Fidelity & Deposit Co. v. United States

103 Ct. Cl. 340, 1945 U.S. Ct. Cl. LEXIS 39, 1945 WL 4030
CourtUnited States Court of Claims
DecidedApril 2, 1945
DocketNo. 44010
StatusPublished

This text of 103 Ct. Cl. 340 (Fidelity & Deposit Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. United States, 103 Ct. Cl. 340, 1945 U.S. Ct. Cl. LEXIS 39, 1945 WL 4030 (cc 1945).

Opinion

Littleton, Judge,

delivered the opinion of the court:

The Yang Construction Company, herein referred to as the contractor, entered into a unit-price contract with defendant dated November 9, 1932, for the construction of a lock and dam across the Allegheny River about five miles from Pittsburgh, Pennsylvania. Eight items involving a powerhouse, lock machinery, and other machinery and equipment were lump-sum items. All others were unit-price items. The estimated contract price based on these lump-sum items and other estimated quantities for the unit-price items was $1,190,251.48. The contractor’s bid, which was accepted, was submitted October 14, and prior to October 24, 1932, it was advised by defendant that the contract had been awarded to it. The contractor, with the consent of defendant, began construction operations under the specifications and drawings October 24,1932, and, subsequent to November 9, signed the formal contract and furnished a performance bond on which plaintiff was surety. The contract was signed and the bond approved by defendant December 6, and the contractor received formal notice to proceed on the following day, December 7, 1932. This fixed the completion date, for a period of 450 days, as March 1st, 1934.

While the contractor was continuing with the work a receivership proceeding was filed against it July 11,1934, and, on the same date, the U. S. District Court for the Western District of Pennsylvania appointed receivers for the contractor. Under authority given by this decree the receivers on July 13 elected to disaffirm the contract between The Vang Construction Company and the defendant and notified the contracting officer of their refusal to accept the contract and proceed with its completion. Thereupon, and on the same day, the plaintiff, as surety on the contractor’s performance bond, entered into a supplemental contract with the Govern[371]*371ment and tbe receivers of Tbe Vang Construction Company, which contract provided that the surety would take over and complete the work under and in accordance with the original contract, receive semi-monthly payments from the Government for all earned estimates for work performed by it under the original contract, and “that in the event the Fidelity and Deposit Company of Maryland sustains a loss in the completion of the work it shall receive payment to the extent thereof from any amounts earned by The Vang Construction Company not heretofore paid to the contractor, if any, after all claims of the United States against the contractor have been satisfied.”

In completing the contract work plaintiff used substantially the contractor’s organization, including its employees and laborers, and expended $138,301.38 for such completion. In addition plaintiff paid $156,145.56 for material and labor claims against the contractor which had accrued at the time of appointment of the receivers. These two amounts total $294,446.94.

During and upon completion plaintiff received from the Government progress payments for contract work performed by it in amounts totaling $78,270.96. This amount included $15,114.72 allowed but not paid to the contractor on progress estimate no. 23. On the final payment voucher plaintiff also received $88,671.80 representing the total of the retained percentages due after deduction by defendant of $16,042.92 for liquidated damages for 53.5 days’ delay. The total of the amount so paid to plaintiff by defendant was $166,942.67. The sum of $50,000 of the retained percentage of $88,671.80 above-mentioned represents amounts withheld by defendant from prior progress payments earned by and paid to the contractor. In addition to the amount of $166,942.67 received from the Government upon completion of work, plaintiff also received from the contractor $98,216. The total of the amounts which plaintiff received from the Government and the contractor was $265,068.76, and inasmuch as plaintiff had paid out for completion of the contract work and on material and labor claims against the contractor a total of $294,446.94, its loss was $29,378.18. The total paid plaintiff [372]*372by defendant under the terms of the original contract and the supplemental agreement of July 13, 1934, was $28,641.29 in excess of the amount expended by plaintiff in completing the work. However, under the terms of the performance bond and the supplemental agreement of July 13, to which the re-, ceivers were also parties, plaintiff upon completion of the work in October 1934 became subrogated to all rights of the contractor and the receivers under the original contract. The supplemental agreement did not amount to an assignment by the receivers of a claim against the Government within the meaning of sec. 3477 of the Devised Statutes, and on November 4,1936, prior to institution of this suit, the receivers, with approval of the court, distributed and returned to The Yang Construction Company all assets of every kind then remaining in their hands, and they were discharged. This action of the receivers included the return to the contractor of any claim which they, as receivers for the company, or the contractor may have had against the United States, under the contract of November 9, 1932.

The first item of the claim is $8,143.88 for alleged excess cost of reconstructing the first of two concrete caissons which the contractor, with the consent of defendant, elected to use as the foundation for the abutment of the dam. The reconstruction cost was $6,013.34 (finding 19). The proof does not show that rebuilding of this caisson delayed the final completion of the contract work.

The specifications and original plans required the contractor to build a cofferdam around the area of the foundation for the abutment and, after pumping the area dry, to construct the concrete foundation. However the contractor proposed the caisson method and asked permission to use it. This permission was granted by change order no. 1 which authorized the contractor at its own expense and risk (finding 8) to use two caissons, each 75 feet long, 28 feet wide, and 30 feet high, with walls and three partitions 8 feet thick above the working chamber. The change order specifically provided that the contractor would be responsible for the construction and the sinking of the caissons and that “any [373]*373caisson which is damaged before landing and seating on bed rock, or is otherwise unsuitable for serving its purpose as a foundation for the abutment wall, will be removed and replaced or repaired to the satisfaction of the contracting officer.” The provisions of the specifications relating to concrete were made applicable to the caissons (finding 11). The work of constructing the two caissons, known as the downstream and upsteam caissons, proceeded simultaneously, but operations on the first, or downstream, caisson were carried on ahead of those for the other one: the two caissons were built adjacent to each other. The pouring of concrete for the downstream caisson was commenced November 24 and was completed November 29, 1932; and that for the upstream caisson was commenced November 30 and was completed December 2, 1932. The same concrete mix was used in both caissons and such concrete was poured under the same conditions and the same instructions of defendant’s inspector. The forms were removed from the first caisson December 3, 1932, and it was allowed to cure until December 7 when the work of removing blocking, or cribbing, and excavating for the sinking of this caisson was commenced.

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
103 Ct. Cl. 340, 1945 U.S. Ct. Cl. LEXIS 39, 1945 WL 4030, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-united-states-cc-1945.