the project contractors. On October 13, 2008, Denver Water Director of Engineering Robert Mahoney terminated Plaintiff on the basis that Plaintiff had failed to perform his job duties, was insubordinate, and had engaged in conduct that resulted in a material impairment of his work and the work of his supervisors and co-workers.

Plaintiffs Amended Complaint pleads three claims for relief stemming from his employment with and termination by Denver Water: a first claim for “Retaliation— First Amendment,” a second claim for “Retaliation — § 1981,” and a third claim for “Retaliation — Title VII.” The following facts are undisputed for purposes of this motion, except where noted.

A. Facts Pertaining to First Claim for Relief for “Retaliation — First Amendment”

1. Official Duties

Plaintiff Bruce R. Field was hired by Denver Water as a Construction Project Manager II on October 7, 2002. On January 13, 2007, Plaintiff was promoted to Construction Manager III (CPM III or CPM). 1 As a CPM III, Plaintiff was responsible for “advanced field and key administrative construction engineering duties, handling complex problems relating to all types of projects in the areas of inspection, construction, project coordination and schedule, contract interpretation and negotiation, and approval of change orders.” 2 His duties included: “managing and coordinating major and complex project construction work and related administrative matters, to include arranging and scheduling for support work,” “ensuring that contractor adheres to intent of contract documents and completes project in a timely manner,” “[sjupervises assigned personnel, and ensures proper field per *1163 formance though personal observation and contractor contact; accomplishes liaison function” and “[g]ives expert interpretation of construction aspects of engineering designs, specifications and related contract documents in group and individual settings.” 3 He was, further, “Responsible for ensuring preparation of a variety of technical reports, correspondence and calculations, and sees that project records are maintained.” 4

Plaintiffs supervisor throughout his employment at Denver Water was Chief of Construction Management Michael Leister. Leister reported to Robert Mahoney, and Mahoney reported to the Manager of Denver Water. The Manager answers to the Board of Water Commissioners, whose members are appointed by the Mayor of Denver. 5 The Auditor of the City and County of Denver (Denver Auditor) signs all Denver Water warrants and countersigns all Denver Water agreements. 6

2. Communications

Plaintiff was the CPM several projects, including the Montclair Pump Station Project (Montclair Project), the Capitol Hill Water Tank Project (Capitol Hill Project), and the Foothills Treatment Plant Project (Foothills Project). Lillard & Clark Construction (Lillard & Clark) was the contractor on the Montclair Project, and Garney Construction (Garney) was the contractor on the Capitol Hill Project and the Foothills Project. During his tenure as CPM III on these projects, Plaintiff became concerned about various aspects of the terms and administration of the projects’ construction contracts. Plaintiff expressed his concerns in numerous communications, including the following: 7

(1) On May 25, 2007, Plaintiff sent an email to Mahoney commenting on an email that Leister had sent to Plaintiff and others summarizing what had been decided at a meeting earlier that day concerning payment understandings on the Capitol Hill Project and Foothills Project. Plaintiff stated, among other things, that he has not agreed to “the questionable spreadsheet error,” that he believed that Garney’s markup was not reasonable, and that Garney was attempting to “gain additional compensation.” 8

(2) On June 2, 2007, Plaintiff contacted Breckenridge Grover of the Denver Auditor’s Office by telephone and told him that he “had concerns about the three projects, regarding the costs, contracts and other issues.” 9

(3) On July 17, 2008, Plaintiff was contacted by Grover and Dennis Gallagher of the Denver Auditor’s Office by telephone. Plaintiff told Gallagher that although he had contacted Grover on June 7, he had not heard back from him. Gallagher said that he had called Denver Water and that everything was straightened out. Plaintiff responded that nothing was straightened out and asked him whom he had spoken with and what actions were taken. Gallagher told Plaintiff to “send us an email with your concerns.” 10

*1164 (4) On July 18, 2008, Plaintiff wrote an email to Grover listing concerns that Plaintiff had “[r]egarding the three current Denver Water CM/GC 11 construction contracts.” His concerns included questions regarding how the contractors on the projects were chosen, who approved the contract documents, how the estimates and profit percentages were determined, and why Denver Water allowed the contractor on the Capitol Hill Project to submit unauthorized overhead costs. Plaintiff stated, “[f]rom my review, these decisions by DW Engineering Managers have allowed the two contractors to gain unearned compensation of potentially over $6.0 million. More detailed specific concerns of each project ean/will be supplied.” He went on to state, “[gjiven the magnitude of this problem, I feel it is appropriate to have an announcement of this issue from your office or the Mayor’s. I don’t feel ‘keeping this quiet’ is the best course of action”. 12

(5) On July 21, 2008, Plaintiff emailed Grover, asking him if his office would be investigating Plaintiffs concerns.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Laul v. L. Alamos Nat'l Labs.
309 F. Supp. 3d 1119 (D. New Mexico, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
804 F. Supp. 2d 1160, 2011 U.S. Dist. LEXIS 37085, 2011 WL 1119893, Counsel Stack Legal Research, https://law.counselstack.com/opinion/field-v-board-of-water-commissioners-cod-2011.