Fidelity & Deposit Co. v. Olney Associates, Inc.

530 A.2d 1, 72 Md. App. 367, 1987 Md. App. LEXIS 378
CourtCourt of Special Appeals of Maryland
DecidedSeptember 3, 1987
Docket1428, September Term, 1986
StatusPublished
Cited by4 cases

This text of 530 A.2d 1 (Fidelity & Deposit Co. v. Olney Associates, Inc.) is published on Counsel Stack Legal Research, covering Court of Special Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Fidelity & Deposit Co. v. Olney Associates, Inc., 530 A.2d 1, 72 Md. App. 367, 1987 Md. App. LEXIS 378 (Md. Ct. App. 1987).

Opinion

JAMES S. GETTY, Judge.

William L. Griffith and Company, Inc., (Griffith) and Fidelity Deposit Company of Maryland (Fidelity) have appealed from a judgment entered in favor of Olney Associates, Inc., (Olney) following a jury trial in the Circuit Court for Montgomery County. Olney has filed a cross-appeal alleging that the trial judge (Beard, J., presiding) erred in granting partial summary judgment to the appellants thereby restricting the damages claimed by Olney. The case was a contract action arising from a one count declaration filed on July 28, 1984, by Olney against Fidelity and Griffith.

*370 Facts

On September 1, 1982, Olney entered into a written contract with Griffith for construction of 34 office units in Montgomery County, Maryland. Fidelity furnished a performance bond and a labor and material payment bond. The contract dated September 1,1982, contained a provision for damages for delay in performance of $400 per day commencing on April 1, 1983.

A dispute arose between Olney and Griffith when Olney refused to pay Griffith any further money until the job was completed. On November 16, 1983, Griffith filed an action to enforce a mechanic’s lien claim and a separate action to enjoin occupancy; on June 28,1984, Olney sued Griffith and Fidelity on a breach of contract theory.

In February of 1984, Olney and Griffith entered into a subsequent agreement to settle the litigation. Although Fidelity was not a party thereto, the agreement nonetheless provided that it was not the intent of the parties to release Fidelity from its liability. Pursuant to the terms of the February agreement, Olney agreed to pay Griffith upon execution of the agreement the sum of $108,375.00 and Griffith agreed to complete the items remaining on a punch list. 1 The sum of $10,000.00 of the total amount due Griffith was placed in escrow by agreement of the parties to be released upon certification by an engineering firm selected by the parties that the work had been completed.

The record indicates that after receiving the $98,375.00 Griffith did not complete the work or request a final inspection to obtain release of the $10,000.00 held in escrow. At the conclusion of the trial, the jury returned a verdict in favor of Olney against both Griffith & Fidelity in the sum *371 of $71,850.33, representing the cost of completing the project. Not submitted to the jury was whether Olney was entitled to damages for delay pursuant to the terms of the original contract dated September 1, 1982, which involved an additional claim for $55,600.00, and whether Olney was entitled to an additional $49,192.08 for units it was unable to sell because of construction problems, mainly water damage.

Prior to trial, Griffith and Fidelity filed a motion for partial summary judgment seeking to limit Olney’s claim to the cost of completion of the project in accordance with the terms of the substituted agreement. The trial court (Messite, J.) granted the motion as to Griffith, but denied it as to Fidelity. Thus, the case proceeded to trial on Olney’s claim against Griffith for failure to complete construction and against Fidelity for both failure to complete the project and for damages for delay under the original contract. 2 Prior to submission of the case to the jury, Fidelity’s motion for partial summary judgment was renewed and granted by the trial court. Olney, therefore, was precluded from seeking delay damages provided for in *372 the original contract. Recovery was limited to the cost of completion of construction, i.e., the punch list attached to the substituted contract. The jury determined these costs to be $71,850.33 and judgment was entered for that amount. Appellants’ motion for new trial and remittitur was denied.

On appeal, appellants allege that the following evidence should not have been admitted:

1. Evidence regarding the original contract dated September, 1982;
2. Evidence that the contractor had not paid its subcontractors;
3. Evidence of work for which subcontractors were paid by a company other than appellant’s;
4. Two self serving letters written by agents of Olney; and
5. Testimony of a witness not identified prior to trial.

On cross-appeal Olney asks us to consider whether it was entitled to damages for delay pursuant to the terms of the the original contract, dated September 1, 1982, amounting to $104,792.08.

I. Evidentiary Issues

We shall combine the evidentiary issues presented by appellants. These contentions will be considered in light of the well settled principle that the admission or exclusion of evidence is a function of the trial court which, on appeal, is traditionally viewed with great latitude. Fleming v. Prince George’s County, 277 Md. 655, 358 A.2d 892 (1976). Moreover,

[f]or an item of evidence to be admissible, it must be both relevant and material. Evidence is material if it tends to establish a proposition that has legal significance to the litigation. Evidence is relevant if it is sufficiently probative of a proposition that, if established, would have legal significance to the litigation, (citation omitted).

*373 Paige v. Manuzak, 57 Md.App. 621, 632, 471 A.2d 758 (1984). See also Schear v. Motel Management Corp., 61 Md.App. 670, 487 A.2d 1240 (1985).

In the case sub judice, the trial judge did not grant appellants’ Motion for Judgment as to Fidelity until the close of all the evidence. Therefore, the issue of whether Olney was entitled to damages for delay from Fidelity pursuant to the September 1, 1982, contract remained before the jury until the granting of that motion. Because the September 1, 1982, contract was before the jury until the granting of appellants’ motion for partial summary judgment at the close of the trial, it is elementary that the initial contract and matters relating to it were relevant and material until appellants’ motion was granted at the close of all the evidence. We hold that the trial judge did not abuse his discretion in permitting testimony relating to either the September 1, 1982, contract or regarding the fact that money Griffith owed its subcontractors pursuant to this contract had been paid by a company other than Griffith.

In so holding we observe that any prejudice claimed by appellants was mitigated by the trial judge’s curative instruction on this matter:

The agreement that you are to consider in this case is what has been referred to throughout this entire trial as the settlement agreement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chicago Title Insurance v. Lumbermen's Mutual Casualty Co.
707 A.2d 913 (Court of Special Appeals of Maryland, 1998)
Merling v. Merling
633 A.2d 403 (Court of Special Appeals of Maryland, 1993)
Eagle-Picher Industries, Inc. v. Balbos
578 A.2d 228 (Court of Special Appeals of Maryland, 1990)
Hauswald Bakery v. Pantry Pride Enterprises, Inc.
553 A.2d 1308 (Court of Special Appeals of Maryland, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
530 A.2d 1, 72 Md. App. 367, 1987 Md. App. LEXIS 378, Counsel Stack Legal Research, https://law.counselstack.com/opinion/fidelity-deposit-co-v-olney-associates-inc-mdctspecapp-1987.