Fidelity & Deposit Company of Maryland

CourtArmed Services Board of Contract Appeals
DecidedJune 21, 2022
DocketASBCA No. 63056
StatusPublished

This text of Fidelity & Deposit Company of Maryland (Fidelity & Deposit Company of Maryland) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Company of Maryland, (asbca 2022).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS Appeal of - ) ) Fidelity & Deposit Company of Maryland ) ASBCA No. 63056 ) Under Contract No. W912ER-11-D-0010-0006 )

APPEARANCES FOR THE APPELLANT: Robert C. Niesley, Esq. Rebecca S. Glos, Esq. Watt, Tieder, Hoffar & Fitzgerald, L.L.P. Irvine, CA

APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq. Engineer Chief Trial Attorney Rebecca L. Bockmann, Esq. Michael E. Taccino, Esq. Engineer Trial Attorneys U.S. Army Engineer District, Middle East Winchester, VA

OPINION BY ADMINISTRATIVE JUDGE SMITH ON GOVERNMENT’S MOTION TO DISMISS FOR LACK OF JURISDICTION

This appeal arises from the same task order contract, and presents the same legal issue, as Appeal No. 63052 which we recently dismissed for lack of jurisdiction. As with Appeal No. 63052, respondent (the government) moves to dismiss for lack of jurisdiction, saying that appellant, Fidelity and Deposit Company of Maryland (F&D), has no standing because F&D was not in privity with the government, and therefore was not a “contractor” per the Contract Disputes Act, when F&D’s claim accrued between 2014 and early 2016. For similar reasons as in Appeal No. 63052, we agree with the government and dismiss the appeal.

STATEMENT OF FACTS FOR PURPOSES OF THE MOTION

In 2013, the government contracted with ECC CENTCOM (ECC) under fixed-price task order Contract No. W912ER-11-D-0010-0006 (the Contract) for design and construction of U.S. Navy housing quarters in Bahrain (R4, tab 5). Between August 2014 and February 2015, the parties disagreed over whether the contract required ECC to install floor drains in guest room bathrooms (R4, tab 16, comment number 5758126, 1-0 to 5-0; tab 8). ECC installed the bathroom floor drains between January 14 and February 15, 2015 (R4, tab 14 at 46, 50, 54, 58, 62, 66, 70, 74, 78, 84, 104, 118, 136). If not already clear from its earlier disagreements with the government, on February 23, 2015, after performing the work, ECC wrote that it was entitled to an equitable adjustment for installing the floor drains (R4, tab 8). On March 23, 2016, ECC submitted a request for equitable adjustment (REA) under the Contract’s changes clause seeking $122,255 for the allegedly changed work (R4, tab 9).

Subsequent to ECC’s REA, on April 19, 2016, the government terminated ECC for default (R4, tab 17). ECC’s surety, F&D, arranged to complete the project and executed a takeover agreement with the government on July 19, 2016 (R4, tab 6). The takeover agreement provided:

For purposes of completion of the Contract, except as may otherwise be provided in this Agreement, Surety is entitled to all rights, title, and interest of Principal in and to the Contract in all respects as if Surety were the original party to the Contract. Further, except as to the extent provided in this Agreement, the Government shall have all rights, obligations, and responsibilities under the Contract with respect to the Surety, to the same extent and effect as if Surety had executed the Contract initially instead of the Principal, as if the Principal’s rights pursuant to the Contract terms had not been terminated.

(Id. ¶ 1) ECC was not a party to the takeover agreement. Id.

On August 30, 2016, the government requested additional information from ECC (not F&D or F&D’s completion contractor, Vertex, though they were aware of the request) to consider ECC’s March 23, 2016, REA (R4, tab10). ECC never responded. Instead, on November 17, 2016, seven months after ECC’s REA and six months after ECC’s termination, Vertex resubmitted ECC’s REA verbatim (and without responding to the government’s August 30, 2016 request), but Vertex withdrew the REA the same day (R4, tabs 11-12).

A year and a half later, on February 26, 2018, Vertex again resubmitted ECC’s REA but with a lower total amount ($114,302.88 instead of $122,255.31) caused by deleting some costs to which the government had objected in its August 2016 response to ECC (R4, tab 13). On April 2, 2019, the government found “full merit” to Vertex’s resubmission of ECC’s REA, but the government never

2 issued a contract modification to implement the change (app. supp. R4, tab 22).

Another two years passed before March 24, 2021, when F&D submitted ECC’s REA for “the additional Guest Bathroom Floor Drains” yet again, but this time as a certified claim (R4, tab 2). F&D’s certified claim alleged the same contract change and sought the same costs as Vertex’s 2018 REA and ECC’s 2016 REA, but deleted one small cost item for a total claim of $113,170.88. Id. On September 21, 2021, the government declined to issue a contracting officer’s final decision (COFD) because F&D was not the contractor (i.e. F&D did not have privity with the government) when the claim arose in 2014-2016 (R4, tab 3). F&D timely appealed to the Board on October 1, 2021 (R4, tab 1).

DECISION

It is the responsibility of F&D, as appellant, to establish the Board’s jurisdiction. Hellenic Air Force, ASBCA No. 60802, 17-1 BCA ¶ 36,821 at 179,457. Standing to bring an appeal before the Board is founded upon privity of contract with the government. See Peerless Ins. Co., ASBCA No. 28887, 88-2 BCA ¶ 20,730 at 104,738. Moreover, the scope of the Board’s jurisdiction is determined by the contents of the claim submitted to the contracting officer. IBM Corp., ASBCA No. 60332, 18-1 BCA¶ 37,002 at 180,190. “The facts supporting jurisdiction are subject to our fact-finding upon a review of the record.” CCIE & Co., ASBCA Nos. 58355, 59008, 14-1 BCA ¶ 35,700 at 174,816.

Regardless of the small differences in total claimed costs between the three previously submitted REAs (first from ECC then two from Vertex) and F&D’s certified claim, the basis of the alleged change has always been the government’s 2014 orders for ECC to install guest bathroom floor drains, ECC’s installation of those drains in early 2015, and costs set forth in ECC’s March 23, 2016, REA which have been adjusted marginally downward since then. The alleged changes to the contract, and performance of the changed work, occurred when ECC was the contractor, before ECC’s termination, before F&D’s takeover agreement with the government, before Vertex performed any work, and before F&D incurred any costs to complete the contract or to pay subcontractor invoices. It is and always has been ECC’s claim, even when Vertex and F&D tried to rebrand it as their own.

F&D points to the language in the takeover agreement (app. opp’n at 7), which provides that F&D is entitled to rights and interest of ECC “as if Surety were the original party to the Contract . . . [and] had executed the Contract initially instead of [ECC]” (R4, tab 6 ¶ 1). However, without participation of the original contractor (and, as found above, ECC was not a party to the takeover agreement), a takeover agreement cannot assign the original contractor’s claims to a surety to confer standing under the Contract Disputes Act. United Pac. Ins. Co., ASBCA No. 52419, 3 01-1 BCA ¶ 31,296 at 154,509. This is a critical difference with Safeco Ins. Co. of America, ASBCA No. 52107, 03-2 BCA ¶ 32,341, relied on by F&D, where the terminated contractor and the surety executed an explicit assignment of claims.

Because F&D was not yet in privity with the government when the claim arose and matured (no later than ECC’s REA of March 23, 2016), F&D has no standing to assert ECC’s claim and the Board does not possess jurisdiction to entertain F&D’s appeal of the government’s denial of F&D’s attempt to assert ECC’s claim. See United Pac., 01-1 BCA ¶ 31,296 at 154,507.

F&D also relies upon conflicting, unsupported and ultimately self-defeating factual assertions.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
Fidelity & Deposit Company of Maryland, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-company-of-maryland-asbca-2022.